Projects Under Construction

District 05

    Updated 20 Mar 2025

Districtwide Projects

East Carroll Parish

Note: The estimated completion date is based on the work order date and the contract
days allowed. Unavoidable contingencies and unforeseen events often develop during construction, which may impact the actual completion date.

Joes Bayou & Carraway Lake Bridges
H.001961.6 - New location/replacement of bridge
Proj. Engr: Zzzz Fleming, Douglas Route: LA 134 map
Contractor: Louisiana Bridge, Inc. Miles: 0.99
Work Order Date Contract Amount Estimated Completion Date
2022-11-18 $6,413,746 Spring of 2025


Lincoln Parish

Note: The estimated completion date is based on the work order date and the contract
days allowed. Unavoidable contingencies and unforeseen events often develop during construction, which may impact the actual completion date.

US 80 Overpass @ Kcs RR
H.000133.6 - New location/replacement of bridge
Proj. Engr: Jantz, Matt Route: US 80 map
Contractor: Wl Bass Construction Inc. Miles: 0.34
Work Order Date Contract Amount Estimated Completion Date
2020-09-20 $8,103,469 Summer of 2024


Ruston Downtown Revitalization Phase 6
H.009746.6 - Sidewalks/bike paths
Proj. Engr: Smith, Jody Route: LA 150 US 80 map
Contractor: Amethyst Construction, Inc. Miles: 0.20
Work Order Date Contract Amount Estimated Completion Date
2021-12-03 $5,003,084 Spring of 2025


I-20: Bienville P/L - 0.71 Mile W La 149
H.011627.6 - Asphalt overlay of asphalt pavement
Proj. Engr: Gauthier, William Route: I-20 map
Contractor: Diamond B Construction Co., L. Miles: 9.22
Work Order Date Contract Amount Estimated Completion Date
2025-03-05 $17,968,396 Fall of 2027


LA 818: Barnet Springs & Creek Bridges
H.014238.6 - New location/replacement of bridge
Proj. Engr: Jantz, Matt Route: LA 818 map
Contractor: Diamond B Construction Co., L. Miles: 0.30
Work Order Date Contract Amount Estimated Completion Date
2025-03-05 $4,094,022 Fall of 2026


LA 819 Repairs: Choudrant
H.015059.6 - Asphalt overlay of asphalt pavement
Proj. Engr: Jantz, Matt Route: LA 819-1 LA 819-2 map
Contractor: Amethyst Construction, Inc. Miles: 0.58
Work Order Date Contract Amount Estimated Completion Date
2024-09-19 $824,105 Beginning of 2025


LA 146: Drainage Improvements
H.015232.6 - Drainage
Proj. Engr: Jantz, Matt Route: LA 146 map
Contractor: Amethyst Construction, Inc. Miles: 0.10
Work Order Date Contract Amount Estimated Completion Date
2024-09-19 $361,015 Beginning of 2025


LA 823: Drainage Improvements
H.015233.6 - Drainage
Proj. Engr: Jantz, Matt Route: LA 823 map
Contractor: Diamond B Construction Co., L. Miles: 0.21
Work Order Date Contract Amount Estimated Completion Date
2024-12-04 $394,839 Spring of 2025


I-20: Lincoln/Madison Parish Tree Removal
H.015418.6 - Miscellaneous
Proj. Engr: Harrison, John Route: I-20 map
Contractor: Trahan Construction, LLC Miles: 44.88
Work Order Date Contract Amount Estimated Completion Date
2024-06-10 $3,489,769 Beginning of 2026


D05 Rumble Strips and Striping Ph 1
H.015594.6 - Striping and pavement markers
Proj. Engr: Jantz, Matt Route: US 80 LA 146 map
Contractor: Highway Graphics LLC Miles: 179.97
Work Order Date Contract Amount Estimated Completion Date
2024-03-07 $3,842,567 Beginning of 2026


D05 Rumble Strips and Striping Ph 2
H.015930.6 - Striping and pavement markers
Proj. Engr: Belfassi, Hamid Route: US 167 map
Contractor: Highway Graphics LLC Miles: 70.16
Work Order Date Contract Amount Estimated Completion Date
2025-02-17 $1,859,565 Beginning of 2026


LA 33: Drainage Repairs
H.016048.6 - Drainage
Proj. Engr: Jantz, Matt Route: LA 33 map
Contractor: Miles: 0.02
Work Order Date Contract Amount Estimated Completion Date
2024-10-05 $112,412 Fall of 2024


Madison Parish

Note: The estimated completion date is based on the work order date and the contract
days allowed. Unavoidable contingencies and unforeseen events often develop during construction, which may impact the actual completion date.

LA 577: Joe's Bayou Rd - 1500 Ft N I-20
H.015323.6 - Concrete pavement rehab-grinding/dowell retrofit/should drain install
Proj. Engr: Foret, Byron Route: LA 577 map
Contractor: Progressive Construction Co., Miles: 0.64
Work Order Date Contract Amount Estimated Completion Date
2025-01-17 $2,284,536 Fall of 2025


Morehouse Parish

Note: The estimated completion date is based on the work order date and the contract
days allowed. Unavoidable contingencies and unforeseen events often develop during construction, which may impact the actual completion date.

