Proposal:H.014232.6
Parish:Ouachita
Description:RUFFIN DRIVE OVER DRAIN TO YOUNGS BAYOU
Type Construction:CLEARING AND GRUBBING, REMOVAL OF TIMBER BRIDGE, GRADING, DRAINAGE STRUCTURES, MILLING ASPHALT CONCRETE, CLASS II BASE COURSE, LIME TREATMENT, ASPHALT CONCRETE OVERLAY, RIPRAP, PRECAST CONCRETE PILES, CONCRETE SLAB SPAN BRIDGE, AND RELATED WORK.
Estimated Construction Cost:$1,627,214.00
| Rank | License | Bidder | Construction Bid |
| 1 | 39613 | Baker Pile Driving and Site Work, LLC | $1,473,517.25 |
| 2 | 14788 | Louisiana Bridge, Inc. | $1,512,661.20 |
| 3 | 12487 | Diamond B Construction Co., L.L.C. | $1,518,139.40 |
| 4 | 56994 | Matt L. Guinn Construction, LLC | $1,855,994.70 |
| 5 | 49239 | WL Bass Construction Inc. | $1,903,792.50 |
| 6 | 39462 | JB JAMES CONSTRUCTION LLC | $1,942,319.00 |
| 7 | 12312 | Gilchrist Construction Company, LLC | $1,956,345.10 |
| 8 | 00044 | Guinn Construction, LLC | $2,067,253.00 |
Line Number | Item Number | Item Description | Quantity | Unit of Measure | - 1 - Baker Pile Driving and Site Work, LLC | - 2 - Louisiana Bridge, Inc. | - 3 - Diamond B Construction Co., L.L.C. | - 4 - Matt L. Guinn Construction, LLC | | Unit Price | Total Amount | Unit Price | Total Amount | Unit Price | Total Amount | Unit Price | Total Amount | | 0001 | 201-01-00100 | Clearing and Grubbing | 1 | LUMP | 19,746.05 | 19,746.05 | 29,000.00 | 29,000.00 | 22,000.00 | 22,000.00 | 35,000.00 | 35,000.00 | | 0002 | 202-02-03000 | Removal of Base – Soil Cement, Asphalt, or BCS | 1,306.1 | SQYD | 7.00 | 9,142.70 | 12.00 | 15,673.20 | 15.00 | 19,591.50 | 12.00 | 15,673.20 | | 0003 | 202-02-04501 | Removal of Bridge (Sta. 15+04.82, 20.15' Wide x 62.00' Long; TImber) | 1,249.3 | LUMP | 32,211.33 | 32,211.33 | 15,000.00 | 15,000.00 | 30,000.00 | 30,000.00 | 30,000.00 | 30,000.00 | | 0004 | 202-02-06100 | Removal of Concrete Walks and Drives | 181 | SQYD | 11.32 | 2,048.92 | 17.00 | 3,077.00 | 30.00 | 5,430.00 | 20.00 | 3,620.00 | | 0005 | 202-02-26000 | Removal of Manholes | 1 | EACH | 1,255.63 | 1,255.63 | 1,500.00 | 1,500.00 | 7,500.00 | 7,500.00 | 1,500.00 | 1,500.00 | | 0006 | 202-02-32120 | Removal of Pipe (Side Drain) (Side Drain) | 255 | LNFT | 25.02 | 6,380.10 | 30.00 | 7,650.00 | 25.00 | 6,375.00 | 15.00 | 3,825.00 | | 0007 | 203-02-00100 | Drainage Excavation | 912 | CUYD | 26.61 | 24,268.32 | 18.00 | 16,416.00 | 25.00 | 22,800.00 | 35.00 | 31,920.00 | | 0008 | 203-05-00100 | Excavation and Embankment | 1 | LUMP | 55,437.10 | 55,437.10 | 25,000.00 | 25,000.00 | 20,000.00 | 20,000.00 | 35,000.00 | 35,000.00 | | 0009 | 204-02-00100 | Temporary Hay Bales | 32 | EACH | 30.83 | 986.56 | 50.00 | 1,600.00 | 35.00 | 1,120.00 | 100.00 | 3,200.00 | | 0010 | 204-03-00100 | Temporary Slope Drains | 80 | LNFT | 47.42 | 3,793.60 | 50.00 | 4,000.00 | 95.00 | 7,600.00 | 10.00 | 800.00 | | 0011 | 204-05-00100 | Temporary Sediment Check Dams (Hay) | 4 | EACH | 289.05 | 1,156.20 | 250.00 | 1,000.00 | 150.00 | 600.00 | 400.00 | 1,600.00 | | 0012 | 204-06-00100 | Temporary Silt Fencing | 1,236 | LNFT | 4.32 | 5,339.52 | 4.25 | 5,253.00 | 2.00 | 2,472.00 | 5.00 | 6,180.00 | | 0013 | 302-01-00300 | Class II Base Course (Crushed Stone) | 380.4 | CUYD | 167.00 | 63,526.80 | 227.00 | 86,350.80 | 125.00 | 47,550.00 | 210.00 | 79,884.00 | | 0014 | 304-01-00100 | Lime | 22.84 | TON | 444.00 | 10,140.96 | 455.00 | 10,392.20 | 460.00 | 10,506.40 | 300.00 | 6,852.00 | | 0015 | 304-05-00100 | Lime Treatment (Type E) | 1,611 | SQYD | 13.33 | 21,474.63 | 15.00 | 24,165.00 | 7.00 | 11,277.00 | 18.00 | 28,998.00 | | 0016 | 401-02-00100 | Aggregate Surface Course (Adjusted Vehicular Measurement) | 4 | CUYD | 381.80 | 1,527.20 | 500.00 | 2,000.00 | 140.00 | 560.00 | 100.00 | 400.00 | | 0017 | 402-01-00101 | Traffic Maintenance Surfacing (Aggregate) (Vehicular Measurement) | 25 | CUYD | 187.97 | 4,699.25 | 240.00 | 6,000.00 | 95.00 | 2,375.00 | 100.00 | 2,500.00 | | 0018 | 502-01-00100 | Asphalt Concrete | 303.5 | TON | 425.00 | 128,987.50 | 300.00 | 91,050.00 | 190.00 | 57,665.00 | 350.00 | 106,225.00 | | 0019 | 509-01-00100 | Milling Asphalt Pavement | 1,243 | SQYD | 21.28 | 26,451.04 | 19.00 | 23,617.00 | 4.00 | 4,972.00 | 15.00 | 18,645.00 | | 0020 | 511-01-00100 | Saw Cutting Asphalt Concrete Pavement | 485 | INLF | 8.48 | 4,112.80 | 5.00 | 2,425.00 | 4.00 | 1,940.00 | 30.00 | 14,550.00 | | 0021 | 601-05-00100 | Saw Cutting Portland Cement Concrete Pavement | 468 | INLF | 8.79 | 4,113.72 | 6.00 | 2,808.00 | 4.00 | 1,872.00 | 40.00 | 18,720.00 | | 0022 | 701-05-01043 | Side Drain Pipe (18" RCP/RPVCP/CMP) | 64 | LNFT | 62.39 | 3,992.96 | 108.00 | 6,912.00 | 95.00 | 6,080.00 | 95.00 | 6,080.00 | | 0023 | 701-05-01062 | Side Drain Pipe (24" RCP/RPVCP/CMP) | 130 | LNFT | 74.49 | 9,683.70 | 120.00 | 15,600.00 | 100.00 | 13,000.00 | 135.00 | 17,550.00 | | 0024 | 701-05-02042 | Side Drain Pipe (Erosion) (18" RPVCP/CMP) | 50 | LNFT | 74.63 | 3,731.50 | 118.00 | 5,900.00 | 125.00 | 6,250.00 | 100.00 | 5,000.00 | | 0025 | 701-05-02062 | Side Drain Pipe (Erosion) (24" RPVCP/CMP) | 180 | LNFT | 67.95 | 12,231.00 | 95.00 | 17,100.00 | 90.00 | 16,200.00 | 135.00 | 24,300.00 | | 0026 | 701-17-00100 | Trench Excavation Safety Protection (Depth >5 feet) | 133 | LNFT | 73.87 | 9,824.71 | 5.00 | 665.00 | 30.00 | 3,990.00 | 25.00 | 3,325.00 | | 0027 | 702-02-00200 | Manholes (R-CB-11) | 1 | EACH | 5,462.76 | 5,462.76 | 8,500.00 | 8,500.00 | 15,000.00 | 15,000.00 | 7,500.00 | 7,500.00 | | 0028 | 702-03-00100 | Catch Basins (CB-01) | 1 | EACH | 6,575.76 | 6,575.76 | 9,000.00 | 9,000.00 | 10,000.00 | 10,000.00 | 8,000.00 | 8,000.00 | | 0029 | 704-03-00200 | Blocked Out Guard Rail - 31", (6'-3" Post Spacing) | 50 | LNFT | 28.42 | 1,421.00 | 40.00 | 2,000.00 | 35.50 | 1,775.00 | 45.00 | 2,250.00 | | 0030 | 704-07-00200 | Guard Rail Transitions (Double Thrie Beam) | 100 | LNFT | 91.06 | 9,106.00 | 155.00 | 15,500.00 | 135.00 | 13,500.00 | 100.00 | 10,000.00 | | 0031 | 704-10-00310 | Guard Rail End Treatment, NCHRP 350 - 31" (TL-3 Flared) | 4 | EACH | 3,204.05 | 12,816.20 | 4,300.00 | 17,200.00 | 3,750.00 | 15,000.00 | 4,000.00 | 16,000.00 | | 0032 | 706-02-00200 | Concrete Drive (6" Thick) | 174.5 | SQYD | 111.08 | 19,383.46 | 80.00 | 13,960.00 | 150.00 | 26,175.00 | 95.00 | 16,577.50 | | 0033 | 711-01-04000 | Riprap (55 lb, 18" Thick) | 670 | SQYD | 98.18 | 65,780.60 | 95.00 | 63,650.00 | 105.00 | 70,350.00 | 135.00 | 90,450.00 | | 0034 | 711-04-00100 | Geotextile Fabric | 670 | SQYD | 4.98 | 3,336.60 | 4.50 | 3,015.00 | 1.00 | 670.00 | 5.00 | 3,350.00 | | 0035 | 713-01-00100 | Temporary Signs and Barricades | 1 | LUMP | 16,049.20 | 16,049.20 | 18,000.00 | 18,000.00 | 80,000.00 | 80,000.00 | 30,000.00 | 30,000.00 | | 0036 | 716-01-00100 | Mulch (Vegetative) | 1.6 | TON | 2,180.00 | 3,488.00 | 3,400.00 | 5,440.00 | 1,500.00 | 2,400.00 | 3,000.00 | 4,800.00 | | 0037 | 717-01-00100 | Seeding | 41 | LB | 28.85 | 1,182.85 | 30.00 | 1,230.00 | 25.00 | 1,025.00 | 30.00 | 1,230.00 | | 0038 | 718-01-00100 | Fertilizer | 810 | LB | 1.44 | 1,166.40 | 2.00 | 1,620.00 | 0.75 | 607.50 | 1.00 | 810.00 | | 0039 | 726-01-00100 | Bedding Material | 3.2 | CUYD | 332.00 | 1,062.40 | 430.00 | 1,376.00 | 180.00 | 576.00 | 200.00 | 640.00 | | 0040 | 727-01-00100 | Mobilization | 1 | LUMP | 117,760.91 | 117,760.91 | 145,000.00 | 145,000.00 | 150,000.00 | 150,000.00 | 150,000.00 | 150,000.00 | | 0041 | 729-16-00300 | Object Marker Assembly (Type 3) | 4 | EACH | 183.05 | 732.20 | 155.00 | 620.00 | 135.00 | 540.00 | 160.00 | 640.00 | | 0042 | 740-01-00100 | Construction Layout | 1 | LUMP | 15,163.35 | 15,163.35 | 15,000.00 | 15,000.00 | 64,000.00 | 64,000.00 | 30,000.00 | 30,000.00 | | 0043 | 804-01-00300 | Precast Concrete Piles (16") | 1,872 | LNFT | 132.03 | 247,160.16 | 143.00 | 267,696.00 | 150.00 | 280,800.00 | 155.00 | 290,160.00 | | 0044 | 805-12-00500 | Bridge Superstructure and Substructure (28' Roadway, 90 Degree Crossing) | 2,800 | SQFT | 142.96 | 400,288.00 | 150.00 | 420,000.00 | 140.00 | 392,000.00 | 225.00 | 630,000.00 | | 0045 | 805-18-00100 | Concrete Finish (Class 2 Rubbed Finish) | 1,190 | SQFT | 4.78 | 5,688.20 | 3.00 | 3,570.00 | 3.00 | 3,570.00 | 3.00 | 3,570.00 | | 0046 | 