Proposal:H.015783
Parish:East Baton Rouge
Routes:L A 410
Description:LA 410: EMERGENCY DRAINAGE REPAIR
Type Construction:
Estimated Construction Cost:$258,401.33
| Rank | License | Bidder | Construction Bid |
| 1 | 61167 | HENDRICK CONSTRUCTION, INC. | $267,183.74 |
| 2 | 72429 | Arbour Construction, LLC | $273,327.96 |
| 3 | 68237 | GULF STATES SERVICES, LLC | $279,449.06 |
| 4 | 68424 | Procivil, LLC | $285,908.26 |
| 5 | 06276 | Barriere Construction Co., LLC | $312,323.87 |
| 6 | 49356 | KORT's CONSTRUCTION SERVICES, INC. | $314,578.26 |
| 7 | 74839 | 21 Construction, L.L.C. | $432,397.38 |
Line Number | Item Number | Item Description | Quantity | Unit of Measure | - 1 - HENDRICK CONSTRUCTION, INC. | - 2 - Arbour Construction, LLC | - 3 - GULF STATES SERVICES, LLC | - 4 - Procivil, LLC | | Unit Price | Total Amount | Unit Price | Total Amount | Unit Price | Total Amount | Unit Price | Total Amount | | 0001 | 201-01-00100 | Clearing and Grubbing | 1 | LUMP | 10,291.34 | 10,291.34 | 10,000.00 | 10,000.00 | 1,000.00 | 1,000.00 | 15,000.00 | 15,000.00 | | 0002 | 202-02-32100 | Removal of Pipe (Cross Drain) 2 - 84" CMPA | 110 | LNFT | 79.13 | 8,704.30 | 60.00 | 6,600.00 | 35.00 | 3,850.00 | 50.00 | 5,500.00 | | 0003 | 203-05-00100 | Excavation and Embankment | 1 | LUMP | 23,398.68 | 23,398.68 | 30,000.00 | 30,000.00 | 16,500.00 | 16,500.00 | 2,500.00 | 2,500.00 | | 0004 | 204-06-00100 | Temporary Silt Fencing | 300 | LNFT | 14.43 | 4,329.00 | 2.00 | 600.00 | 1.00 | 300.00 | 2.00 | 600.00 | | 0005 | 502-01-00100 | Asphalt Concrete | 48.8 | TON | 781.93 | 38,158.18 | 480.00 | 23,424.00 | 540.00 | 26,352.00 | 450.00 | 21,960.00 | | 0006 | 509-01-00100 | Milling Asphalt Pavement | 426.7 | SQYD | 38.13 | 16,270.07 | 30.00 | 12,801.00 | 34.00 | 14,507.80 | 25.00 | 10,667.50 | | 0007 | 509-02-00100 | Contractor Retained Reclaimed Asphalt Pavement | -23.7 | CUYD | 0.01 | -0.24 | 0.01 | -0.24 | 0.01 | -0.24 | 0.01 | -0.24 | | 0008 | 510-01-00200 | Pavement Patching (12" Minimum Thickness) | 111.1 | SQYD | 261.90 | 29,097.09 | 192.00 | 21,331.20 | 175.00 | 19,442.50 | 150.00 | 16,665.00 | | 0009 | 701-02-01120 | Cross Drain Pipe Arch (60" Equiv. RCPA) | 112 | LNFT | 453.41 | 50,781.92 | 640.00 | 71,680.00 | 785.00 | 87,920.00 | 1,000.00 | 112,000.00 | | 0010 | 701-17-00100 | Trench Excavation Safety Protection (Depth >5 feet) | 56 | LNFT | 55.81 | 3,125.36 | 10.00 | 560.00 | 1.00 | 56.00 | 1.00 | 56.00 | | 0011 | 706-03-00300 | Incidental Concrete Paving (6" Thick) | 10 | SQYD | 309.48 | 3,094.80 | 300.00 | 3,000.00 | 250.00 | 2,500.00 | 200.00 | 2,000.00 | | 0012 | 713-01-00100 | Temporary Signs and Barricades | 1 | LUMP | 10,971.96 | 10,971.96 | 24,000.00 | 24,000.00 | 30,000.00 | 30,000.00 | 45,000.00 | 45,000.00 | | 0013 | 713-03-02000 | Temporary Pavement Markings (Broken Line) (4" Width) (10' Length) | 0.03 | MILE | 39,585.47 | 1,187.56 | 30,000.00 | 900.00 | 5,000.00 | 150.00 | 1,000.00 | 30.00 | | 0014 | 713-04-01000 | Temporary Pavement