Proposal:H.016147.6
Parish:St. Tammany
Routes:I-12
Description:I-12: AIRPORT RD - I-10
Type Construction:CLEARING AND GRUBBING, GRADING, MILLING ASPHALT CONCRETE, PAVEMENT PATCHING, CLASS II BASE COURSE, ASPHALT CONCRETE OVERLAY (SMA), CONCRETE PIER PROTECTION SYSTEM, AND RELATED WORK.
Estimated Construction Cost:$15,184,576.98
Maximum Number of Days Allowed for Construction:9999
Calculated Daily User Cost:$18,000.00
| Rank | License | Bidder | Construction Bid | Bidder's Proposed Contract Time | Total Bid |
| 1 | 62139 | Huey P. Stockstill, LLC | $16,995,518.85 | 260.00 | $21,675,518.85 |
| 2 | 06276 | Barriere Construction Co., LLC | $19,948,671.94 | 238.00 | $24,232,671.94 |
| 3 | 73475 | Madden Gulf Coast, LLC | $19,035,882.65 | 440.00 | $26,955,882.65 |
Line Number | Item Number | Item Description | Quantity | Unit of Measure | - 1 - Huey P. Stockstill, LLC | - 2 - Barriere Construction Co., LLC | - 3 - Madden Gulf Coast, LLC | | Unit Price | Total Amount | Unit Price | Total Amount | Unit Price | Total Amount | | 0001 | 201-01-00200 | Clearing and Grubbing (Selective) | 1 | LUMP | 450,000.00 | 450,000.00 | 500,000.00 | 500,000.00 | 725,000.00 | 725,000.00 | | 0002 | 202-02-02020 | Removal of Asphalt Pavement | 5,087.2 | SQYD | 10.00 | 50,872.00 | 20.25 | 103,015.80 | 20.00 | 101,744.00 | | 0003 | 202-02-06060 | Removal of Concrete Catch Basin | 1 | EACH | 1,500.00 | 1,500.00 | 682.00 | 682.00 | 1,500.00 | 1,500.00 | | 0004 | 202-02-06080 | Removal of Concrete Combination Curb and Gutter | 80 | LNFT | 20.00 | 1,600.00 | 63.00 | 5,040.00 | 50.00 | 4,000.00 | | 0005 | 202-02-06090 | Removal of Concrete Revetment | 1 | LUMP | 35,000.00 | 35,000.00 | 8,600.00 | 8,600.00 | 15,000.00 | 15,000.00 | | 0006 | 202-02-14500 | Removal of Guard Rail | 10,804 | LNFT | 7.00 | 75,628.00 | 11.50 | 124,246.00 | 6.50 | 70,226.00 | | 0007 | 202-02-32500 | Removal of Portland Cement Concrete Pavement | 3,191 | SQYD | 25.00 | 79,775.00 | 29.00 | 92,539.00 | 35.00 | 111,685.00 | | 0008 | 202-02-38300 | Removal of Sign and U-Channel Post | 71 | EACH | 50.00 | 3,550.00 | 18.50 | 1,313.50 | 35.00 | 2,485.00 | | 0009 | 203-05-00100 | Excavation and Embankment | 1 | LUMP | 165,000.00 | 165,000.00 | 234,000.00 | 234,000.00 | 335,000.00 | 335,000.00 | | 0010 | 204-05-00100 | Temporary Sediment Check Dams (Hay) | 30 | EACH | 140.00 | 4,200.00 | 141.00 | 4,230.00 | 125.00 | 3,750.00 | | 0011 | 204-06-00100 | Temporary Silt Fencing | 15,000 | LNFT | 2.25 | 33,750.00 | 2.35 | 35,250.00 | 2.25 | 33,750.00 | | 0012 | 302-02-12020 | Class II Base Course (12" Thick) (Crushed Stone) | 199.8 | SQYD | 100.00 | 19,980.00 | 149.00 | 29,770.20 | 100.00 | 19,980.00 | | 0013 | 302-03-00100 | Base Drain Outlet | 5 | EACH | 3,000.00 | 15,000.00 | 3,325.00 | 16,625.00 | 500.00 | 2,500.00 | | 0014 | 502-01-00200 | Asphalt Concrete, Drives, Turnouts and Miscellaneous | 2,277.4 | TON | 175.00 | 398,545.00 | 250.00 | 569,350.00 | 300.00 | 683,220.00 | | 0015 | 502-04-00100 | Asphalt Concrete (SMA) Wearing Course | 49,496.7 | TON | 195.00 | 9,651,856.50 | 175.00 | 8,661,922.50 | 163.00 | 8,067,962.10 | | 0016 | 509-01-00100 | Milling Asphalt Pavement | 417,341 | SQYD | 3.00 | 1,252,023.00 | 4.00 | 1,669,364.00 | 5.50 | 2,295,375.50 | | 0017 | 509-02-00100 | Contractor Retained Reclaimed Asphalt Pavement | -23,190 | CUYD | 0.01 | -231.90 | 0.01 | -231.90 | 0.01 | -231.90 | | 0018 | 510-01-00200 | Pavement Patching (12" Minimum Thickness) | 1,069 | SQYD | 125.00 | 133,625.00 | 172.00 | 183,868.00 | 200.00 | 213,800.00 | | 0019 | 510-01-00300 | Pavement Patching (18" Minimum Thickness) | 1,103 | SQYD | 155.00 | 170,965.00 | 187.00 | 206,261.00 | 256.00 | 282,368.00 | | 0020 | 511-01-00100 | Saw Cutting Asphalt Concrete Pavement | 18,536 | INLF | 0.55 | 10,194.80 | 0.80 | 14,828.80 | 1.00 | 18,536.00 | | 0021 | 511-02-00100 | Sawing and Sealing Longitudinal Joints in Asphalt Concrete Overlay | 58,779 | LNFT | 1.95 | 114,619.05 | 2.05 | 120,496.95 | 2.05 | 120,496.95 | | 0022 | 511-03-00100 | Sawing and Sealing Transverse Joints in Asphalt Concrete Overlay | 4,008 | LNFT | 2.00 | 8,016.00 | 4.15 | 16,633.20 | 4.15 | 16,633.20 | | 0023 | 511-04-00100 | Sawcuts in Asphalt Concrete Lifts | 62,787 | LNFT | 0.95 | 59,647.65 | 0.90 | 56,508.30 | 0.80 | 50,229.60 | | 0024 | 601-05-00100 | Saw Cutting Portland Cement Concrete Pavement | 8,280 | INLF | 1.10 | 9,108.00 | 1.00 | 8,280.00 | 0.90 | 7,452.00 | | 0025 | 602-02-00200 | Cleaning and Resealing Existing Longitudinal Pavement Joints | 3,941 | LNFT | 3.00 | 11,823.00 | 5.00 | 19,705.00 | 4.50 | 17,734.50 | | 0026 | 602-02-00300 | Cleaning and Resealing Existing Transverse Pavements Joints | 3,554 | LNFT | 3.00 | 10,662.00 | 5.00 | 17,770.00 | 4.50 | 15,993.00 | | 0027 | 602-03-00100 | Cleaning and Sealing Random Cracks | 850 | LNFT | 6.00 | 5,100.00 | 5.00 | 4,250.00 | 4.50 | 3,825.00 | | 0028 | 602-05-01280 | Full Depth Patching of Jointed Concrete Pavement (16.0 square yards and under) (12" Thick) | 13.3 | SQYD | 500.00 | 6,650.00 | 1,050.00 | 13,965.00 | 900.00 | 11,970.00 | | 0029 | 602-05-02280 | Full Depth Patching of Jointed Concrete Pavement (16.1 square yards to 48.0 square yards) (12" Thick) | 53.3 | SQYD | 400.00 | 21,320.00 | 1,050.00 | 55,965.00 | 865.00 | 46,104.50 | | 0030 | 602-05-03280 | Full Depth Patching of Jointed Concrete Pavement (48.1 square yards and over) (12" Thick) | 413.3 | SQYD | 330.00 | 136,389.00 | 1,050.00 | 433,965.00 | 700.00 | 289,310.00 | | 0031 | 602-11-00100 | Removal of Existing Shoulder Underdrain Systems | 450 | LNFT | 20.00 | 9,000.00 | 57.00 | 25,650.00 | 50.00 | 22,500.00 | | 0032 | 701-14-00100 | Cleaning Existing Pipes 24" RCP | 130 | LNFT | 40.00 | 5,200.00 | 125.00 | 16,250.00 | 200.00 | 26,000.00 | | 0033 | 702-04-00200 | Adjusting Catch Basins | 1 | EACH | 3,000.00 | 3,000.00 | 13,500.00 | 13,500.00 | 5,500.00 | 5,500.00 | | 0034 | 702-09-00100 | Cleaning Existing Catch Basin | 1 | EACH | 1,000.00 | 1,000.00 | 920.00 | 920.00 | 1,000.00 | 1,000.00 | | 0035 | 704-01-01020 | Guard Rail (Single Thrie Beam) (6'-3" post spacing) | 100 | LNFT | 45.00 | 4,500.00 | 57.00 | 5,700.00 | 40.06 | 4,006.00 | | 0036 | 704-03-00200 | Blocked Out Guard Rail - 31", (6'-3" Post Spacing) | 8,725.2 | LNFT | 35.00 | 305,382.00 | 34.00 | 296,656.80 | 32.00 | 279,206.40 | | 0037 | 704-04-00200 | Blocked Out Guard Rail – 31”, (Double Faced, 6’-3” Post Spacing) | 25 | LNFT | 50.00 | 1,250.00 | 46.00 | 1,150.00 | 45.00 | 1,125.00 | | 0038 | 704-05-00300 | Guard Rail Anchor Sections - 31", (Trailing End) | 260 | LNFT | 180.00 | 46,800.00 | 172.00 | 44,720.00 | 165.00 | 42,900.00 | | 0039 | 704-06-00200 | Guard Rail Bridge Attachments (Single Thrie Beam) | 25 | LNFT | 60.00 | 1,500.00 | 69.00 | 1,725.00 | 50.00 | 1,250.00 | | 0040 | 704-07-00200 | Guard Rail Transitions (Double Thrie Beam) | 700 | LNFT | 120.00 | 84,000.00 | 126.00 | 88,200.00 | 110.00 | 77,000.00 | | 0041 | 704-09-00100 | Guard Rail Anchor Block | 1 | EACH | 12,000.00 | 12,000.00 | 11,500.00 | 11,500.00 | 9,500.00 | 9,500.00 | | 0042 | 704-10-00205 | Guard Rail End Treatment, MASH, (TL-3 Tangent) | 19 | EACH | 3,800.00 | 72,200.00 | 4,000.00 | 76,000.00 | 3,225.00 | 61,275.00 | | 0043 | 704-10-00305 | Guard Rail End Treatment, MASH, (TL-3 Bi-Directional) | 2 | EACH | 12,000.00 | 24,000.00 | 9,750.00 | 19,500.00 | 10,600.00 | 21,200.00 | | 0044 | 704-10-00310 | Guard Rail End Treatment, NCHRP 350 - 31" (TL-3 Flared) | 19 | EACH | 3,500.00 | 66,500.00 | 4,000.00 | 76,000.00 | 2,950.00 | 56,050.00 | | 0045 | 706-03-00100 | Incidental Concrete Paving (4" Thick) | 1,746.1 | SQYD | 90.00 | 157,149.00 | 74.50 | 130,084.45 | 100.00 | 174,610.00 | | 0046 | 707-03-00100 | Combination Concrete Curb and Gutter | 80 | LNFT | 110.00 | 8,800.00 | 86.00 | 6,880.00 | 200.00 | 16,000.00 | | 0047 | 707-04-00100 | Asphalt Concrete Curb | 202.5 | LNFT | 110.00 | 22,275.00 | 97.00 | 19,642.50 | 110.00 | 22,275.00 | | 0048 | 712-01-00100 | Concrete Cast-in-Place Revetment (4" Thick) | 827 | SQYD | 200.00 | 165,400.00 | 86.00 | 71,122.00 | 125.00 | 103,375.00 | | 0049 | 713-01-00100 | Temporary Signs and Barricades | 1 | LUMP | 514,000.00 | 514,000.00 | 1,730,000.00 | 1,730,000.00 | 1,370,000.00 | 1,370,000.00 | | 0050 | 713-02-00300 | Temporary Pavement Markings (8" Width) | 36,179 | LNFT | 0.25 | 9,044.75 | 0.25 | 9,044.75 | 0.35 | 12,662.65 | | 0051 | 713-03-02000 | Temporary Pavement Markings (Broken Line) (4" Width) (10' Length) | 20.171 | MILE | 800.00 | 16,136.80 | 1,700.00 | 34,290.70 | 750.00 | 15,128.25 | | 0052 | 713-04-01000 | Temporary Pavement Markings (Solid Line) (4" Width) | 28.857 | MILE | 1,300.00 | 37,514.10 | 4,000.00 | 115,428.00 | 1,200.00 | 34,628.40 | | 0053 | 713-11-00100 | Portable Changeable Message Signs | 8 | EACH | 17,000.00 | 136,000.00 | 101,000.00 | 808,000.00 | 20,000.00 | 160,000.00 | | 0054 | 724-02-00100 | Rumble Strips (Shoulder/Edge) | 18.942 | MILE | 1,800.00 | 34,095.60 | 2,250.00 | 42,619.50 | 1,000.00 | 18,942.00 | | 0055 | 727-01-00100 | Mobilization | 1 | LUMP | 1,200,000.00 | 1,200,000.00 | 1,911,000.00 | 1,911,000.00 | 1,865,000.00 | 1,865,000.00 | | 0056 | 729-16-00300 | Object Marker