Bid Tabulations for the Letting of 7/8/2026 LA DOTD Headquarters

Proposal:H.016109.6
Parish:St. Charles
Routes:LA 3127
Description:LA 3127 WESTBOUND: ST. JOHN P/L - I-310
Type Construction:DRAINAGE STRUCTURES, MILLING ASPHALT PAVEMENT, MILLING CONCRETE PAVEMENT, ASPHALT CONCRETE OVERLAY, PAVEMENT PATCHING, COFFERDAMS, AND RELATED WORK.
Estimated Construction Cost:$9,957,783.75
Rank License BidderConstruction Bid
106276Barriere Construction Co., LLC$7,479,171.00
273475Madden Gulf Coast, LLC$9,288,544.63
302179Boh Bros. Construction Co., LLC.$9,447,277.95


Line
Number
Item NumberItem DescriptionQuantityUnit of
Measure
- 1 -
Barriere Construction Co., LLC
- 2 -
Madden Gulf Coast, LLC
- 3 -
Boh Bros. Construction Co., LLC.
Unit PriceTotal
Amount
Unit PriceTotal
Amount
Unit PriceTotal
Amount
0001202-02-02020Removal of Asphalt Pavement 177.3   SQYD25.004,432.5025.004,432.5025.004,432.50
0002202-02-14500Removal of Guard Rail 2,100.4   LNFT10.6522,369.266.0012,602.4015.0031,506.00
0003202-02-32100Removal of Pipe (Cross Drain) 56" x 39" CMPA (48" EQUIV. CMPA)576     LNFT50.5029,088.0030.0017,280.0035.0020,160.00
0004202-02-38300Removal of Sign and U-Channel Post 23     EACH20.25465.7565.001,495.0025.00575.00
0005203-07-00100Borrow (Vehicular Measurement) 4,200     CUYD23.5098,700.0025.00105,000.0030.00126,000.00
0006502-01-00100Asphalt Concrete 42,495.1   TON115.004,886,936.50118.005,014,421.80135.005,736,838.50
0007502-01-00200Asphalt Concrete, Drives, Turnouts and Miscellaneous 2,771.5   TON1.002,771.5050.00138,575.00230.00637,445.00
0008509-01-00100Milling Asphalt Pavement 233,391     SQYD2.00466,782.003.00700,173.003.50816,868.50
0009509-02-00100Contractor Retained Reclaimed Asphalt Pavement -13,172     CUYD0.01-131.720.01-131.720.10-1,317.20
0010510-01-00250Pavement Patching (14 inch Minimum Thickness) 3,500     SQYD101.00353,500.00120.00420,000.00175.00612,500.00
0011701-02-01080Cross Drain Pipe Arch (48" Equiv. RCPA) 576     LNFT425.00244,800.00375.00216,000.00450.00259,200.00
0012701-17-00100Trench Excavation Safety Protection (Depth >5 feet) 192     LNFT1.00192.0025.004,800.001.00192.00
0013704-03-00200Blocked Out Guard Rail - 31", (6'-3" Post Spacing) 1,175.2   LNFT30.2535,549.8034.0039,956.8030.0035,256.00
0014704-07-00200Guard Rail Transitions (Double Thrie Beam) 200     LNFT101.0020,200.00120.0024,000.00115.0023,000.00
0015704-10-00310Guard Rail End Treatment, NCHRP 350 - 31" (TL-3 Flared) 8     EACH3,550.0028,400.003,150.0025,200.003,750.0030,000.00
0016711-02-00300Riprap (30 lb) 30     CUYD252.007,560.00175.005,250.00200.006,000.00
0017711-04-00100Geotextile Fabric 45     SQYD3.00135.003.00135.001.0045.00
0018713-01-00100Temporary Signs and Barricades 1     LUMP380,000.00380,000.00500,000.00500,000.00470,000.00470,000.00
0019713-02-00300Temporary Pavement Markings (8" Width) 5,655     LNFT0.351,979.250.351,979.250.10565.50
0020713-03-01000Temporary Pavement Markings (Broken Line) (4" Width) (4' Length) 26.552 MILE684.0018,161.57450.0011,948.40350.009,293.20
0021713-03-02000Temporary Pavement Markings (Broken Line) (4" Width) (10' Length) 26.552 MILE700.0018,586.40700.0018,586.40725.0019,250.20
0022713-04-01000Temporary Pavement Markings (Solid Line) (4" Width) 60.03  MILE1,200.0072,036.001,200.0072,036.00925.0055,527.75
