Proposal:H.016299.6
Parish:Rapides
Routes:LA 115
Description:LA 115: AVOYELLES P/L TO LA 1207
Type Construction:MILLING ASPHALT PAVEMENT, PAVEMENT PATCHING, ASPHALT CONCRETE PAVEMENT, AND RELATED WORK.
Estimated Construction Cost:$3,898,191.75
| Rank | License | Bidder | Construction Bid |
| 1 | 12487 | Diamond B Construction Co., L.L.C. | $3,301,842.60 |
| 2 | 12312 | Gilchrist Construction Company, LLC | $3,649,361.05 |
Line Number | Item Number | Item Description | Quantity | Unit of Measure | - 1 - Diamond B Construction Co., L.L.C. | - 2 - Gilchrist Construction Company, LLC | | Unit Price | Total Amount | Unit Price | Total Amount | | 0001 | 202-02-14500 | Removal of Guard Rail | 452 | LNFT | 14.00 | 6,328.00 | 15.00 | 6,780.00 | | 0002 | 203-07-00100 | Borrow (Vehicular Measurement) | 170 | CUYD | 18.00 | 3,060.00 | 130.00 | 22,100.00 | | 0003 | 401-02-00100 | Aggregate Surface Course (Adjusted Vehicular Measurement) | 1,096 | CUYD | 120.00 | 131,520.00 | 65.00 | 71,240.00 | | 0004 | 502-01-00100 | Asphalt Concrete | 11,182.8 | TON | 135.00 | 1,509,678.00 | 138.00 | 1,543,226.40 | | 0005 | 502-01-00200 | Asphalt Concrete, Drives, Turnouts and Miscellaneous | 1,537.7 | TON | 190.00 | 292,163.00 | 138.00 | 212,202.60 | | 0006 | 509-01-00100 | Milling Asphalt Pavement | 51,189 | SQYD | 2.75 | 140,769.75 | 3.00 | 153,567.00 | | 0007 | 509-02-00100 | Contractor Retained Reclaimed Asphalt Pavement | -2,665 | CUYD | 1.00 | -2,665.00 | 1.00 | -2,665.00 | | 0008 | 510-01-00260 | Pavement Patching (16 inch Minimum Thickness) | 5,036 | SQYD | 160.00 | 805,760.00 | 190.00 | 956,840.00 | | 0009 | 511-03-00100 | Sawing and Sealing Transverse Joints in Asphalt Concrete Overlay | 22 | LNFT | 95.00 | 2,090.00 | 240.00 | 5,280.00 | | 0010 | 511-04-00100 | Sawcuts in Asphalt Concrete Lifts | 22 | LNFT | 95.00 | 2,090.00 | 240.00 | 5,280.00 | | 0011 | 704-03-00200 | Blocked Out Guard Rail - 31", (6'-3" Post Spacing) | 150 | LNFT | 36.00 | 5,400.00 | 37.00 | 5,550.00 | | 0012 | 704-06-00200 | Guard Rail Bridge Attachments (Single Thrie Beam) | 50 | LNFT | 85.00 | 4,250.00 | 87.00 | 4,350.00 | | 0013 | 704-07-00200 | Guard Rail Transitions (Double Thrie Beam) | 100 | LNFT | 135.00 | 13,500.00 | 137.00 | 13,700.00 | | 0014 | 704-10-00310 | Guard Rail End Treatment, NCHRP 350 - 31" (TL-3 Flared) | 4 | EACH | 3,750.00 | 15,000.00 | 3,800.00 | 15,200.00 | | 0015 | 713-01-00100 | Temporary Signs and Barricades | 1 | LUMP | 45,000.00 | 45,000.00 | 100,000.00 | 100,000.00 | | 0016 | 713-03-01000 | Temporary Pavement Markings (Broken Line) (4" Width) (4' Length) | 11.882 | MILE | 150.00 | 1,782.30 | 200.00 | 2,376.40 | | 0017 | 713-03-02000 | Temporary Pavement Markings (Broken Line) (4" Width) (10' Length) | 7.891 | MILE | 650.00 | 5,129.15 | 650.00 | 5,129.15 | | 0018 | 713-04-01000 | Temporary Pavement Markings (Solid Line) (4" Width) | 36.245 | MILE | 900.00 | 32,620.50 | 900.00 | 32,620.50 | | 0019 | 724-01-00100 | Rumble Strips (Centerline) | 3.884 | MILE | 1,000.00 | 3,884.00 | 1,100.00 | 4,272.40 | | 0020 | 727-01-00100 | Mobilization | 1 | LUMP | 156,000.00 | 156,000.00 | 340,000.00 | 340,000.00 | | 0021 | 729-16-00300 | Object Marker Assembly (Type 3) | 4 | EACH | 135.00 | 540.00 | 140.00 | 560.00 | | 0022 | 731-02-00100 | Reflectorized Raised Pavement Markers | 788 | EACH | 6.00 | 4,728.00 | 7.00 | 5,516.00 | | 0023 | 732-02-02000 | Plastic Pavement Striping (Solid Line) (4" Width) (Thermoplastic 90 mil) | 12.082 | MILE | 5,500.00 | 66,451.00 | 5,600.00 | 67,659.20 | | 0024 | 732-03-02000 | Plastic Pavement Striping (Broken Line) (4" Width) (Thermoplastic 90 mil) | 2.63 | MILE | 2,950.00 | 7,758.50 | 3,100.00 | 8,153.00 | | 0025 | 732-05-00100 | Removal of Existing Markings | 0.076 | MILE | 6,000.00 | 456.00 | 7,000.00 | 532.00 | | 0026 | 735-01-00100 | Mailboxes | 119 | EACH | 1.00 | 119.00 | 1.00 | 119.00 | | 0027 | 735-02-00100 | Mailbox Supports (Single) | 109 | EACH | 247.00 | 26,923.00 | 250.00 | 27,250.00 | | 0028 | 735-03-00100 | Mailbox Supports (Double) | 5 | EACH | 247.00 | 1,235.00 | 250.00 | 1,250.00 | | 0029 | 739-01-00100 | Hydro-Seeding | 1.883 | ACRE | 2,800.00 | 5,272.40 | 2,800.00 | 5,272.40 | | 0030 | 740-01-00100 | Construction Layout | 1 | LUMP | 15,000.00 | 15,000.00 | 36,000.00 | 36,000.00 | | | | | | | | | | | | | | CONTRACTOR TOTAL | | | | 3,301,842.60 | | 3,649,361.05 |
|