Assembly (Type 3) | 82 | EACH | 100.00 | 8,200.00 | 286.00 | 23,452.00 | 90.00 | 7,380.00 | | 0057 | 731-01-00100 | Nonreflectorized Raised Pavement Markers | 13,177 | EACH | 16.00 | 210,832.00 | 12.50 | 164,712.50 | 15.00 | 197,655.00 | | 0058 | 731-02-00100 | Reflectorized Raised Pavement Markers | 18,836 | EACH | 8.00 | 150,688.00 | 7.00 | 131,852.00 | 7.50 | 141,270.00 | | 0059 | 732-01-02080 | Plastic Pavement Striping (24" Width) (Thermoplastic 125 mil) | 3,045 | LNFT | 13.00 | 39,585.00 | 18.50 | 56,332.50 | 12.00 | 36,540.00 | | 0060 | 732-02-02000 | Plastic Pavement Striping (Solid Line) (4" Width) (Thermoplastic 90 mil) | 28.857 | MILE | 6,000.00 | 173,142.00 | 6,300.00 | 181,799.10 | 5,000.00 | 144,285.00 | | 0061 | 732-02-02040 | Plastic Pavement Striping (Solid Line) (8" Width) (Thermoplastic 90 mil) | 3.497 | MILE | 8,000.00 | 27,976.00 | 17,200.00 | 60,148.40 | 7,500.00 | 26,227.50 | | 0062 | 732-03-02000 | Plastic Pavement Striping (Broken Line) (4" Width) (Thermoplastic 90 mil) | 19.05 | MILE | 1,300.00 | 24,765.00 | 2,865.00 | 54,578.25 | 1,250.00 | 23,812.50 | | 0063 | 732-03-02040 | Plastic Pavement Striping (Dotted Line)(8" W)(3' L)(Thermo 90 mil) | 3.355 | MILE | 6,500.00 | 21,807.50 | 17,200.00 | 57,706.00 | 6,000.00 | 20,130.00 | | 0064 | 732-03-02102 | Plastic Pav't Striping (Broken) (4" W) (Preformed Tape Retroreflectivity I or Thermo 90 mil)(Black and White Contrast) | 1.121 | MILE | 10,000.00 | 11,210.00 | 5,700.00 | 6,389.70 | 9,000.00 | 10,089.00 | | 0065 | 732-04-01020 | Plastic Pavement Legends and Symbols (Arrow - Straight) | 2 | EACH | 350.00 | 700.00 | 516.00 | 1,032.00 | 300.00 | 600.00 | | 0066 | 732-04-01080 | Plastic Pavement Legends and Symbols (Arrow - Left Turn) | 14 | EACH | 400.00 | 5,600.00 | 516.00 | 7,224.00 | 350.00 | 4,900.00 | | 0067 | 732-04-01100 | Plastic Pavement Legends and Symbols (Arrow - Right Turn) | 4 | EACH | 350.00 | 1,400.00 | 516.00 | 2,064.00 | 300.00 | 1,200.00 | | 0068 | 732-04-01120 | Plastic Pavement Legends and Symbols (Arrow - Merge) | 2 | EACH | 410.00 | 820.00 | 1,085.00 | 2,170.00 | 375.00 | 750.00 | | 0069 | 732-04-05040 | Plastic Pavement Legends and Symbols (EXIT ONLY) | 4 | EACH | 500.00 | 2,000.00 | 2,866.00 | 11,464.00 | 450.00 | 1,800.00 | | 0070 | 732-04-15020 | Plastic Pavement Legends and Symbols (ONLY) | 6 | EACH | 400.00 | 2,400.00 | 860.00 | 5,160.00 | 350.00 | 2,100.00 | | 0071 | 732-05-00100 | Removal of Existing Markings | 3.135 | MILE | 8,000.00 | 25,080.00 | 1,145.00 | 3,589.58 | 7,500.00 | 23,512.50 | | 0072 | 739-01-00100 | Hydro-Seeding | 5.37 | ACRE | 2,700.00 | 14,499.00 | 2,978.00 | 15,991.86 | 2,700.00 | 14,499.00 | | 0073 | 740-01-00100 | Construction Layout | 1 | LUMP | 150,000.00 | 150,000.00 | 58,000.00 | 58,000.00 | 90,000.00 | 90,000.00 | | 0074 | 810-06-00100 | Concrete Pier Protection System (Vehicle) Ramp F | 229 | LNFT | 1,100.00 | 251,900.00 | 1,490.00 | 341,210.00 | 1,400.00 | 320,600.00 | | | | | | | | | | | | | | | | CONTRACTOR TOTAL | | | | 16,995,518.85 | | 19,948,671.94 | | 19,035,882.65 |
|