Proposal:H.016622.6
Parish:St. Martin
Routes:LA 92-1
Description:LA 92-1: LA 31 - LA 347
Type Construction:MILLING ASPHALT CONCRETE, IN-PLACE CEMENT STABLILIZED SUBGRADE, IN-PLACE CEMENT STABILIZED BASE COURSE, LIME TREATMENT, ASPHALT CONCRETE OVERLAY, ROADWAY REINFORCING MESH, AND RELATED WORK.
Estimated Construction Cost:$1,736,045.59
| Rank | License | Bidder | Construction Bid |
| 1 | 51821 | Elliott Construction, LLC | $1,434,769.56 |
| 2 | 06276 | Barriere Construction Co., LLC | $1,754,069.09 |
| 3 | 34356 | Prairie Contractors LLC | $1,795,088.03 |
| 4 | 33663 | Glenn Lege Construction LLC | $1,859,503.06 |
Line Number | Item Number | Item Description | Quantity | Unit of Measure | - 1 - Elliott Construction, LLC | - 2 - Barriere Construction Co., LLC | - 3 - Prairie Contractors LLC | - 4 - Glenn Lege Construction LLC | | Unit Price | Total Amount | Unit Price | Total Amount | Unit Price | Total Amount | Unit Price | Total Amount | | 0001 | 202-02-02020 | Removal of Asphalt Pavement (Removal of Guard Rail Pads) | 555.8 | SQYD | 20.00 | 11,116.00 | 9.00 | 5,002.20 | 45.00 | 25,011.00 | 10.02 | 5,569.12 | | 0002 | 202-02-04560 | Removal of Bridge Joint (Poured Joint Seals) | 300 | LNFT | 5.50 | 1,650.00 | 22.00 | 6,600.00 | 10.00 | 3,000.00 | 5.81 | 1,743.00 | | 0003 | 202-02-14500 | Removal of Guard Rail | 588.3 | LNFT | 14.00 | 8,236.20 | 8.50 | 5,000.55 | 16.00 | 9,412.80 | 9.88 | 5,812.40 | | 0004 | 203-07-00100 | Borrow (Vehicular Measurement) | 356 | CUYD | 45.00 | 16,020.00 | 20.00 | 7,120.00 | 60.00 | 21,360.00 | 37.68 | 13,414.08 | | 0005 | 204-05-00100 | Temporary Sediment Check Dams (Hay) | 8 | EACH | 155.00 | 1,240.00 | 139.00 | 1,112.00 | 155.00 | 1,240.00 | 174.23 | 1,393.84 | | 0006 | 204-06-00100 | Temporary Silt Fencing | 1,030 | LNFT | 2.75 | 2,832.50 | 2.50 | 2,575.00 | 2.48 | 2,554.40 | 2.62 | 2,698.60 | | 0007 | 303-01-00200 | In-Place Cement Stabilized Base Course (8-1/2" Thick) | 9,785 | SQYD | 13.00 | 127,205.00 | 17.00 | 166,345.00 | 15.00 | 146,775.00 | 14.18 | 138,751.30 | | 0008 | 303-02-00100 | Removal of Existing Patches | 150 | SQYD | 30.00 | 4,500.00 | 117.00 | 17,550.00 | 25.00 | 3,750.00 | 35.72 | 5,358.00 | | 0009 | 304-01-00100 | Lime | 46.24 | TON | 385.00 | 17,802.40 | 525.00 | 24,276.00 | 375.00 | 17,340.00 | 298.16 | 13,786.92 | | 0010 | 304-03-00400 | Lime Treatment (Type C) (12" Thick) | 4,892 | SQYD | 7.50 | 36,690.00 | 6.50 | 31,798.00 | 13.00 | 63,596.00 | 9.47 | 46,327.24 | | 0011 | 309-01-12000 | In-Place Cement Treated Subgrade (12" Thick) | 9,785 | SQYD | 14.00 | 136,990.00 | 17.00 | 166,345.00 | 15.00 | 146,775.00 | 15.49 | 151,569.65 | | 0012 | 401-02-00100 | Aggregate Surface Course (Adjusted Vehicular Measurement) | 1,359 | CUYD | 65.00 | 88,335.00 | 30.00 | 40,770.00 | 70.00 | 95,130.00 | 92.24 | 125,354.16 | | 0013 | 402-01-00101 | Traffic Maintenance Surfacing (Aggregate) (Vehicular Measurement) | 100 | CUYD | 70.00 | 7,000.00 | 25.00 | 2,500.00 | 50.00 | 5,000.00 | 105.85 | 10,585.00 | | 0014 | 502-01-00100 | Asphalt Concrete | 3,473.3 | TON | 140.00 | 486,262.00 | 173.00 | 600,880.90 | 141.00 | 489,735.30 | 144.32 | 501,266.66 | | 0015 | 502-01-00200 | Asphalt Concrete, Drives, Turnouts and Miscellaneous | 235.7 | TON | 195.00 | 45,961.50 | 251.00 | 59,160.70 | 230.00 | 54,211.00 | 209.60 | 49,402.72 | | 0016 | 509-01-00100 | Milling Asphalt Pavement | 11,476 | SQYD | 3.50 | 40,166.00 | 5.00 | 57,380.00 | 5.75 | 65,987.00 | 2.57 | 29,493.32 | | 0017 | 509-02-00100 | Contractor Retained Reclaimed Asphalt Pavement | -917 | CUYD | 0.01 | -9.17 | 0.01 | -9.17 | 0.01 | -9.17 | 0.01 | -9.17 | | 0018 | 510-01-00300 | Pavement Patching (18" Minimum Thickness) | 80 | SQYD | 245.00 | 19,600.00 | 242.00 | 19,360.00 | 300.00 | 24,000.00 | 350.12 | 28,009.60 | | 0019 | 511-03-00100 | Sawing and Sealing Transverse Joints in Asphalt Concrete Overlay | 72 | LNFT | 11.00 | 792.00 | 45.00 | 3,240.00 | 15.00 | 1,080.00 | 11.62 | 836.64 | | 0020 | 602-12-00100 | Undersealing Pavement | 4 | TON | 4,400.00 | 17,600.00 | 4,800.00 | 19,200.00 | 5,000.00 | 20,000.00 | 4,646.00 | 18,584.00 | | 0021 | 602-14-00100 | Holes | 8 | EACH | 550.00 | 4,400.00 | 700.00 | 5,600.00 | 625.00 | 5,000.00 | 580.75 | 4,646.00 | | 0022 | 704-03-00200 | Blocked Out Guard Rail - 31", (6'-3" Post Spacing) | 300 | LNFT | 38.00 | 11,400.00 | 34.50 | 10,350.00 | 45.00 | 13,500.00 | 40.08 | 12,024.00 | | 0023 | 704-06-00200 | Guard Rail Bridge Attachments (Single Thrie Beam) | 50 | LNFT | 50.00 | 2,500.00 | 46.00 | 2,300.00 | 100.00 | 5,000.00 | 53.43 | 2,671.50 | | 0024 | 704-07-00200 | Guard Rail Transitions (Double Thrie Beam) | 100 | LNFT | 132.00 | 13,200.00 | 120.00 | 12,000.00 | 165.00 | 16,500.00 | 139.38 | 13,938.00 | | 0025 | 704-10-00205 | Guard Rail End Treatment, MASH, (TL-3 Tangent) | 4 | EACH | 3,825.00 | 15,300.00 | 3,475.00 | 13,900.00 | 5,000.00 | 20,000.00 | 4,036.21 | 16,144.84 | | 0026 | 713-01-00100 | Temporary Signs and Barricades | 1 | LUMP | 25,000.00 | 