Proposal:H.014581.6-R1
Parish:Jefferson
Routes:LA 3017
Description:PETERS ROAD BRIDGE & EXTENSION PHASE 2A
Type Construction:CLEARING AND GRUBBING, GRADING, DRAINAGE STRUCTURES, VINYL SHEETING, PRECAST REINFORCED CONCRETE BOX CULVERT, REMOVAL OF PRECAST CONCRETE BRIDGE, RIPRAP, COFFERDAMS, AND RELATED WORK.
Estimated Construction Cost:$24,934,022.53
| Rank | License | Bidder | Construction Bid |
| 1 | 44187 | RNGD Construction LLC | $23,979,040.50 |
| 2 | 24901 | Hard Rock Construction LLC | $27,380,900.95 |
| 3 | 36961 | Cycle Construction Co. L.L.C. | $28,168,656.60 |
| 4 | 12069 | B & K Construction Co. LLC | $32,510,845.00 |
| 5 | 06276 | Barriere Construction Co., LLC | $35,576,638.00 |
| 6 | 48896 | Command Construction Industries LLC | $35,970,953.44 |
| 7 | 02179 | Boh Bros. Construction Co., LLC. | $38,944,558.00 |
Line Number | Item Number | Item Description | Quantity | Unit of Measure | - 1 - RNGD Construction LLC | - 2 - Hard Rock Construction LLC | - 3 - Cycle Construction Co. L.L.C. | - 4 - B & K Construction Co. LLC | | Unit Price | Total Amount | Unit Price | Total Amount | Unit Price | Total Amount | Unit Price | Total Amount | | 0001 | 201-01-00100 | Clearing and Grubbing | 4 | LUMP | 20,000.00 | 20,000.00 | 100,000.00 | 100,000.00 | 900,000.00 | 900,000.00 | 50,000.00 | 50,000.00 | | 0002 | 202-01-00100 | Removal of Structures and Obstructions | 1 | LUMP | 10,000.00 | 10,000.00 | 181,000.00 | 181,000.00 | 132,875.00 | 132,875.00 | 150,000.00 | 150,000.00 | | 0003 | 202-02-00040 | Removal of Riprap (Salvageable) (Vehicular Measurement) | 10,000 | CUYD | 30.00 | 300,000.00 | 5.00 | 50,000.00 | 22.50 | 225,000.00 | 22.00 | 220,000.00 | | 0004 | 202-02-04501 | Removal of Bridge (28' x 100' Precast Concrete Deck, Timber Piles) | 2,800 | LUMP | 40,000.00 | 40,000.00 | 66,000.00 | 66,000.00 | 36,000.00 | 36,000.00 | 75,000.00 | 75,000.00 | | 0005 | 203-02-00100 | Drainage Excavation | 1,219 | CUYD | 32.00 | 39,008.00 | 100.00 | 121,900.00 | 28.00 | 34,132.00 | 20.00 | 24,380.00 | | 0006 | 203-03-00100 | Embankment | 29,523 | CUYD | 27.50 | 811,882.50 | 53.00 | 1,564,719.00 | 39.00 | 1,151,397.00 | 75.00 | 2,214,225.00 | | 0007 | 204-02-00100 | Temporary Hay Bales | 49 | EACH | 26.00 | 1,274.00 | 25.00 | 1,225.00 | 28.00 | 1,372.00 | 35.00 | 1,715.00 | | 0008 | 204-05-00100 | Temporary Sediment Check Dams (Hay) | 27 | EACH | 160.00 | 4,320.00 | 152.00 | 4,104.00 | 170.00 | 4,590.00 | 200.00 | 5,400.00 | | 0009 | 204-06-00100 | Temporary Silt Fencing | 4,646 | LNFT | 3.00 | 13,938.00 | 2.40 | 11,150.40 | 4.00 | 18,584.00 | 4.00 | 18,584.00 | | 0010 | 204-07-00100 | Temporary Stone Construction Entrance | 2 | EACH | 8,000.00 | 16,000.00 | 30,000.00 | 60,000.00 | 3,900.00 | 7,800.00 | 9,500.00 | 19,000.00 | | 0011 | 502-01-00200 | Asphalt