805-18-00200 | Concrete Finish (Class 3 Special Finish) | 1,190 | SQFT | 4.78 | 5,688.20 | 3.00 | 3,570.00 | 3.50 | 4,165.00 | 3.00 | 3,570.00 | | 0047 | 813-01-00100 | Concrete Approach Slabs (Cast-in-Place) (28' Clear Roadway; 90 Degree Crossing) | 580 | SQFT | 117.14 | 67,941.20 | 132.00 | 76,560.00 | 97.00 | 56,260.00 | 95.00 | 55,100.00 | | | | | | | | | | | | | | | | | | CONTRACTOR TOTAL | | | | 1,473,517.25 | | 1,512,661.20 | | 1,518,139.40 | | 1,855,994.70 |
Line Number | Item Number | Item Description | Quantity | Unit of Measure | - 5 - WL Bass Construction Inc. | - 6 - JB JAMES CONSTRUCTION LLC | - 7 - Gilchrist Construction Company, LLC | - 8 - Guinn Construction, LLC | | Unit Price | Total Amount | Unit Price | Total Amount | Unit Price | Total Amount | Unit Price | Total Amount | | 0001 | 201-01-00100 | Clearing and Grubbing | 1 | LUMP | 35,500.00 | 35,500.00 | 200,000.00 | 200,000.00 | 65,000.00 | 65,000.00 | 30,000.00 | 30,000.00 | | 0002 | 202-02-03000 | Removal of Base – Soil Cement, Asphalt, or BCS | 1,306.1 | SQYD | 5.00 | 6,530.50 | 10.00 | 13,061.00 | 15.00 | 19,591.50 | 15.00 | 19,591.50 | | 0003 | 202-02-04501 | Removal of Bridge (Sta. 15+04.82, 20.15' Wide x 62.00' Long; TImber) | 1,249.3 | LUMP | 67,700.00 | 67,700.00 | 150,000.00 | 150,000.00 | 57,000.00 | 57,000.00 | 40,000.00 | 40,000.00 | | 0004 | 202-02-06100 | Removal of Concrete Walks and Drives | 181 | SQYD | 2.00 | 362.00 | 30.00 | 5,430.00 | 32.00 | 5,792.00 | 15.00 | 2,715.00 | | 0005 | 202-02-26000 | Removal of Manholes | 1 | EACH | 1,500.00 | 1,500.00 | 1,500.00 | 1,500.00 | 5,000.00 | 5,000.00 | 2,500.00 | 2,500.00 | | 0006 | 202-02-32120 | Removal of Pipe (Side Drain) (Side Drain) | 255 | LNFT | 20.00 | 5,100.00 | 30.00 | 7,650.00 | 70.00 | 17,850.00 | 25.00 | 6,375.00 | | 0007 | 203-02-00100 | Drainage Excavation | 912 | CUYD | 22.00 | 20,064.00 | 28.00 | 25,536.00 | 28.00 | 25,536.00 | 30.00 | 27,360.00 | | 0008 | 203-05-00100 | Excavation and Embankment | 1 | LUMP | 44,000.00 | 44,000.00 | 60,000.00 | 60,000.00 | 100,000.00 | 100,000.00 | 50,000.00 | 50,000.00 | | 0009 | 204-02-00100 | Temporary Hay Bales | 32 | EACH | 35.00 | 1,120.00 | 35.00 | 1,120.00 | 35.00 | 1,120.00 | 150.00 | 4,800.00 | | 0010 | 204-03-00100 | Temporary Slope Drains | 80 | LNFT | 200.00 | 16,000.00 | 75.00 | 6,000.00 | 20.00 | 1,600.00 | 10.00 | 800.00 | | 0011 | 204-05-00100 | Temporary Sediment Check Dams (Hay) | 4 | EACH | 150.00 | 600.00 | 150.00 | 600.00 | 200.00 | 800.00 | 600.00 | 2,400.00 | | 0012 | 204-06-00100 | Temporary Silt Fencing | 1,236 | LNFT | 3.00 | 3,708.00 | 5.00 | 6,180.00 | 4.00 | 4,944.00 | 4.00 | 4,944.00 | | 0013 | 302-01-00300 | Class II Base Course (Crushed Stone) | 380.4 | CUYD | 230.00 | 87,492.00 | 175.00 | 66,570.00 | 200.00 | 76,080.00 | 250.00 | 95,100.00 | | 0014 | 304-01-00100 | Lime | 22.84 | TON | 400.00 | 9,136.00 | 300.00 | 6,852.00 | 400.00 | 9,136.00 | 1,000.00 | 22,840.00 | | 0015 | 304-05-00100 | Lime Treatment (Type E) | 1,611 | SQYD | 7.00 | 11,277.00 | 8.00 | 12,888.00 | 6.00 | 9,666.00 | 16.00 | 25,776.00 | | 0016 | 401-02-00100 | Aggregate Surface Course (Adjusted Vehicular Measurement) | 4 | CUYD | 170.00 | 680.00 | 1,000.00 | 4,000.00 | 600.00 | 2,400.00 | 500.00 | 2,000.00 | | 0017 | 402-01-00101 | Traffic Maintenance Surfacing (Aggregate) (Vehicular Measurement) | 25 | CUYD | 130.00 | 3,250.00 | 250.00 | 6,250.00 | 200.00 | 5,000.00 | 100.00 | 2,500.00 | | 0018 | 502-01-00100 | Asphalt Concrete | 303.5 | TON | 300.00 | 91,050.00 | 300.00 | 91,050.00 | 300.00 | 91,050.00 | 375.00 | 113,812.50 | | 0019 | 509-01-00100 | Milling Asphalt Pavement | 1,243 | SQYD | 19.00 | 23,617.00 | 20.00 | 24,860.00 | 15.00 | 18,645.00 | 18.00 | 22,374.00 | | 0020 | 511-01-00100 | Saw Cutting Asphalt Concrete Pavement | 485 | INLF | 1.00 | 485.00 | 1.00 | 485.00 | 10.00 | 4,850.00 | 10.00 | 4,850.00 | | 0021 | 601-05-00100 | Saw Cutting Portland Cement Concrete Pavement | 468 | INLF | 2.00 | 936.00 | 1.50 | 702.00 | 10.00 | 4,680.00 | 12.50 | 5,850.00 | | 0022 | 701-05-01043 | Side Drain Pipe (18" RCP/RPVCP/CMP) | 64 | LNFT | 80.00 | 5,120.00 | 170.00 | 10,880.00 | 175.00 | 11,200.00 | 125.00 | 8,000.00 | | 0023 | 701-05-01062 | Side Drain Pipe (24" RCP/RPVCP/CMP) | 130 | LNFT | 130.00 | 16,900.00 | 170.00 | 22,100.00 | 190.00 | 24,700.00 | 225.00 | 29,250.00 | | 0024 | 701-05-02042 | Side Drain Pipe (Erosion) (18" RPVCP/CMP) | 50 | LNFT | 85.00 | 4,250.00 | 150.00 | 7,500.00 | 210.00 | 10,500.00 | 125.00 | 6,250.00 | | 0025 | 701-05-02062 | Side Drain Pipe (Erosion) (24" RPVCP/CMP) | 180 | LNFT | 110.00 | 19,800.00 | 180.00 | 32,400.00 | 210.00 | 37,800.00 | 225.00 | 40,500.00 | | 0026 | 701-17-00100 | Trench Excavation Safety Protection (Depth >5 feet) | 133 | LNFT | 300.00 | 39,900.00 | 1.00 | 133.00 | 50.00 | 6,650.00 | 10.00 | 1,330.00 | | 0027 | 702-02-00200 | Manholes (R-CB-11) | 1 | EACH | 12,000.00 | 12,000.00 | 17,000.00 | 17,000.00 | 20,000.00 | 20,000.00 | 6,500.00 | 6,500.00 | | 0028 | 702-03-00100 | Catch Basins (CB-01) | 1 | EACH | 6,500.00 | 6,500.00 | 10,000.00 | 10,000.00 | 15,000.00 | 15,000.00 | 7,500.00 | 7,500.00 | | 0029 | 704-03-00200 | Blocked Out Guard Rail - 31", (6'-3" Post Spacing) | 50 | LNFT | 35.00 | 1,750.00 | 25.00 | 1,250.00 | 26.00 | 1,300.00 | 50.00 | 2,500.00 | | 0030 | 704-07-00200 | Guard Rail Transitions (Double Thrie Beam) | 100 | LNFT | 120.00 | 12,000.00 | 85.00 | 8,500.00 | 86.00 | 8,600.00 | 150.00 | 15,000.00 | | 