Search


Bid Tabulations for the Letting of 6/10/2026 LA DOTD Headquarters

Proposal:H.016298.6
Parish:Avoyelles
Routes:LA 1
Description:LA 1:ATCHAFALAYA RIVER-ROSEWOOD CROSSING
Type Construction:CLASS II BASE COURSE, MILLING ASPHALT CONCRETE OVERLAY, PAVEMENT PATCHING AND RELATED WORK.
Estimated Construction Cost:$6,725,361.17
Rank License BidderConstruction Bid
112031R.J. Daigle & Sons Contractors, Inc$5,091,168.32
200046Barber Bros. Contracting Co., L.L.C$5,514,337.61
312487Diamond B Construction Co., L.L.C.$5,804,468.11
412312Gilchrist Construction Company, LLC$5,972,662.23


Line
Number
Item NumberItem DescriptionQuantityUnit of
Measure
- 1 -
R.J. Daigle & Sons Contractors, Inc
- 2 -
Barber Bros. Contracting Co., L.L.C
- 3 -
Diamond B Construction Co., L.L.C.
- 4 -
Gilchrist Construction Company, LLC
Unit PriceTotal
Amount
Unit PriceTotal
Amount
Unit PriceTotal
Amount
Unit PriceTotal
Amount
0001202-02-06102Removal of Incidental Concrete Paving 113     SQYD28.753,248.7530.003,390.0045.005,085.0028.003,164.00
0002202-02-14500Removal of Guard Rail 205     LNFT16.103,300.5015.003,075.0013.502,767.5014.002,870.00
0003203-07-00100Borrow (Vehicular Measurement) 727     CUYD79.3157,658.3770.0050,890.0012.008,724.0070.0050,890.00
0004302-02-12020Class II Base Course (12" Thick) (Crushed Stone) 266     SQYD123.0032,718.0095.0025,270.00130.0034,580.00150.0039,900.00
0005401-02-00100Aggregate Surface Course (Adjusted Vehicular Measurement) 130     CUYD152.6019,838.00150.0019,500.00130.0016,900.0085.0011,050.00
0006502-01-00100Asphalt Concrete 24,079.2   TON116.002,793,187.20124.002,985,820.80147.003,539,642.40136.003,274,771.20
0007502-01-00200Asphalt Concrete, Drives, Turnouts and Miscellaneous 937     TON215.00201,455.00245.00229,565.00147.00137,739.00200.00187,400.00
0008507-01-00100Asphalt Material (CRS-2P Emulsion) 52,839     GAL5.00264,195.005.00264,195.005.00264,195.004.80253,627.20
0009507-02-00200Aggregate (S2) 77,708     SQYD2.30178,728.402.40186,499.202.25174,843.002.25174,843.00
0010507-02-00300Aggregate (S3) 77,708     SQYD1.50116,562.001.60124,332.801.45112,676.601.50116,562.00
0011509-01-00100Milling Asphalt Pavement 82,491     SQYD2.23183,954.934.00329,964.002.75226,850.253.00247,473.00
0012509-02-00100Contractor Retained Reclaimed Asphalt Pavement -4,118     CUYD0.01-41.180.000.001.00-4,118.001.00-4,118.00
0013510-01-00200Pavement Patching (12" Minimum Thickness) 182     SQYD103.5318,842.46195.0035,490.00200.0036,400.00190.0034,580.00
0014510-01-00250Pavement Patching (14 inch Minimum Thickness) 1,219     SQYD107.60131,164.40170.00207,230.00190.00231,610.00190.00231,610.00
0015511-02-00100Sawing and Sealing Longitudinal Joints in Asphalt Concrete Overlay 47,314     LNFT2.0596,993.702.1099,359.401.6075,702.402.0094,628.00
0016511-03-00100Sawing and Sealing Transverse Joints in Asphalt Concrete Overlay 25     LNFT2.1754.2510.00250.002.2556.253.0075.00
0017511-04-00100Sawcuts in Asphalt Concrete Lifts 94,653     LNFT1.0195,599.531.0094,653.001.0094,653.001.25118,316.25
0018702-04-00150Adjusting Manholes w/Manhole Adjustment Rings 2     EACH402.50805.00500.001,000.002,100.004,200.002,500.005,000.00
0019704-03-00200Blocked Out Guard Rail - 31", (6'-3" Post Spacing) 56.3   LNFT40.252,266.0838.002,139.4037.002,083.1038.002,139.40