Concrete, Drives, Turnouts and Miscellaneous | 143.6 | TON | 400.00 | 57,440.00 | 175.00 | 25,130.00 | 270.00 | 38,772.00 | 500.00 | 71,800.00 | | 0012 | 511-01-00100 | Saw Cutting Asphalt Concrete Pavement | 1,440 | INLF | 2.00 | 2,880.00 | 1.00 | 1,440.00 | 1.00 | 1,440.00 | 2.00 | 2,880.00 | | 0013 | 701-02-01060 | Cross Drain Pipe Arch (42" Equiv. RCPA) | 29 | LNFT | 360.00 | 10,440.00 | 620.00 | 17,980.00 | 600.00 | 17,400.00 | 330.00 | 9,570.00 | | 0014 | 701-03-01002 | Storm Drain Pipe (15" RCP/RPVCP) | 192 | LNFT | 110.00 | 21,120.00 | 205.00 | 39,360.00 | 350.00 | 67,200.00 | 160.00 | 30,720.00 | | 0015 | 701-03-01022 | Storm Drain Pipe (18" RCP/RPVCP) | 14 | LNFT | 200.00 | 2,800.00 | 245.00 | 3,430.00 | 440.00 | 6,160.00 | 260.00 | 3,640.00 | | 0016 | 701-03-01082 | Storm Drain Pipe (36" RCP/RPVCP) | 124 | LNFT | 210.00 | 26,040.00 | 312.00 | 38,688.00 | 460.00 | 57,040.00 | 265.00 | 32,860.00 | | 0017 | 701-04-01200 | Storm Drain Pipe Arch (84" Equiv. RCPA) | 33 | LNFT | 1,400.00 | 46,200.00 | 2,000.00 | 66,000.00 | 1,950.00 | 64,350.00 | 1,720.00 | 56,760.00 | | 0018 | 701-11-01080 | Reinforced Concrete Pipe Arch (Extension) (36" Equiv.) | 87 | LNFT | 250.00 | 21,750.00 | 381.00 | 33,147.00 | 380.00 | 33,060.00 | 235.00 | 20,445.00 | | 0019 | 701-15-00100 | Concrete Collar | 2 | EACH | 1,400.00 | 2,800.00 | 5,000.00 | 10,000.00 | 4,300.00 | 8,600.00 | 3,000.00 | 6,000.00 | | 0020 | 701-17-00100 | Trench Excavation Safety Protection (Depth >5 feet) | 2,398 | LNFT | 0.50 | 1,199.00 | 12.00 | 28,776.00 | 1.00 | 2,398.00 | 1.00 | 2,398.00 | | 0021 | 702-02-00300 | Manholes (R-CB-11 MOD) | 2 | EACH | 14,000.00 | 28,000.00 | 18,000.00 | 36,000.00 | 20,600.00 | 41,200.00 | 13,000.00 | 26,000.00 | | 0022 | 702-03-00100 | Catch Basins (CB-01) | 8 | EACH | 4,000.00 | 32,000.00 | 4,600.00 | 36,800.00 | 7,640.00 | 61,120.00 | 7,300.00 | 58,400.00 | | 0023 | 711-03-00400 | Riprap (55 lb) | 1,890 | TON | 110.00 | 207,900.00 | 83.00 | 156,870.00 | 12.00 | 22,680.00 | 80.00 | 151,200.00 | | 0024 | 711-04-00100 | Geotextile Fabric | 1,386 | SQYD | 2.00 | 2,772.00 | 1.25 | 1,732.50 | 3.00 | 4,158.00 | 2.00 | 2,772.00 | | 0025 | 712-01-00400 | Concrete Cast-in-Place Revetment (7" Thick) | 480 | SQYD | 185.00 | 88,800.00 | 480.00 | 230,400.00 | 295.00 | 141,600.00 | 400.00 | 192,000.00 | | 0026 | 713-01-00100 | Temporary Signs and Barricades | 1 | LUMP | 160,000.00 | 160,000.00 | 50,000.00 | 50,000.00 | 245,000.00 | 245,000.00 | 150,000.00 | 150,000.00 | | 0027 | 716-01-00100 | Mulch (Vegetative) | 11.6 | TON | 1,000.00 | 11,600.00 | 953.00 | 11,054.80 | 960.00 | 11,136.00 | 1,250.00 | 14,500.00 | | 0028 | 720-01-01000 | Erosion Control System (Slope Protection) (Type A) | 3,134 | SQYD | 2.00 | 6,268.00 | 1.50 | 4,701.00 | 1.50 | 4,701.00 | 2.00 | 6,268.00 | | 0029 | 720-01-02040 | Erosion Control System, Flexible (Channel Liner) (Type E) | 400 | SQYD | 2.00 | 800.00 | 1.50 | 600.00 | 1.50 | 600.00 | 3.00 | 1,200.00 | | 0030 | 720-01-02060 | Erosion Control System, Flexible (Channel Liner) (Type F) | 200 | SQYD | 2.00 | 400.00 | 1.50 | 300.00 | 1.50 | 300.00 | 4.50 | 900.00 | | 0031 | 722-02-00100 | Project Site Laboratory (Equipped) | 1 | EACH | 100,000.00 | 100,000.00 | 28,000.00 | 28,000.00 | 61,000.00 | 61,000.00 | 20,000.00 | 20,000.00 | | 0032 | 725-01-00100 | Temporary Detour Roads | 575 | SQYD | 720.00 | 414,000.00 | 900.00 | 517,500.00 | 655.00 | 376,625.00 | 850.00 | 488,750.00 | | 0033 | 726-01-00100 | Bedding Material | 8,192.4 | CUYD | 95.00 | 778,278.00 | 125.00 | 1,024,050.00 | 129.00 | 1,056,819.60 | 210.00 | 1,720,404.00 | | 0034 | 727-01-00100 | Mobilization | 1 | LUMP | 2,000,000.00 | 2,000,000.00 | 655,000.00 | 655,000.00 | 567,000.00 | 567,000.00 | 2,065,000.00 | 2,065,000.00 | | 0035 | 735-01-00100 | Mailboxes | 1 | EACH | 40.00 | 40.00 | 1.25 | 1.25 | 34.00 | 34.00 | 350.00 | 350.00 | | 0036 | 735-02-00100 | Mailbox Supports (Single) | 1 | EACH | 375.00 | 375.00 | 200.00 | 200.00 | 450.00 | 450.00 | 100.00 | 100.00 | | 0037 | 739-01-00100 | Hydro-Seeding | 9 | ACRE | 3,000.00 | 27,000.00 | 3,000.00 | 27,000.00 | 2,930.00 | 26,370.00 | 4,000.00 | 36,000.00 | | 0038 | 740-01-00100 | Construction Layout | 1 | LUMP | 100,000.00 | 100,000.00 | 60,000.00 | 60,000.00 | 83,000.00 | 83,000.00 | 150,000.00 | 150,000.00 | | 0039 | 741-20-01060 | Water Main (4" PVC) | 100 | LNFT | 200.00 | 20,000.00 | 335.00 | 33,500.00 | 133.00 | 13,300.00 | 95.00 | 9,500.00 | | 0040 | 741-20-01080 | Water Main (6" PVC) | 30 | LNFT | 200.00 | 6,000.00 | 412.00 | 12,360.00 | 100.00 | 3,000.00 | 160.00 | 4,800.00 | | 0041 | 741-25-00100 | Water Meter and Box | 1 | EACH | 1,100.00 | 1,100.00 | 3,700.00 | 3,700.00 | 4,825.00 | 4,825.00 | 3,500.00 | 3,500.00 | | 0042 | 741-27-00100 | Backflow Preventer | 2 | EACH | 12,000.00 | 24,000.00 | 16,000.00 | 32,000.00 | 7,600.00 | 15,200.00 | 6,850.00 | 13,700.00 | | 0043 | 741-28-01080 | Service Connection (1 1/2" PVC) | 140 | LNFT | 100.00 | 14,000.00 | 50.00 | 7,000.00 | 39.00 | 5,460.00 | 40.00 | 5,600.00 | | 0044 | 805-15-01200 | Reinforced Concrete Box Culverts (Precast) (6' x 6') | 65 | LNFT | 1,600.00 | 104,000.00 | 1,050.00 | 68,250.00 | 1,470.00 | 95,550.00 | 1,600.00 | 104,000.00 | | 0045 | 805-15-02600 | Reinforced Concrete Box Culverts (Precast) (10' x 10') | 8,240 | LNFT | 1,650.00 | 13,596,000.00 | 1,875.00 | 15,450,000.00 | 1,605.00 | 13,225,200.00 | 1,700.00 | 14,008,000.00 | | 0046 | 805-17-00100 | Reinforced Concrete Box Culvert Headwall (Quantity of Steel = 15,638 lbs., Quantity of Concrete = 84.59 cuyd.) | 2 | EACH | 200,000.00 | 