0031 | 704-10-00310 | Guard Rail End Treatment, NCHRP 350 - 31" (TL-3 Flared) | 4 | EACH | 3,200.00 | 12,800.00 | 3,000.00 | 12,000.00 | 3,100.00 | 12,400.00 | 5,500.00 | 22,000.00 | | 0032 | 706-02-00200 | Concrete Drive (6" Thick) | 174.5 | SQYD | 160.00 | 27,920.00 | 100.00 | 17,450.00 | 180.00 | 31,410.00 | 250.00 | 43,625.00 | | 0033 | 711-01-04000 | Riprap (55 lb, 18" Thick) | 670 | SQYD | 100.00 | 67,000.00 | 140.00 | 93,800.00 | 105.00 | 70,350.00 | 135.00 | 90,450.00 | | 0034 | 711-04-00100 | Geotextile Fabric | 670 | SQYD | 5.00 | 3,350.00 | 4.00 | 2,680.00 | 7.00 | 4,690.00 | 5.00 | 3,350.00 | | 0035 | 713-01-00100 | Temporary Signs and Barricades | 1 | LUMP | 50,000.00 | 50,000.00 | 40,000.00 | 40,000.00 | 75,000.00 | 75,000.00 | 25,000.00 | 25,000.00 | | 0036 | 716-01-00100 | Mulch (Vegetative) | 1.6 | TON | 1,500.00 | 2,400.00 | 1,500.00 | 2,400.00 | 3,700.00 | 5,920.00 | 3,500.00 | 5,600.00 | | 0037 | 717-01-00100 | Seeding | 41 | LB | 25.00 | 1,025.00 | 25.00 | 1,025.00 | 13.00 | 533.00 | 50.00 | 2,050.00 | | 0038 | 718-01-00100 | Fertilizer | 810 | LB | 1.00 | 810.00 | 0.70 | 567.00 | 1.00 | 810.00 | 2.00 | 1,620.00 | | 0039 | 726-01-00100 | Bedding Material | 3.2 | CUYD | 200.00 | 640.00 | 300.00 | 960.00 | 88.00 | 281.60 | 500.00 | 1,600.00 | | 0040 | 727-01-00100 | Mobilization | 1 | LUMP | 190,300.00 | 190,300.00 | 190,000.00 | 190,000.00 | 190,000.00 | 190,000.00 | 200,000.00 | 200,000.00 | | 0041 | 729-16-00300 | Object Marker Assembly (Type 3) | 4 | EACH | 100.00 | 400.00 | 150.00 | 600.00 | 150.00 | 600.00 | 200.00 | 800.00 | | 0042 | 740-01-00100 | Construction Layout | 1 | LUMP | 50,000.00 | 50,000.00 | 40,000.00 | 40,000.00 | 25,000.00 | 25,000.00 | 20,000.00 | 20,000.00 | | 0043 | 804-01-00300 | Precast Concrete Piles (16") | 1,872 | LNFT | 170.00 | 318,240.00 | 175.00 | 327,600.00 | 160.00 | 299,520.00 | 160.00 | 299,520.00 | | 0044 | 805-12-00500 | Bridge Superstructure and Substructure (28' Roadway, 90 Degree Crossing) | 2,800 | SQFT | 185.00 | 518,000.00 | 120.00 | 336,000.00 | 175.00 | 490,000.00 | 240.00 | 672,000.00 | | 0045 | 805-18-00100 | Concrete Finish (Class 2 Rubbed Finish) | 1,190 | SQFT | 1.00 | 1,190.00 | 1.00 | 1,190.00 | 3.00 | 3,570.00 | 4.00 | 4,760.00 | | 0046 | 805-18-00200 | Concrete Finish (Class 3 Special Finish) | 1,190 | SQFT | 1.00 | 1,190.00 | 5.00 | 5,950.00 | 3.00 | 3,570.00 | 4.00 | 4,760.00 | | 0047 | 813-01-00100 | Concrete Approach Slabs (Cast-in-Place) (28' Clear Roadway; 90 Degree Crossing) | 580 | SQFT | 190.00 | 110,200.00 | 120.00 | 69,600.00 | 140.00 | 81,200.00 | 115.00 | 66,700.00 | | | | | | | | | | | | | | | | | | CONTRACTOR TOTAL | | | | 1,903,792.50 | | 1,942,319.00 | | 1,956,345.10 | | 2,067,253.00 |
|