Loyola Drive at I-10 Interchange Improvements
State Proj. No.:
SP H.011670
Start date:
Beginning of 2020
Cost:
125.6 million
Contractor:
Gilchrist Construction
 |
Map It |
PROJECT OVERVIEW: The project will modify existing Loyola ramps and will add two elevated flyover ramps. The project will also add auxiliary lanes along I-10 between Loyola Drive and Williams Blvd. while modifying Loyola Drive to accommodate the improvements and to tie in to the Airport connector road. The Design-Build contract was given a Notice to Proceed on August 30, 2020 with a contracted completion date of late, 2022 with a contract price of $125.6 million.  STATUS: DOTD Executed a Notice to Proceed for a Design-Build contract on August 30, 2019. Test Piles were driven in November 2019, with construction work beginning in late March 2020 on I-10 mainline. Construction contract completion date of November 2022. Project Environmental documents can be found here. CURRENT ACTIVITY: Review of I-10 mainline design submittals, right of way acquisition, utility relocations, and early construction activities. CONTRACTOR: Gilchrist Construction, LLC DOTD PROJECT MANAGER: Timothy Nickel, P.E.
|