Proposal:H.972494.1-R2
Parish:Jefferson
Description:US 61 AIRLINE PS REPAIRS
Type Construction:Pump station repairs and related work.
Estimated Construction Cost:$135,000.00
| Rank | License | Bidder | Construction Bid |
| 1 | 57913 | Quality Machine Works, Inc | $156,364.00 |
| 2 | 58640 | Sartin Builders, LLC | $310,000.00 |
Line Number | Item Number | Item Description | Quantity | Unit of Measure | - 1 - Quality Machine Works, Inc | - 2 - Sartin Builders, LLC | | Unit Price | Total Amount | Unit Price | Total Amount | | 0001 | NS-MNT-03100 | Pump Refurbishment (Pump 1) | 1 | EACH | 56,846.00 | 56,846.00 | 75,000.00 | 75,000.00 | | 0002 | NS-MNT-03100 | Pump Refurbishment (Pump 3) | 1 | EACH | 54,336.00 | 54,336.00 | 75,000.00 | 75,000.00 | | 0003 | NS-MNT-03125 | Check Valve (Inspect) (Pump 1) | 1 | EACH | 4,363.00 | 4,363.00 | 5,000.00 | 5,000.00 | | 0004 | NS-MNT-03125 | Check Valve (Inspect) (Pump 4) | 1 | EACH | 3,444.00 | 3,444.00 | 5,000.00 | 5,000.00 | | 0005 | NS-MNT-03125 | Check Valve (New) (Pump 1) | 1 | EACH | 13,706.00 | 13,706.00 | 40,000.00 | 40,000.00 | | 0006 | NS-MNT-03125 | Check Valve (New) (Pump 4) | 1 | EACH | 8,969.00 | 8,969.00 | 40,000.00 | 40,000.00 | | 0007 | NS-MNT-03125 | Check Valve (Rehab) (Pump 2) | 1 | EACH | 7,350.00 | 7,350.00 | 35,000.00 | 35,000.00 | | 0008 | NS-MNT-03125 | Check Valve (Rehab) (Pump 3) | 1 | EACH | 7,350.00 | 7,350.00 | 35,000.00 | 35,000.00 | | | | | | | | | | | | | | CONTRACTOR TOTAL | | | | 156,364.00 | | 310,000.00 |
|