0023713-05-00220Temporary Pavement Legends & Symbols (Arrow - Left Turn) 3     EACH25.0075.0025.0075.0025.0075.00
0024713-05-00230Temporary Pavement Legends & Symbols (Arrow - Right Turn) 21     EACH25.00525.0025.00525.0025.00525.00
0025713-05-00240Temporary Pavement Legends & Symbols (Arrow - Merge) 3     EACH25.0075.0025.0075.0025.0075.00
0026713-05-00300Temporary Pavement Legends & Symbols (ONLY) 3     EACH25.0075.0025.0075.0025.0075.00
0027713-08-00100Temporary Precast Concrete Barrier (Department Furnished) 126     EACH375.0047,250.00550.0069,300.00400.0050,400.00
0028713-10-00100Temporary Precast Concrete Barrier Movement 252     EACH425.00107,100.00220.0055,440.0080.0020,160.00
0029716-01-00100Mulch (Vegetative) 20     TON675.0013,500.00675.0013,500.00700.0014,000.00
0030717-01-00100Seeding 600     LB9.755,850.00975.00585,000.0010.006,000.00
0031718-01-00100Fertilizer 9,500     LB0.888,360.000.908,550.001.009,500.00
0032724-02-00100Rumble Strips (Shoulder/Edge) 15.08  MILE302.004,554.161,000.0015,080.00325.004,901.00
0033726-01-00100Bedding Material 195.9   CUYD1.00195.90120.0023,508.00125.0024,487.50
0034727-01-00100Mobilization 1     LUMP380,000.00380,000.00825,000.00825,000.00225,000.00225,000.00
0035729-16-00300Object Marker Assembly (Type 3) 23     EACH101.002,323.00100.002,300.00100.002,300.00
0036731-02-00100Reflectorized Raised Pavement Markers 1,597     EACH5.007,985.005.007,985.006.5010,380.50
0037732-01-01040Plastic Pavement Striping (8" Width) (Thermoplastic 90 mil) 1,885     LNFT4.057,634.254.007,540.003.256,126.25
0038732-01-01080Plastic Pavement Striping (24" Width) (Thermoplastic 90 mil) 96     LNFT20.001,920.0020.001,920.0012.501,200.00
0039732-02-02000Plastic Pavement Striping (Solid Line) (4" Width) (Thermoplastic 90 mil) 20.01  MILE5,050.00101,050.505,000.00100,050.005,250.00105,052.50
0040732-03-02000Plastic Pavement Striping (Broken Line) (4" Width) (Thermoplastic 90 mil) 8.851 MILE1,320.0011,683.321,300.0011,506.302,250.0019,914.75
0041732-03-02030Plastic Pavement Striping (Dotted Line)(8" W)(2' L)(Thermo 90 mil) 0.307 MILE10,650.003,269.5510,500.003,223.5011,000.003,377.00
0042732-04-01080Plastic Pavement Legends and Symbols (Arrow - Left Turn) 1     EACH405.00405.00400.00400.00250.00250.00
0043732-04-01100Plastic Pavement Legends and Symbols (Arrow - Right Turn) 7     EACH405.002,835.00400.002,800.00250.001,750.00
0044732-04-01120Plastic Pavement Legends and Symbols (Arrow - Merge) 1     EACH755.00755.00750.00750.00250.00250.00
0045732-04-15020Plastic Pavement Legends and Symbols (ONLY) 1     EACH655.00655.00650.00650.00250.00250.00
0046732-05-00100Removal of Existing Markings 0.091 MILE20,000.001,820.0020,000.001,820.006,500.00591.50
0047740-01-00100Construction Layout 1     LUMP29,552.8129,552.81137,000.00137,000.0015,000.0015,000.00
0048817-03-00100Cofferdams 1     LUMP28,500.0028,500.0025,000.0025,000.0017,500.0017,500.00
0049NS-602-00001Milling Concrete Pavement 886.6   SQYD19.5017,288.7020.0017,732.0015.0013,299.00
0050NS-700-00810Impact Attenuator (Construction Zone)(Test Level 3) 4     EACH355.001,420.009,500.0038,000.00375.001,500.00
           
  CONTRACTOR TOTAL   7,479,171.00 9,288,544.63 9,447,277.95