400,000.00 | 100,000.00 | 200,000.00 | 280,000.00 | 560,000.00 | 300,000.00 | 600,000.00 | | 0047 | 805-18-00100 | Concrete Finish (Class 2 Rubbed Finish) | 384 | SQFT | 9.00 | 3,456.00 | 5.00 | 1,920.00 | 4.50 | 1,728.00 | 4.00 | 1,536.00 | | 0048 | 805-18-00200 | Concrete Finish (Class 3 Special Finish) | 384 | SQFT | 15.00 | 5,760.00 | 3.00 | 1,152.00 | 2.50 | 960.00 | 7.00 | 2,688.00 | | 0049 | 817-03-00100 | Cofferdams | 1 | LUMP | 4,300,000.00 | 4,300,000.00 | 6,200,000.00 | 6,200,000.00 | 8,600,000.00 | 8,600,000.00 | 9,500,000.00 | 9,500,000.00 | | 0050 | NS-742-00001 | Tie In Sewer Effluent | 1 | EACH | 5,000.00 | 5,000.00 | 8,200.00 | 8,200.00 | 2,110.00 | 2,110.00 | 4,300.00 | 4,300.00 | | 0051 | TS-802-20000 | PERMANENT SHEETING (VINYL) | 6,160 | SQFT | 15.00 | 92,400.00 | 16.00 | 98,560.00 | 21.00 | 129,360.00 | 25.00 | 154,000.00 | | | | | | | | | | | | | | | | | | CONTRACTOR TOTAL | | | | 23,979,040.50 | | 27,380,900.95 | | 28,168,656.60 | | 32,510,845.00 |
Line Number | Item Number | Item Description | Quantity | Unit of Measure | - 5 - Barriere Construction Co., LLC | - 6 - Command Construction Industries LLC | - 7 - Boh Bros. Construction Co., LLC. | | Unit Price | Total Amount | Unit Price | Total Amount | Unit Price | Total Amount | | 0001 | 201-01-00100 | Clearing and Grubbing | 4 | LUMP | 79,000.00 | 79,000.00 | 2,000,000.00 | 2,000,000.00 | 50,000.00 | 50,000.00 | | 0002 | 202-01-00100 | Removal of Structures and Obstructions | 1 | LUMP | 16,000.00 | 16,000.00 | 1,000,000.00 | 1,000,000.00 | 75,000.00 | 75,000.00 | | 0003 | 202-02-00040 | Removal of Riprap (Salvageable) (Vehicular Measurement) | 10,000 | CUYD | 100.00 | 1,000,000.00 | 20.00 | 200,000.00 | 20.00 | 200,000.00 | | 0004 | 202-02-04501 | Removal of Bridge (28' x 100' Precast Concrete Deck, Timber Piles) | 2,800 | LUMP | 58,000.00 | 58,000.00 | 1,000,000.00 | 1,000,000.00 | 100,000.00 | 100,000.00 | | 0005 | 203-02-00100 | Drainage Excavation | 1,219 | CUYD | 56.00 | 68,264.00 | 20.00 | 24,380.00 | 50.00 | 60,950.00 | | 0006 | 203-03-00100 | Embankment | 29,523 | CUYD | 65.00 | 1,918,995.00 | 20.00 | 590,460.00 | 60.00 | 1,771,380.00 | | 0007 | 204-02-00100 | Temporary Hay Bales | 49 | EACH | 54.00 | 2,646.00 | 20.00 | 980.00 | 30.00 | 1,470.00 | | 0008 | 204-05-00100 | Temporary Sediment Check Dams (Hay) | 27 | EACH | 240.00 | 6,480.00 | 150.00 | 4,050.00 | 300.00 | 8,100.00 | | 0009 | 204-06-00100 | Temporary Silt Fencing | 4,646 | LNFT | 2.00 | 9,292.00 | 0.01 | 46.46 | 4.00 | 18,584.00 | | 0010 | 204-07-00100 | Temporary Stone Construction Entrance | 2 | EACH | 10,000.00 | 20,000.00 | 5,000.00 | 10,000.00 | 12,000.00 | 24,000.00 | | 0011 | 502-01-00200 | Asphalt Concrete, Drives, Turnouts and Miscellaneous | 143.6 | TON | 390.00 | 56,004.00 | 275.00 | 