Proposal:H.012368
Parish:East Baton Rouge
Description:LA 1248: Drainage Modifications
Type Construction:
Estimated Construction Cost:$56,853.24
| Rank | License | Bidder | Construction Bid |
| 1 | 25587 | Gutcon, Inc. | $39,187.00 |
| 2 | 13992 | Brown Contractors, Inc. | $79,577.30 |
| 3 | 05693 | Industrial Enterprises, Inc. | $84,857.48 |
| 4 | 02179 | Boh Bros. Construction Co., LLC. | $84,960.00 |
| 5 | 38325 | Cheniere Construction | $91,479.78 |
| 6 | 00046 | Barber Bros. Contracting Co., L.L.C | $96,160.30 |
| 16084 | Spinks Construction, Inc. | IRREGULAR |
| 54488 | Expert Maintenance & Const Svc LLC | IRREGULAR |
| 57931 | KCR CONTRACTORS, LLC | IRREGULAR |
Line Number | Item Number | Item Description | Quantity | Unit of Measure | - 1 - Gutcon, Inc. | - 2 - Brown Contractors, Inc. | - 3 - Industrial Enterprises, Inc. | - 4 - Boh Bros. Construction Co., LLC. | | Unit Price | Total Amount | Unit Price | Total Amount | Unit Price | Total Amount | Unit Price | Total Amount | | 0001 | 202-02-06100 | Removal of Concrete Walks and Drives | 150 | SQYD | 25.00 | 3,750.00 | 25.00 | 3,750.00 | 24.00 | 3,600.00 | 16.00 | 2,400.00 | | 0002 | 203-05-00100 | Excavation and Embankment | 1 | LUMP | 1,000.00 | 1,000.00 | 9,500.00 | 9,500.00 | 9,800.00 | 9,800.00 | 4,500.00 | 4,500.00 | | 0003 | 204-06-00100 | Temporary Silt Fencing | 400 | LNFT | 0.50 | 200.00 | 2.30 | 920.00 | 2.50 | 1,000.00 | 3.00 | 1,200.00 | | 0004 | 701-05-01000 | Side Drain Pipe (12" RCP/PP/CMP) | 162 | LNFT | 40.00 | 6,480.00 | 85.00 | 13,770.00 | 37.20 | 6,026.40 | 80.00 | 12,960.00 | | 0005 | 701-15-00100 | Concrete Collar | 4 | EACH | 10.00 | 40.00 | 300.00 | 1,200.00 | 500.00 | 2,000.00 | 600.00 | 2,400.00 | | 0006 | 702-03-00300 | Catch Basins (CB-04) | 5 | EACH | 1,000.00 | 5,000.00 | 2,400.00 | 12,000.00 | 3,000.00 | 15,000.00 | 2,000.00 | 10,000.00 | | 0007 | 705-09-00100 | Rebuilt Fence | 300 | LNFT | 0.00 | 0.00 | 1.00 | 300.00 | 34.00 | 10,200.00 | 30.00 | 9,000.00 | | 0008 | 706-01-00100 | Concrete Walk (4" Thick) | 150 | SQYD | 45.00 | 6,750.00 | 88.00 | 13,200.00 | 84.00 | 12,600.00 | 62.00 | 9,300.00 | | 0009 | 713-01-00100 | Temporary Signs and Barricades | 1 | LUMP | 5,000.00 | 5,000.00 | 9,500.00 | 9,500.00 | 7,500.00 | 7,500.00 | 6,400.00 | 6,400.00 | | 0010 | 726-01-00100 | Bedding Material | 39.34 | CUYD | 50.00 | 1,967.00 | 95.00 | 3,737.30 | 86.25 | 3,393.08 | 91.51 | 3,600.00 | | 0011 | 727-01-00100 | Mobilization | 1 | LUMP | 7,000.00 | 7,000.00 | 7,900.00 | 7,900.00 | 9,600.00 | 9,600.00 | 20,000.00 | 20,000.00 | | 0012 | 739-01-00100 | Hydro-Seeding | 0.2 | ACRE | 5,000.00 | 1,000.00 | 3,000.00 | 600.00 | 6,690.00 | 1,338.00 | 6,000.00 | 1,200.00 | | 0013 | 740-01-00100 | Construction Layout | 1 | LUMP | 1,000.00 | 1,000.00 | 3,200.00 | 3,200.00 | 2,800.00 | 2,800.00 | 2,000.00 | 2,000.00 | | | | | | | | | | | | | | | | | | CONTRACTOR TOTAL | | | | 39,187.00 | | 79,577.30 | | 84,857.48 | | 84,960.00 |
