Proposal:H.015455.6
Parish:Lincoln
Description:SPRING CREEK ROAD OVER WAFER CREEK
Type Construction:CLEARING AND GRUBBING, REMOVAL OF BRIDGE, GRADING, DRAINAGE STRUCTURES, CLASS II BASE COURSE, LIME TREATMENT, ASPHALT CONCRETE PAVEMENT, PRECAST CONCRETE PILES, CONCRETE SLAB SPAN BRIDGE, AND RELATED WORK.
Estimated Construction Cost:$1,535,800.15
| Rank | License | Bidder | Construction Bid |
| 1 | 71454 | Chief Bridge & Concrete LLC | $1,155,680.65 |
| 2 | 14788 | Louisiana Bridge, Inc. | $1,226,492.30 |
| 3 | 00044 | Guinn Construction, LLC | $1,270,236.60 |
| 4 | 39462 | JB JAMES CONSTRUCTION LLC | $1,451,491.90 |
Line Number | Item Number | Item Description | Quantity | Unit of Measure | - 1 - Chief Bridge & Concrete LLC | - 2 - Louisiana Bridge, Inc. | - 3 - Guinn Construction, LLC | - 4 - JB JAMES CONSTRUCTION LLC | | Unit Price | Total Amount | Unit Price | Total Amount | Unit Price | Total Amount | Unit Price | Total Amount | | 0001 | 201-01-00100 | Clearing and Grubbing | 1 | LUMP | 75,000.00 | 75,000.00 | 31,000.00 | 31,000.00 | 40,000.00 | 40,000.00 | 150,000.00 | 150,000.00 | | 0002 | 202-01-00100 | Removal of Structures and Obstructions | 1 | LUMP | 5,000.00 | 5,000.00 | 4,000.00 | 4,000.00 | 5,000.00 | 5,000.00 | 7,000.00 | 7,000.00 | | 0003 | 202-02-03030 | Removal of Pavement Structure | 896.4 | SQYD | 8.00 | 7,171.20 | 14.00 | 12,549.60 | 15.00 | 13,446.00 | 10.00 | 8,964.00 | | 0004 | 202-02-04501 | Removal of Bridge Bridge Str. No. 053132356924281 (STA. 105+34; 38' x 27' COPCSS) | 1,016 | LUMP | 100,000.00 | 100,000.00 | 31,000.00 | 31,000.00 | 25,000.00 | 25,000.00 | 85,000.00 | 85,000.00 | | 0005 | 202-02-12000 | Removal of Fence | 510 | LNFT | 10.00 | 5,100.00 | 10.00 | 5,100.00 | 5.00 | 2,550.00 | 4.00 | 2,040.00 | | 0006 | 203-02-00100 | Drainage Excavation | 811 | CUYD | 25.00 | 20,275.00 | 21.00 | 17,031.00 | 35.00 | 28,385.00 | 35.00 | 28,385.00 | | 0007 | 203-05-00100 | Excavation and Embankment | 1 | LUMP | 25,000.00 | 25,000.00 | 26,000.00 | 26,000.00 | 55,500.00 | 55,500.00 | 100,000.00 | 100,000.00 | | 0008 | 204-05-00100 | Temporary Sediment Check Dams (Hay) | 3 | EACH | 200.00 | 600.00 | 230.00 | 690.00 | 500.00 | 1,500.00 | 200.00 | 600.00 | | 0009 | 204-05-00200 | Temporary Sediment Check Dams (Stone) | 1 | EACH | 1,500.00 | 1,500.00 | 1,400.00 | 1,400.00 | 2,000.00 | 2,000.00 | 1,500.00 | 1,500.00 | | 0010 | 204-06-00100 | Temporary Silt Fencing | 886 | LNFT | 5.00 | 4,430.00 | 5.00 | 4,430.00 | 3.00 | 2,658.00 | 7.00 | 6,202.00 | | 0011 | 302-02-08570 | Class II Base Course (8-1/2" Thick) (Crushed Stone or Recycled Portland Cement Concrete) | 832.2 | SQYD | 46.00 | 38,281.20 | 70.00 | 58,254.00 | 75.00 | 62,415.00 | 48.00 | 39,945.60 | | 0012 | 302-03-00100 | Base Drain Outlet | 6 | EACH | 1,500.00 | 9,000.00 | 950.00 | 5,700.00 | 2,000.00 | 12,000.00 | 1,900.00 | 11,400.00 | | 0013 | 304-01-00100 | Lime | 11.81 | TON | 415.00 | 4,901.15 | 450.00 | 5,314.50 | 1,000.00 | 11,810.00 | 700.00 | 8,267.00 | | 0014 | 304-05-00100 | Lime Treatment (Type E) | 832.2 | SQYD | 5.00 | 4,161.00 | 13.00 | 10,818.60 | 18.00 | 14,979.60 | 13.00 | 10,818.60 | | 0015 | 401-02-00100 | Aggregate Surface Course (Adjusted Vehicular Measurement) | 40 | CUYD | 215.00 | 8,600.00 | 265.00 | 10,600.00 | 250.00 | 10,000.00 | 170.00 | 6,800.00 | | 0016 | 502-01-00100 | Asphalt Concrete | 171.2 | TON | 220.00 | 37,664.00 | 335.00 | 57,352.00 | 350.00 | 59,920.00 | 400.00 | 68,480.00 | | 0017 | 511-01-00100 | Saw Cutting Asphalt Concrete Pavement | 82 | INLF | 14.00 | 1,148.00 | 4.00 | 328.00 | 30.00 | 2,460.00 | 30.50 | 2,501.00 | | 0018 | 701-05-02046 | Side Drain Pipe (Erosion) (18" RPVCP) | 152 | LNFT | 115.00 | 17,480.00 | 86.00 | 13,072.00 | 125.00 | 19,000.00 | 200.00 | 30,400.00 | | 0019 | 704-03-00200 | Blocked Out Guard Rail - 31", (6'-3" Post Spacing) | 50 | LNFT | 40.00 | 2,000.00 | 40.00 | 2,000.00 | 45.00 | 2,250.00 | 33.00 | 1,650.00 | | 0020 | 704-07-00200 | Guard Rail Transitions (Double Thrie Beam) | 100 | LNFT | 125.00 | 12,500.00 | 155.00 | 15,500.00 | 150.00 | 15,000.00 | 120.00 | 12,000.00 | | 0021 | 704-10-00120 | Guard Rail End Treatment, MASH, (TL-3 Flared) | 4 | EACH | 4,000.00 | 16,000.00 | 4,500.00 | 18,000.00 | 4,500.00 | 18,000.00 | 3,100.00 | 12,400.00 | | 0022 | 708-01-00100 | Right-of-Way Monument | 8 | EACH | 650.00 | 5,200.00 | 700.00 | 5,600.00 | 1,000.00 | 8,000.00 | 650.00 | 5,200.00 | | 0023 | 708-02-00100 | Right-of-Way Monument Witness Post | 8 | EACH | 200.00 | 1,600.00 | 300.00 | 2,400.00 | 300.00 | 2,400.00 | 200.00 | 1,600.00 | | 0024 | 711-01-04000 | Riprap (55 lb, 18" Thick) | 361 | SQYD | 115.00 | 41,515.00 | 100.00 | 36,100.00 | 125.00 | 45,125.00 | 120.00 | 43,320.00 | | 0025 | 711-04-00100 | Geotextile Fabric | 361 | SQYD | 8.00 | 2,888.00 | 4.00 | 1,444.00 | 5.00 | 1,805.00 | 4.00 | 1,444.00 | | 0026 | 713-01-00100 | Temporary Signs and Barricades | 1 | LUMP | 25,000.00 | 25,000.00 | 25,000.00 | 25,000.00 | 25,000.00 | 25,000.00 | 50,000.00 | 50,000.00 | | 0027 | 716-01-00100 | Mulch (Vegetative) | 1.9 | TON | 2,500.00 | 4,750.00 | 3,000.00 | 5,700.00 | 