Line Number | Item | Description | Unit | Quantity |
0001 | 203-05-00100 | Excavation and Embankment | LUMP | 1 |
0002 | 204-02-00100 | Temporary Hay Bales | EACH | 780 |
0003 | 204-06-00100 | Temporary Silt Fencing | LNFT | 923 |
0004 | 401-02-00100 | Aggregate Surface Course (Adjusted Vehicular Measurement) | CUYD | 165 |
0005 | 713-01-00100 | Temporary Signs and Barricades | LUMP | 1 |
0006 | 713-11-00100 | Portable Changeable Message Signs | EACH | 4 |
0007 | 716-01-00100 | Mulch (Vegetative) | TON | 156 |
0008 | 717-01-00100 | Seeding | LB | 6,240 |
0009 | 718-01-00100 | Fertilizer | LB | 78,000 |
0010 | 727-01-00100 | Mobilization | LUMP | 1 |
0011 | 740-01-00100 | Construction Layout | LUMP | 1 |
0012 | NS-704-00001 | High Tension Cable Barrier | LNFT | 226,983 |
0013 | NS-704-00002 | Cable Barrier Gated End Terminal | EACH | 104 |
0014 | NS-704-00003 | Concrete Strip | SQYD | 100,168.1 |