Search


Bid Tabulations for the Letting of 8/25/2025 in District 58 - Chase

Proposal:H.972580.1-R2
Parish:Franklin
Description:DIST 58 HQ BOILER REPLACEMENT
Type Construction:REMOVAL AND REPLACEMENT OF BOILER, PUMPS, VALVES, AND OTHER APPURTENANCES, AND ASSOCIATED ELECTRICAL WORK
Estimated Construction Cost:$129,149.00
Rank License BidderConstruction Bid
137074Byrnes Mechanical Contractors, Inc.$276,000.00


Line
Number
Item NumberItem DescriptionQuantityUnit of
Measure
- 1 -
Byrnes Mechanical Contractors, Inc.
Unit PriceTotal
Amount
0001TS-821-00201Building Heating, Ventilating, and Air Conditioning 1     LUMP268,050.00268,050.00
0002TS-822-00002Building Electrical 1     LUMP7,950.007,950.00
       
  CONTRACTOR TOTAL   276,000.00