39,490.00 | 400.00 | 57,440.00 | | 0012 | 511-01-00100 | Saw Cutting Asphalt Concrete Pavement | 1,440 | INLF | 1.00 | 1,440.00 | 1.00 | 1,440.00 | 1.00 | 1,440.00 | | 0013 | 701-02-01060 | Cross Drain Pipe Arch (42" Equiv. RCPA) | 29 | LNFT | 680.00 | 19,720.00 | 250.00 | 7,250.00 | 625.00 | 18,125.00 | | 0014 | 701-03-01002 | Storm Drain Pipe (15" RCP/RPVCP) | 192 | LNFT | 240.00 | 46,080.00 | 125.00 | 24,000.00 | 125.00 | 24,000.00 | | 0015 | 701-03-01022 | Storm Drain Pipe (18" RCP/RPVCP) | 14 | LNFT | 380.00 | 5,320.00 | 125.00 | 1,750.00 | 200.00 | 2,800.00 | | 0016 | 701-03-01082 | Storm Drain Pipe (36" RCP/RPVCP) | 124 | LNFT | 340.00 | 42,160.00 | 200.00 | 24,800.00 | 230.00 | 28,520.00 | | 0017 | 701-04-01200 | Storm Drain Pipe Arch (84" Equiv. RCPA) | 33 | LNFT | 1,980.00 | 65,340.00 | 1,200.00 | 39,600.00 | 1,500.00 | 49,500.00 | | 0018 | 701-11-01080 | Reinforced Concrete Pipe Arch (Extension) (36" Equiv.) | 87 | LNFT | 520.00 | 45,240.00 | 225.00 | 19,575.00 | 325.00 | 28,275.00 | | 0019 | 701-15-00100 | Concrete Collar | 2 | EACH | 4,000.00 | 8,000.00 | 750.00 | 1,500.00 | 2,000.00 | 4,000.00 | | 0020 | 701-17-00100 | Trench Excavation Safety Protection (Depth >5 feet) | 2,398 | LNFT | 1.00 | 2,398.00 | 0.01 | 23.98 | 7.00 | 16,786.00 | | 0021 | 702-02-00300 | Manholes (R-CB-11 MOD) | 2 | EACH | 35,000.00 | 70,000.00 | 13,000.00 | 26,000.00 | 12,000.00 | 24,000.00 | | 0022 | 702-03-00100 | Catch Basins (CB-01) | 8 | EACH | 5,700.00 | 45,600.00 | 6,000.00 | 48,000.00 | 4,500.00 | 36,000.00 | | 0023 | 711-03-00400 | Riprap (55 lb) | 1,890 | TON | 105.00 | 198,450.00 | 80.00 | 151,200.00 | 100.00 | 189,000.00 | | 0024 | 711-04-00100 | Geotextile Fabric | 1,386 | SQYD | 3.00 | 4,158.00 | 5.00 | 6,930.00 | 1.50 | 2,079.00 | | 0025 | 712-01-00400 | Concrete Cast-in-Place Revetment (7" Thick) | 480 | SQYD | 240.00 | 115,200.00 | 125.00 | 60,000.00 | 175.00 | 84,000.00 | | 0026 | 713-01-00100 | Temporary Signs and Barricades | 1 | LUMP | 1,550,000.00 | 1,550,000.00 | 500,000.00 | 500,000.00 | 100,000.00 | 100,000.00 | | 0027 | 716-01-00100 | Mulch (Vegetative) | 11.6 | TON | 1,000.00 | 11,600.00 | 900.00 | 10,440.00 | 700.00 | 8,120.00 | | 0028 | 720-01-01000 | Erosion Control System (Slope Protection) (Type A) | 3,134 | SQYD | 2.00 | 6,268.00 | 1.00 | 3,134.00 | 11.00 | 34,474.00 | | 0029 | 720-01-02040 | Erosion Control System, Flexible (Channel Liner) (Type E) | 400 | SQYD | 2.50 | 1,000.00 | 1.00 | 400.00 | 26.00 | 10,400.00 | | 0030 | 720-01-02060 | Erosion Control System, Flexible (Channel Liner) (Type F) | 200 | SQYD | 4.00 | 800.00 | 1.00 | 200.00 | 26.00 | 5,200.00 | | 0031 | 722-02-00100 | Project Site Laboratory (Equipped) | 1 | EACH | 10,000.00 | 10,000.00 | 25,000.00 | 25,000.00 | 75,000.00 | 75,000.00 | | 0032 | 725-01-00100 | Temporary Detour Roads | 575 | SQYD | 900.00 | 517,500.00 | 500.00 | 287,500.00 | 600.00 | 345,000.00 | | 0033 | 726-01-00100 | Bedding Material | 8,192.4 | CUYD | 300.00 | 2,457,720.00 | 125.00 | 1,024,050.00 | 200.00 | 1,638,480.00 | | 0034 | 727-01-00100 | Mobilization | 1 | LUMP | 3,400,000.00 | 3,400,000.00 | 3,500,000.00 | 3,500,000.00 | 3,360,000.00 | 3,360,000.00 | | 0035 | 735-01-00100 | Mailboxes | 1 | EACH | 1.00 | 1.00 | 250.00 | 250.00 | 75.00 | 75.00 | | 0036 | 735-02-00100 | Mailbox Supports (Single) | 1 | EACH | 1,000.00 | 1,000.00 | 450.00 | 450.00 | 300.00 | 300.00 | | 0037 | 739-01-00100 | Hydro-Seeding | 9 | ACRE | 3,000.00 | 27,000.00 | 4,000.00 | 36,000.00 | 5,000.00 | 45,000.00 | | 0038 | 740-01-00100 | Construction Layout | 1 | LUMP | 315,000.00 | 315,000.00 | 500,000.00 | 500,000.00 | 500,000.00 | 500,000.00 | | 0039 | 741-20-01060 | Water Main (4" PVC) | 100 | LNFT | 120.00 | 12,000.00 | 100.00 | 10,000.00 | 140.00 | 14,000.00 | | 0040 | 741-20-01080 | Water Main (6" PVC) | 30 | LNFT | 220.00 | 6,600.00 | 100.00 | 3,000.00 | 210.00 | 6,300.00 | | 0041 | 741-25-00100 | Water Meter and Box | 1 | EACH | 7,500.00 | 7,500.00 | 1,250.00 | 1,250.00 | 2,900.00 | 2,900.00 | | 0042 | 741-27-00100 | Backflow Preventer | 2 | EACH | 4,000.00 | 8,000.00 | 5,000.00 | 10,000.00 | 9,000.00 | 18,000.00 | | 0043 | 741-28-01080 | Service Connection (1 1/2" PVC) | 140 | LNFT | 20.00 | 2,800.00 | 10.00 | 1,400.00 | 21.00 | 2,940.00 | | 0044 | 805-15-01200 | Reinforced Concrete Box Culverts (Precast) (6' x 6') | 65 | LNFT | 1,600.00 | 104,000.00 | 1,500.00 | 97,500.00 | 1,300.00 | 84,500.00 | | 0045 | 805-15-02600 | Reinforced Concrete Box Culverts (Precast) (10' x 10') | 8,240 | LNFT | 1,790.00 | 14,749,600.00 | 1,725.00 | 14,214,000.00 | 2,000.00 | 16,480,000.00 | | 0046 | 805-17-00100 | Reinforced Concrete Box Culvert Headwall (Quantity of Steel = 15,638 lbs., Quantity of Concrete = 84.59 cuyd.) | 2 | EACH | 270,000.00 | 540,000.00 | 200,000.00 | 400,000.00 | 350,000.00 | 700,000.00 | | 0047 | 805-18-00100 | Concrete Finish (Class 2 Rubbed Finish) | 384 | SQFT | 9.00 | 3,456.00 | 3.00 | 1,152.00 | 1.25 | 480.00 | | 0048 | 805-18-00200 | Concrete Finish (Class 3 Special Finish) | 384 | SQFT | 9.00 | 3,456.00 | 3.00 | 1,152.00 | 5.00 | 1,920.00 | | 0049 | 817-03-00100 | Cofferdams | 1 | LUMP | 7,200,000.00 | 7,200,000.00 | 10,000,000.00 | 10,000,000.00 | 12,500,000.00 | 12,500,000.00 | | 0050 | NS-742-00001 | Tie In Sewer Effluent | 1 | EACH | 4,510.00 | 4,510.00 | 1,000.00 | 1,000.00 | 500.00 | 500.00 | | 0051 | TS-802-20000 | PERMANENT SHEETING (VINYL) | 6,160 | SQFT | 119.00 | 733,040.00 | 10.00 | 61,600.00 | 22.00 | 135,520.00 | | | | | | | | | | | | | | | | CONTRACTOR TOTAL | | | | 35,576,638.00 | | 35,970,953.44 | | 38,944,558.00 |
|