0020704-06-00200Guard Rail Bridge Attachments (Single Thrie Beam) 25     LNFT74.751,868.7570.001,750.0085.002,125.0087.002,175.00
0021704-07-00200Guard Rail Transitions (Double Thrie Beam) 50     LNFT143.757,187.50135.006,750.00135.006,750.00136.006,800.00
0022704-10-00310Guard Rail End Treatment, NCHRP 350 - 31" (TL-3 Flared) 2     EACH3,795.007,590.003,500.007,000.003,850.007,700.003,900.007,800.00
0023706-03-00700Incidental Concrete Paving (10" Thick) 42     SQYD224.259,418.50280.0011,760.00250.0010,500.00200.008,400.00
0024707-01-00100Concrete Curb 3,686.9   LNFT51.75190,797.0850.00184,345.0092.00339,194.8067.00247,022.30
0025713-01-00100Temporary Signs and Barricades 1     LUMP185,000.00185,000.00175,000.00175,000.0098,000.0098,000.00100,000.00100,000.00
0026713-03-01000Temporary Pavement Markings (Broken Line) (4" Width) (4' Length) 14.674 MILE460.196,752.83300.004,402.20165.002,421.21170.002,494.58
0027713-03-02000Temporary Pavement Markings (Broken Line) (4" Width) (10' Length) 14.424 MILE575.248,297.26500.007,212.00500.007,212.00500.007,212.00
0028713-04-01000Temporary Pavement Markings (Solid Line) (4" Width) 27.2   MILE977.5026,588.00850.0023,120.00850.0023,120.00850.0023,120.00
0029713-06-00200Temporary Reflectorized Raised Pavement Markers (Tabs) 2,571     EACH2.887,404.482.757,070.252.506,427.502.506,427.50
0030724-01-00100Rumble Strips (Centerline) 3.315 MILE345.521,145.40325.001,077.381,000.003,315.001,100.003,646.50
0031724-02-00100Rumble Strips (Shoulder/Edge) 6.631 MILE344.952,287.36325.002,155.081,000.006,631.001,100.007,294.10
0032727-01-00100Mobilization 1     LUMP285,000.00285,000.00275,000.00275,000.00195,000.00195,000.00570,000.00570,000.00
0033729-16-00300Object Marker Assembly (Type 3) 2     EACH115.00230.00110.00220.00135.00270.00135.00270.00
0034731-02-00100Reflectorized Raised Pavement Markers 1,046     EACH5.756,014.505.505,753.005.005,230.005.005,230.00
0035732-01-01040Plastic Pavement Striping (8" Width) (Thermoplastic 90 mil) 369     LNFT2.881,062.722.70996.302.50922.503.001,107.00
0036732-01-02080Plastic Pavement Striping (24" Width) (Thermoplastic 125 mil) 218     LNFT12.652,757.7012.002,616.0011.002,398.0012.002,616.00
0037732-02-02000Plastic Pavement Striping (Solid Line) (4" Width) (Thermoplastic 90 mil) 12.566 MILE6,327.0179,505.215,900.0074,139.405,500.0069,113.005,600.0070,369.60
0038732-03-02000Plastic Pavement Striping (Broken Line) (4" Width) (Thermoplastic 90 mil) 4.808 MILE3,048.7714,658.492,800.0013,462.402,700.0012,981.602,700.0012,981.60
0039732-04-01080Plastic Pavement Legends and Symbols (Arrow - Left Turn) 13     EACH345.004,485.00325.004,225.00300.003,900.00325.004,225.00
0040735-01-00100Mailboxes 3     EACH34.50103.5050.00150.0025.0075.0030.0090.00
0041735-02-00100Mailbox Supports (Single) 3     EACH293.25879.75270.00810.00200.00600.00300.00900.00
0042739-01-00100Hydro-Seeding 7.08  ACRE2,627.6718,603.902,500.0017,700.002,400.0016,992.002,500.0017,700.00
0043740-01-00100Construction Layout 1     LUMP23,000.0023,000.0025,000.0025,000.0019,000.0019,000.0020,000.0020,000.00
             
  CONTRACTOR TOTAL   5,091,168.32 5,514,337.61 5,804,468.11 5,972,662.23