Bid Tabulations for the Letting of 8/12/2026 LA DOTD Headquarters

Proposal:H.014803.6
Parish:St. Helena
Routes:LA 16
Description:LA 16: LA 63 TO LM 9.852
Type Construction:BORROW, DRAINAGE STRUCTURES, MILLING ASPHALT PAVEMENT, PAVEMENT PATCHING, ASPHALT CONCRETE OVERLAY, CULVERT REHABILITATION, AND RELATED WORK.
Estimated Construction Cost:$6,533,801.40
Rank License BidderConstruction Bid
106276Barriere Construction Co., LLC$4,109,860.99
273475Madden Gulf Coast, LLC$4,323,988.02
312031R.J. Daigle & Sons Contractors, Inc$4,403,952.40
400046Barber Bros. Contracting Co., L.L.C$5,043,952.20


Line
Number
Item NumberItem DescriptionQuantityUnit of
Measure
- 1 -
Barriere Construction Co., LLC
- 2 -
Madden Gulf Coast, LLC
- 3 -
R.J. Daigle & Sons Contractors, Inc
- 4 -
Barber Bros. Contracting Co., L.L.C
Unit PriceTotal
Amount
Unit PriceTotal
Amount
Unit PriceTotal
Amount
Unit PriceTotal
Amount
0001202-01-00100Removal of Structures and Obstructions 1     LUMP30,000.0030,000.002,500.002,500.0066,000.0066,000.003,000.003,000.00
0002202-02-02020Removal of Asphalt Pavement 505.8   SQYD9.404,754.5220.0010,116.004.552,301.3920.0010,116.00
0003202-02-14500Removal of Guard Rail 588     LNFT8.504,998.0010.005,880.009.005,292.0012.007,056.00
0004202-02-38300Removal of Sign and U-Channel Post 4     EACH65.00260.0040.00160.0070.00280.0040.00160.00
0005203-07-00100Borrow (Vehicular Measurement) 1,318     CUYD10.0013,180.0087.00114,666.0011.7515,486.5045.0059,310.00
0006203-10-00100Cleaning Existing Ditches 1,400     LNFT5.007,000.008.5011,900.0012.0016,800.009.0012,600.00
0007204-05-00100Temporary Sediment Check Dams (Hay) 28     EACH159.004,452.00175.004,900.00175.004,900.00160.004,480.00
0008204-06-00100Temporary Silt Fencing 1,100     LNFT3.003,300.002.252,475.003.253,575.003.503,850.00
0009502-01-00100Asphalt Concrete 21,480.5   TON110.002,362,855.0094.002,019,167.00103.102,214,639.55115.002,470,257.50
0010502-01-00200Asphalt Concrete, Drives, Turnouts and Miscellaneous 737.4   TON175.00129,045.00185.00136,419.00103.1076,025.94210.00154,854.00
0011509-01-00100Milling Asphalt Pavement 97,822     SQYD1.15112,495.302.25220,099.501.85180,970.704.00391,288.00
0012509-02-00100Contractor Retained Reclaimed Asphalt Pavement -4,608     CUYD0.01-46.080.01-46.080.01-46.080.000.00
0013510-01-00200Pavement Patching (12" Minimum Thickness) 360     SQYD105.0037,800.00142.0051,120.00116.2541,850.00140.0050,400.00
0014510-01-00260Pavement Patching (16 inch Minimum Thickness) 445     SQYD120.0053,400.00165.0073,425.00135.5060,297.50160.0071,200.00
0015511-01-00100Saw Cutting Asphalt Concrete Pavement 720     INLF1.00720.002.001,440.001.15828.001.00720.00
0016701-01-01061Cross Drain Pipe (42" RCP) 416     LNFT270.00112,320.00221.0091,936.00350.00145,600.00235.0097,760.00
0017701-01-01081Cross Drain Pipe (48" RCP) 472     LNFT290.00136,880.00246.00116,112.00470.00221,840.00260.00122,720.00
0018701-01-01100Cross Drain Pipe (54" RCP) 100     LNFT480.0048,000.00304.0030,400.00620.0062,000.00325.0032,500.00
0019701-01-01120Cross Drain Pipe (60" RCP) 272     LNFT540.00146,880.00332.0090,304.00500.00136,000.00355.0096,560.00
0020701-17-00100Trench Excavation Safety Protection (Depth >5 feet) 580     LNFT1.00580.0020.0011,600.0019.0011,020.003.001,740.00
0021704-03-00200Blocked Out Guard Rail - 31", (6'-3" Post Spacing) 125     LNFT33.504,187.5025.003,125.0035.004,375.0028.003,500.00