2,000.00 | 3,800.00 | 1,750.00 | 3,325.00 | | 0028 | 717-01-00100 | Seeding | 28 | LB | 30.00 | 840.00 | 34.00 | 952.00 | 50.00 | 1,400.00 | 30.00 | 840.00 | | 0029 | 718-01-00100 | Fertilizer | 930 | LB | 0.95 | 883.50 | 1.50 | 1,395.00 | 2.00 | 1,860.00 | 1.50 | 1,395.00 | | 0030 | 720-01-01000 | Erosion Control System (Slope Protection) (Type A) | 351 | SQYD | 3.10 | 1,088.10 | 4.00 | 1,404.00 | 5.00 | 1,755.00 | 3.50 | 1,228.50 | | 0031 | 727-01-00100 | Mobilization | 1 | LUMP | 125,000.00 | 125,000.00 | 145,000.00 | 145,000.00 | 115,000.00 | 115,000.00 | 120,000.00 | 120,000.00 | | 0032 | 729-16-00300 | Object Marker Assembly (Type 3) | 4 | EACH | 125.00 | 500.00 | 155.00 | 620.00 | 200.00 | 800.00 | 100.00 | 400.00 | | 0033 | 740-01-00100 | Construction Layout | 1 | LUMP | 15,800.00 | 15,800.00 | 18,000.00 | 18,000.00 | 15,000.00 | 15,000.00 | 40,000.00 | 40,000.00 | | 0034 | 804-01-00300 | Precast Concrete Piles (16") | 1,380 | LNFT | 145.00 | 200,100.00 | 163.00 | 224,940.00 | 155.00 | 213,900.00 | 140.00 | 193,200.00 | | 0035 | 805-01-00100 | Class A1 Concrete (Slab Span) | 101.92 | CUYD | 1,400.00 | 142,688.00 | 1,800.00 | 183,456.00 | 1,750.00 | 178,360.00 | 1,500.00 | 152,880.00 | | 0036 | 805-01-00300 | Class A1 Concrete (Bent Cap) | 27.14 | CUYD | 2,200.00 | 59,708.00 | 2,600.00 | 70,564.00 | 2,800.00 | 75,992.00 | 3,000.00 | 81,420.00 | | 0037 | 805-18-00100 | Concrete Finish (Class 2 Rubbed Finish) | 967 | SQFT | 3.00 | 2,901.00 | 5.00 | 4,835.00 | 3.00 | 2,901.00 | 2.00 | 1,934.00 | | 0038 | 805-18-00200 | Concrete Finish (Class 3 Special Finish) | 967 | SQFT | 3.50 | 3,384.50 | 5.00 | 4,835.00 | 3.00 | 2,901.00 | 3.00 | 2,901.00 | | 0039 | 806-01-00100 | Deformed Reinforcing Steel | 27,282 | LB | 1.50 | 40,923.00 | 1.80 | 49,107.60 | 2.00 | 54,564.00 | 1.60 | 43,651.20 | | 0040 | 810-01-00100 | Concrete Bridge Railing (Standard) | 80 | LNFT | 220.00 | 17,600.00 | 230.00 | 18,400.00 | 285.00 | 22,800.00 | 300.00 | 24,000.00 | | 0041 | 810-01-00200 | Concrete Bridge Railing (Slotted) | 80 | LNFT | 220.00 | 17,600.00 | 230.00 | 18,400.00 | 285.00 | 22,800.00 | 200.00 | 16,000.00 | | 0042 | 813-01-00100 | Concrete Approach Slabs (Cast-in-Place) | 580 | SQFT | 80.00 | 46,400.00 | 130.00 | 75,400.00 | 115.00 | 66,700.00 | 120.00 | 69,600.00 | | 0043 | 815-03-00300 | Joint Seal (Poured) | 140 | LNFT | 25.00 | 3,500.00 | 20.00 | 2,800.00 | 25.00 | 3,500.00 | 20.00 | 2,800.00 | | | | | | | | | | | | | | | | | | CONTRACTOR TOTAL | | | | 1,155,680.65 | | 1,226,492.30 | | 1,270,236.60 | | 1,451,491.90 |
|