0001203-01-00100General Excavation CUYD700
0002203-07-00100Borrow (Vehicular Measurement) CUYD700
0003203-08-00100Geotextile Fabric SQYD100
0004303-03-00400In-Place Cement Treated Base Course (12" Thick) SQYD7,018.1
0005304-05-00100Lime Treatment (Type E) SQYD500
0006401-02-00100Aggregate Surface Course (Adjusted Vehicular Measurement) CUYD137
0007502-01-00100Asphalt Concrete TON1,828.5
0008502-01-00200Asphalt Concrete, Drives, Turnouts and Miscellaneous TON74
0009509-01-00100Milling Asphalt Pavement SQYD6,774
0010509-02-00100Contractor Retained Reclaimed Asphalt Pavement CUYD-442
0011510-01-00200Pavement Patching (12" Minimum Thickness) SQYD120
0012702-04-00200Adjusting Catch Basins EACH1
0013713-01-00100Temporary Signs and Barricades LUMP1
0014713-02-00500Temporary Pavement Markings (24" Width) LNFT25
0015713-03-01000Temporary Pavement Markings (Broken Line) (4" Width) (4' Length) MILE0.471
0016727-01-00100Mobilization LUMP1
0017731-02-00100Reflectorized Raised Pavement Markers EACH125
0018732-01-01080Plastic Pavement Striping (24" Width) (Thermoplastic 90 mil) LNFT25
0019732-02-02000Plastic Pavement Striping (Solid Line) (4" Width) (Thermoplastic 90 mil) MILE0.942
0020732-03-02000Plastic Pavement Striping (Broken Line) (4" Width) (Thermoplastic 90 mil) MILE0.471
0021740-01-00100Construction Layout LUMP1