Up R.R. Overpass Near Bonita (Hbi)
H.000665.6 -
Proj. Engr: Harrison, John Route: US 165 map
Contractor: Baker Pile Driving and Site Wo Miles: 1.32
Work Order Date Contract Amount Estimated Completion Date
2021-10-20 $24,749,487 Summer of 2025


US 425: Up RR Xing (Mer Rouge)
H.014904.6 - Railroads
Proj. Engr: Harrison, John Route: US 425 LA 138 map
Contractor: D & J Construction Co., LLC Miles: 0.05
Work Order Date Contract Amount Estimated Completion Date
2024-12-13 $421,841 Spring of 2025


Ouachita Parish

Note: The estimated completion date is based on the work order date and the contract
days allowed. Unavoidable contingencies and unforeseen events often develop during construction, which may impact the actual completion date.

LA 15 (Winnsboro Road) Streetscaping
H.007531.6 - Sidewalks/bike paths
Proj. Engr: Anzalone, Brad Route: LA 15 map
Contractor: Jd's Rebar & Construction, Inc Miles: 0.85
Work Order Date Contract Amount Estimated Completion Date
2024-09-06 $1,970,546 Beginning of 2026


US 165 Sb: Rilla - Pearl St
H.014108.6 - Asphalt overlay of asphalt pavement
Proj. Engr: Hodge, Samuel Route: US 165 map
Contractor: Diamond B Construction Co., L. Miles: 4.59
Work Order Date Contract Amount Estimated Completion Date
2024-10-21 $5,412,673 Summer of 2025


US 165 & La 139 Prep to Stop Beacons (Ouach)
H.014295.6 - Planning study
Proj. Engr: Belfassi, Hamid Route: LA 139 map
Contractor: Ems Electric of Monroe, L.L.C. Miles: 2.67
Work Order Date Contract Amount Estimated Completion Date
2024-05-20 $1,133,641 Fall of 2025


US 80: La 617 Ouachita River Bridge
H.014835.6 - Asphalt overlay of asphalt pavement
Proj. Engr: Hodge, Samuel Route: US 80 map
Contractor: Diamond B Construction Co., L. Miles: 2.32
Work Order Date Contract Amount Estimated Completion Date
2023-04-10 $5,921,887 Fall of 2024


US 80: 670 Ft W La 3249 - La 617
H.014851.6 - Asphalt overlay of asphalt pavement
Proj. Engr: Hodge, Samuel Route: US 80 map
Contractor: Diamond B Construction Co., L. Miles: 2.23
Work Order Date Contract Amount Estimated Completion Date
2024-09-01 $4,378,086 Spring of 2025


Richland Parish

Note: The estimated completion date is based on the work order date and the contract
days allowed. Unavoidable contingencies and unforeseen events often develop during construction, which may impact the actual completion date.

LA 132: Bridges Near Mangham
H.013990.6 - New location/replacement of bridge
Proj. Engr: Belfassi, Hamid Route: LA 132 map
Contractor: Diamond B Construction Co., L. Miles: 3.83
Work Order Date Contract Amount Estimated Completion Date
2023-10-21 $10,003,666 Summer of 2026


LA 17: Franklin P/L - Rundell Lp
H.014789.6 - Asphalt overlay of asphalt pavement
Proj. Engr: Belfassi, Hamid Route: LA 17 map
Contractor: D & J Construction Co., LLC Miles: 2.40
Work Order Date Contract Amount Estimated Completion Date
2024-11-08 $2,937,641 Beginning of 2025


LA 133: La 15 - US 80
H.014811.6 - Asph concrete ovly over in place stabilized/cement treated base course
Proj. Engr: Belfassi, Hamid Route: LA 133 map
Contractor: Diamond B Construction Co., L. Miles: 8.27
Work Order Date Contract Amount Estimated Completion Date
2024-11-01 $6,733,447 Fall of 2025


Union Parish

Note: The estimated completion date is based on the work order date and the contract
days allowed. Unavoidable contingencies and unforeseen events often develop during construction, which may impact the actual completion date.

LA 151: Creek and Relief Bridges
H.013992.6 - New location/replacement of bridge
Proj. Engr: Jantz, Matt Route: LA 151 map
Contractor: Brown Industrial Construction, Miles: 0.61
Work Order Date Contract Amount Estimated Completion Date
2023-02-05 $11,004,361 Fall of 2025


LA 15: Drainage Improvements
H.015234.6 - Drainage
Proj. Engr: Jantz, Matt Route: LA 15 map
Contractor: C W & W Contractors, Inc. Miles: 0.10
Work Order Date Contract Amount Estimated Completion Date
2025-02-03 $185,157 Spring of 2025


District 05

No districtwide projects.