0022704-07-00200Guard Rail Transitions (Double Thrie Beam) 100     LNFT120.0012,000.0085.008,500.00130.0013,000.0090.009,000.00
0023704-10-00310Guard Rail End Treatment, NCHRP 350 - 31" (TL-3 Flared) 4     EACH3,400.0013,600.003,500.0014,000.003,550.0014,200.003,700.0014,800.00
0024707-04-00100Asphalt Concrete Curb 54     LNFT92.504,995.00200.0010,800.00126.006,804.0070.003,780.00
0025713-01-00100Temporary Signs and Barricades 1     LUMP131,000.00131,000.00148,000.00148,000.00160,000.00160,000.00115,000.00115,000.00
0026713-02-00500Temporary Pavement Markings (24" Width) 840     LNFT1.00840.000.50420.000.55462.000.50420.00
0027713-03-01000Temporary Pavement Markings (Broken Line) (4" Width) (4' Length) 11.228 MILE100.001,122.80450.005,052.60450.005,052.60300.003,368.40
0028713-03-02000Temporary Pavement Markings (Broken Line) (4" Width) (10' Length) 8.076 MILE605.004,885.98600.004,845.60680.005,491.68600.004,845.60
0029713-04-01000Temporary Pavement Markings (Solid Line) (4" Width) 32.487 MILE805.0026,152.04800.0025,989.60900.0029,238.30800.0025,989.60
0030713-11-00100Portable Changeable Message Signs 2     EACH4,900.009,800.004,500.009,000.005,750.0011,500.003,000.006,000.00
0031724-01-00100Rumble Strips (Centerline) 3.743 MILE300.001,122.901,000.003,743.00340.001,272.62350.001,310.05
0032724-02-00100Rumble Strips (Shoulder/Edge) 7.485 MILE300.002,245.501,000.007,485.00340.002,544.90350.002,619.75
0033726-01-00100Bedding Material 172.4   CUYD1.00172.40121.5020,946.60185.0031,894.00130.0022,412.00
0034727-01-00100Mobilization 1     LUMP161,000.00161,000.00232,000.00232,000.00245,000.00245,000.00350,000.00350,000.00
0035729-16-00200Object Marker Assembly (Type 2) 22     EACH76.001,672.0075.001,650.0085.001,870.0080.001,760.00
0036729-16-00300Object Marker Assembly (Type 3) 4     EACH95.00380.00100.00400.0090.00360.00110.00440.00
0037731-02-00100Reflectorized Raised Pavement Markers 728     EACH5.003,640.005.003,640.005.253,822.005.303,858.40
0038732-01-01080Plastic Pavement Striping (24" Width) (Thermoplastic 90 mil) 280     LNFT14.504,060.0014.504,060.0016.004,480.0016.004,480.00
0039732-02-02000Plastic Pavement Striping (Solid Line) (4" Width) (Thermoplastic 90 mil) 10.829 MILE4,400.0047,647.604,400.0047,647.604,900.0053,062.104,600.0049,813.40
0040732-03-02000Plastic Pavement Striping (Broken Line) (4" Width) (Thermoplastic 90 mil) 2.692 MILE1,115.003,001.581,100.002,961.201,200.003,230.401,200.003,230.40
0041732-03-02010Plastic Pavement Striping (Dotted Line)(4" W)(2' L)(Thermo 90 mil) 0.147 MILE6,050.00889.356,000.00882.006,900.001,014.306,100.00896.70
0042735-01-00100Mailboxes 46     EACH35.001,610.0050.002,300.0034.001,564.0055.002,530.00
0043735-02-00100Mailbox Supports (Single) 46     EACH260.0011,960.00250.0011,500.00290.0013,340.00260.0011,960.00
0044739-01-00100Hydro-Seeding 10.988 ACRE2,700.0029,667.602,800.0030,766.403,000.0032,964.002,800.0030,766.40
0045740-01-00100Construction Layout 1     LUMP4,200.004,200.0015,000.0015,000.0018,500.0018,500.0030,000.0030,000.00
0046NS-701-00020Culvert Rehabilitation by Spray Applied Lining (60" CMP)400     LNFT584.00233,600.00880.00352,000.00660.00264,000.00900.00360,000.00
0047NS-701-00020Culvert Rehabilitation by Spray Applied Lining (84" CMP)279     LNFT665.00185,535.001,300.00362,700.00750.00209,250.001,400.00390,600.00
             
  CONTRACTOR TOTAL   4,109,860.99 4,323,988.02 4,403,952.40 5,043,952.20