Markings (Solid Line) (4" Width) | 0.06 | MILE | 19,798.83 | 1,187.93 | 30,000.00 | 1,800.00 | 5,000.00 | 300.00 | 1,000.00 | 60.00 | | 0015 | 726-01-00100 | Bedding Material | 60 | CUYD | 84.81 | 5,088.60 | 100.00 | 6,000.00 | 1.00 | 60.00 | 150.00 | 9,000.00 | | 0016 | 727-01-00100 | Mobilization | 1 | LUMP | 26,239.81 | 26,239.81 | 26,400.00 | 26,400.00 | 58,000.00 | 58,000.00 | 25,000.00 | 25,000.00 | | 0017 | 729-16-00200 | Object Marker Assembly (Type 2) | 2 | EACH | 91.43 | 182.86 | 240.00 | 480.00 | 75.00 | 150.00 | 500.00 | 1,000.00 | | 0018 | 731-02-00100 | Reflectorized Raised Pavement Markers | 4 | EACH | 418.71 | 1,674.84 | 120.00 | 480.00 | 200.00 | 800.00 | 100.00 | 400.00 | | 0019 | 732-02-02000 | Plastic Pavement Striping (Solid Line) (4" Width) (Thermoplastic 90 mil) | 0.06 | MILE | 80,742.00 | 4,844.52 | 60,000.00 | 3,600.00 | 25,000.00 | 1,500.00 | 50,000.00 | 3,000.00 | | 0020 | 732-03-02000 | Plastic Pavement Striping (Broken Line) (4" Width) (Thermoplastic 90 mil) | 0.03 | MILE | 100,528.64 | 3,015.86 | 60,000.00 | 1,800.00 | 15,000.00 | 450.00 | 50,000.00 | 1,500.00 | | 0021 | 735-01-00100 | Mailboxes | 1 | EACH | 24.38 | 24.38 | 360.00 | 360.00 | 25.00 | 25.00 | 20.00 | 20.00 | | 0022 | 735-02-00100 | Mailbox Supports (Single) | 1 | EACH | 304.78 | 304.78 | 360.00 | 360.00 | 250.00 | 250.00 | 250.00 | 250.00 | | 0023 | 739-01-00100 | Hydro-Seeding | 0.1 | ACRE | 7,255.10 | 725.51 | 30,000.00 | 3,000.00 | 5,000.00 | 500.00 | 15,000.00 | 1,500.00 | | 0024 | 740-01-00100 | Construction Layout | 1 | LUMP | 16,643.38 | 16,643.38 | 14,000.00 | 14,000.00 | 2,500.00 | 2,500.00 | 500.00 | 500.00 | | 0025 | NS-500-00340 | Saw Cutting Asphalt Concrete Pavement | 48 | INLF | 22.40 | 1,075.20 | 24.00 | 1,152.00 | 7.00 | 336.00 | 25.00 | 1,200.00 | | 0026 | NS-713-00009 | Portable Changeable Message Sign (with communications) | 3 | EACH | 2,255.35 | 6,766.05 | 3,000.00 | 9,000.00 | 4,000.00 | 12,000.00 | 3,500.00 | 10,500.00 | | | | | | | | | | | | | | | | | | CONTRACTOR TOTAL | | | | 267,183.74 | | 273,327.96 | | 279,449.06 | | 285,908.26 |
Line Number | Item Number | Item Description | Quantity | Unit of Measure | - 5 - Barriere Construction Co., LLC | - 6 - KORT's CONSTRUCTION SERVICES, INC. | - 7 - 21 Construction, L.L.C. | | Unit Price | Total Amount | Unit Price | Total Amount | Unit Price | Total Amount | | 0001 | 201-01-00100 | Clearing and Grubbing | 1 | LUMP | 5,000.00 | 5,000.00 | 7,500.00 | 7,500.00 | 50,000.00 | 50,000.00 | | 0002 | 202-02-32100 | Removal of Pipe (Cross Drain) 2 - 84" CMPA | 110 | LNFT | 263.00 | 28,930.00 | 45.00 | 4,950.00 | 125.00 | 13,750.00 | | 0003 | 203-05-00100 | Excavation and Embankment | 1 | LUMP | 25,475.00 | 25,475.00 | 13,000.00 | 13,000.00 | 35,000.00 | 35,000.00 | | 0004 | 204-06-00100 | Temporary Silt Fencing | 300 | LNFT | 6.00 | 1,800.00 | 3.00 | 900.00 | 6.00 | 1,800.00 | | 0005 | 502-01-00100 | Asphalt Concrete | 48.8 | TON | 491.00 | 23,960.80 | 450.00 | 21,960.00 | 450.00 | 21,960.00 | | 0006 | 509-01-00100 | Milling Asphalt Pavement | 426.7 | SQYD | 29.50 | 12,587.65 | 35.00 | 14,934.50 | 22.50 | 9,600.75 | | 0007 | 509-02-00100 | Contractor Retained Reclaimed Asphalt Pavement | -23.7 | CUYD | 0.01 | -0.24 | 0.01 | -0.24 | 0.10 | -2.37 | | 0008 | 510-01-00200 | Pavement Patching (12" Minimum Thickness) | 111.1 | SQYD | 181.00 | 20,109.10 | 300.00 | 33,330.00 | 240.00 | 26,664.00 | | 0009 | 701-02-01120 | Cross Drain Pipe Arch (60" Equiv. RCPA) | 112 | LNFT | 762.50 | 85,400.00 | 950.00 | 106,400.00 | 1,360.00 | 152,320.00 | | 0010 | 701-17-00100 | Trench Excavation Safety Protection (Depth >5 feet) | 56 | LNFT | 1.00 | 56.00 | 20.00 | 1,120.00 | 125.00 | 7,000.00 | | 0011 | 706-03-00300 | Incidental Concrete Paving (6" Thick) | 10 | SQYD | 300.00 | 3,000.00 | 180.00 | 1,800.00 | 375.00 | 3,750.00 | | 0012 | 713-01-00100 | Temporary Signs and Barricades | 1 | LUMP | 37,500.00 | 37,500.00 | 30,000.00 | 30,000.00 | 35,000.00 | 35,000.00 | | 0013 | 713-03-02000 | Temporary Pavement Markings (Broken Line) (4" Width) (10' Length) | 0.03 | MILE | 12.00 | 0.36 | 25,000.00 | 750.00 | 5,500.00 | 165.00 | | 0014 | 713-04-01000 | Temporary Pavement Markings (Solid Line) (4" Width) | 0.06 | MILE | 12.00 | 0.72 | 25,000.00 | 1,500.00 | 5,500.00 | 330.00 | | 0015 | 726-01-00100 | Bedding Material | 60 | CUYD | 10.00 | 600.00 | 190.00 | 11,400.00 | 150.00 | 9,000.00 | | 0016 | 727-01-00100 | Mobilization | 1 | LUMP | 44,000.00 | 44,000.00 | 30,000.00 | 30,000.00 | 42,500.00 | 42,500.00 | | 0017 | 729-16-00200 | Object Marker Assembly (Type 2) | 2 | EACH | 90.00 | 180.00 | 175.00 | 350.00 | 325.00 | 650.00 | | 0018 | 731-02-00100 | Reflectorized Raised Pavement Markers | 4 | EACH | 120.00 | 480.00 | 15.00 | 60.00 | 60.00 | 240.00 | | 0019 | 732-02-02000 | Plastic Pavement Striping (Solid Line) (4" Width) (Thermoplastic 90 mil) | 0.06 | MILE | 60,000.00 | 3,600.00 | 22,000.00 | 1,320.00 | 27,500.00 | 1,650.00 | | 0020 | 732-03-02000 | Plastic Pavement Striping (Broken Line) (4" Width) (Thermoplastic 90 mil) | 0.03 | MILE | 59,000.00 | 1,770.00 | 22,000.00 | 660.00 | 16,500.00 | 495.00 | | 0021 | 735-01-00100 | Mailboxes | 1 | EACH | 24.00 | 24.00 | 200.00 | 200.00 | 275.00 | 275.00 | | 0022 | 735-02-00100 | Mailbox Supports (Single) | 1 | EACH | 300.00 | 300.00 | 300.00 | 300.00 | 400.00 | 400.00 | | 0023 | 739-01-00100 | Hydro-Seeding | 0.1 | ACRE | 30,500.00 | 3,050.00 | 25,000.00 | 2,500.00 | 28,500.00 | 2,850.00 | | 0024 | 740-01-00100 | Construction Layout | 1 | LUMP | 6,700.00 | 6,700.00 | 10,000.00 | 10,000.00 | 8,000.00 | 8,000.00 | | 0025 | NS-500-00340 | Saw Cutting Asphalt Concrete Pavement | 48 | INLF | 0.01 | 0.48 | 3.00 | 144.00 | 25.00 | 1,200.00 | | 0026 | NS-713-00009 | Portable Changeable Message Sign (with communications) | 3 | EACH | 2,600.00 | 7,800.00 | 6,500.00 | 19,500.00 | 2,600.00 | 7,800.00 | | | | | | | | | | | | | | | | CONTRACTOR TOTAL | | | | 312,323.87 | | 314,578.26 | | 432,397.38 |
|