Line Number | Item Number | Item Description | Quantity | Unit of Measure | - 5 - Cheniere Construction | - 6 - Barber Bros. Contracting Co., L.L.C | Spinks Construction, Inc. | Expert Maintenance & Const Svc LLC | | Unit Price | Total Amount | Unit Price | Total Amount | Unit Price | Total Amount | Unit Price | Total Amount | | 0001 | 202-02-06100 | Removal of Concrete Walks and Drives | 150 | SQYD | 35.76 | 5,364.00 | 10.00 | 1,500.00 | 10.00 | 1,500.00 | 4,540.00 | 681,000.00 | | 0002 | 203-05-00100 | Excavation and Embankment | 1 | LUMP | 4,540.00 | 4,540.00 | 18,000.00 | 18,000.00 | 1,000.00 | 1,000.00 | 5,540.00 | 5,540.00 | | 0003 | 204-06-00100 | Temporary Silt Fencing | 400 | LNFT | 11.00 | 4,400.00 | 2.00 | 800.00 | 3.00 | 1,200.00 | 3,940.00 | 1,576,000.00 | | 0004 | 701-05-01000 | Side Drain Pipe (12" RCP/PP/CMP) | 162 | LNFT | 137.50 | 22,275.00 | 70.00 | 11,340.00 | 90.00 | 14,580.00 | 9,640.00 | 1,561,680.00 | | 0005 | 701-15-00100 | Concrete Collar | 4 | EACH | 1,010.00 | 4,040.00 | 1,200.00 | 4,800.00 | 1,000.00 | 4,000.00 | 4,740.00 | 18,960.00 | | 0006 | 702-03-00300 | Catch Basins (CB-04) | 5 | EACH | 1,300.00 | 6,500.00 | 2,000.00 | 10,000.00 | 2,000.00 | 10,000.00 | 20,540.00 | 102,700.00 | | 0007 | 705-09-00100 | Rebuilt Fence | 300 | LNFT | 14.50 | 4,350.00 | 50.00 | 15,000.00 | 30.00 | 9,000.00 | 9,040.00 | 2,712,000.00 | | 0008 | 706-01-00100 | Concrete Walk (4" Thick) | 150 | SQYD | 72.85 | 10,927.50 | 55.00 | 8,250.00 | 70.00 | 10,500.00 | 12,040.00 | 1,806,000.00 | | 0009 | 713-01-00100 | Temporary Signs and Barricades | 1 | LUMP | 15,660.00 | 15,660.00 | 12,000.00 | 12,000.00 | 10,000.00 | 10,000.00 | 6,540.00 | 6,540.00 | | 0010 | 726-01-00100 | Bedding Material | 39.34 | CUYD | 116.25 | 4,573.28 | 45.00 | 1,770.30 | 50.00 | 1,967.00 | 2,523.50 | 99,274.49 | | 0011 | 727-01-00100 | Mobilization | 1 | LUMP | 3,705.00 | 3,705.00 | 10,000.00 | 10,000.00 | 4,000.00 | 4,000.00 | 6,540.00 | 6,540.00 | | 0012 | 739-01-00100 | Hydro-Seeding | 0.2 | ACRE | 10,725.00 | 2,145.00 | 6,000.00 | 1,200.00 | 10,000.00 | 2,000.00 | 200.00 | 40.00 | | 0013 | 740-01-00100 | Construction Layout | 1 | LUMP | 3,000.00 | 3,000.00 | 1,500.00 | 1,500.00 | 3,000.00 | 3,000.00 | 6,580.00 | 6,580.00 | | | | | | | | | | | | | | | | | | CONTRACTOR TOTAL | | | | 91,479.78 | | 96,160.30 | | IRREGULAR | | IRREGULAR |
Line Number | Item Number | Item Description | Quantity | Unit of Measure | KCR CONTRACTORS, LLC | | Unit Price | Total Amount | | 0001 | 202-02-06100 | Removal of Concrete Walks and Drives | 150 | SQYD | 10.00 | 1,500.00 | | 0002 | 203-05-00100 | Excavation and Embankment | 1 | LUMP | 8,500.00 | 8,500.00 | | 0003 | 204-06-00100 | Temporary Silt Fencing | 400 | LNFT | 2.00 | 800.00 | | 0004 | 701-05-01000 | Side Drain Pipe (12" RCP/PP/CMP) | 162 | LNFT | 102.00 | 16,524.00 | | 0005 | 701-15-00100 | Concrete Collar | 4 | EACH | 500.00 | 2,000.00 | | 0006 | 702-03-00300 | Catch Basins (CB-04) | 5 | EACH | 500.00 | 2,500.00 | | 0007 | 705-09-00100 | Rebuilt Fence | 300 | LNFT | 15.00 | 4,500.00 | | 0008 | 706-01-00100 | Concrete Walk (4" Thick) | 150 | SQYD | 55.00 | 8,250.00 | | 0009 | 713-01-00100 | Temporary Signs and Barricades | 1 | LUMP | 9,800.00 | 9,800.00 | | 0010 | 726-01-00100 | Bedding Material | 39.34 | CUYD | 1.00 | 39.34 | | 0011 | 727-01-00100 | Mobilization | 1 | LUMP | 3,500.00 | 3,500.00 | | 0012 | 739-01-00100 | Hydro-Seeding | 0.2 | ACRE | 5,500.00 | 1,100.00 | | 0013 | 740-01-00100 | Construction Layout | 1 | LUMP | 3,000.00 | 3,000.00 | | | | | | | | | | | | CONTRACTOR TOTAL | | | | IRREGULAR |
|