25,000.00 | 111,000.00 | 111,000.00 | 175,000.00 | 175,000.00 | 169,541.83 | 169,541.83 | | 0027 | 713-03-01000 | Temporary Pavement Markings (Broken Line) (4" Width) (4' Length) | 2.409 | MILE | 750.00 | 1,806.75 | 700.00 | 1,686.30 | 650.00 | 1,565.85 | 793.86 | 1,912.41 | | 0028 | 713-03-02000 | Temporary Pavement Markings (Broken Line) (4" Width) (10' Length) | 2.409 | MILE | 770.00 | 1,854.93 | 100.00 | 240.90 | 1.00 | 2.41 | 696.90 | 1,678.83 | | 0029 | 713-04-01000 | Temporary Pavement Markings (Solid Line) (4" Width) | 6.543 | MILE | 1,155.00 | 7,557.17 | 100.00 | 654.30 | 1.00 | 6.54 | 1,045.35 | 6,839.73 | | 0030 | 722-02-00100 | Project Site Laboratory (Equipped) | 1 | EACH | 8,000.00 | 8,000.00 | 12,000.00 | 12,000.00 | 20,000.00 | 20,000.00 | 9,989.41 | 9,989.41 | | 0031 | 724-01-00100 | Rumble Strips (Centerline) | 0.737 | MILE | 1,100.00 | 810.70 | 4,278.00 | 3,152.89 | 1,200.00 | 884.40 | 1,161.50 | 856.03 | | 0032 | 724-02-00100 | Rumble Strips (Shoulder/Edge) | 1.475 | MILE | 1,100.00 | 1,622.50 | 2,364.00 | 3,486.90 | 1,200.00 | 1,770.00 | 1,161.50 | 1,713.21 | | 0033 | 724-03-00100 | Rumble Strips (Intersection) | 1 | EACH | 4,675.00 | 4,675.00 | 1,000.00 | 1,000.00 | 5,500.00 | 5,500.00 | 4,936.38 | 4,936.38 | | 0034 | 727-01-00100 | Mobilization | 1 | LUMP | 125,000.00 | 125,000.00 | 152,000.00 | 152,000.00 | 175,000.00 | 175,000.00 | 171,679.80 | 171,679.80 | | 0035 | 729-16-00200 | Object Marker Assembly (Type 2) | 2 | EACH | 85.00 | 170.00 | 75.00 | 150.00 | 145.00 | 290.00 | 174.23 | 348.46 | | 0036 | 729-16-00300 | Object Marker Assembly (Type 3) | 4 | EACH | 95.00 | 380.00 | 85.00 | 340.00 | 155.00 | 620.00 | 98.73 | 394.92 | | 0037 | 731-02-00100 | Reflectorized Raised Pavement Markers | 107 | EACH | 7.00 | 749.00 | 6.00 | 642.00 | 7.50 | 802.50 | 5.81 | 621.67 | | 0038 | 732-02-02000 | Plastic Pavement Striping (Solid Line) (4" Width) (Thermoplastic 90 mil) | 2.181 | MILE | 6,450.00 | 14,067.45 | 5,850.00 | 12,758.85 | 5,500.00 | 11,995.50 | 5,226.75 | 11,399.54 | | 0039 | 732-03-02000 | Plastic Pavement Striping (Broken Line) (4" Width) (Thermoplastic 90 mil) | 0.803 | MILE | 2,975.00 | 2,388.93 | 2,700.00 | 2,168.10 | 1,500.00 | 1,204.50 | 1,277.65 | 1,025.95 | | 0040 | 732-05-00100 | Removal of Existing Markings | 0.069 | MILE | 5,500.00 | 379.50 | 5,000.00 | 345.00 | 15,000.00 | 1,035.00 | 12,195.75 | 841.51 | | 0041 | 735-01-00100 | Mailboxes | 1 | EACH | 33.00 | 33.00 | 30.00 | 30.00 | 10.00 | 10.00 | 34.85 | 34.85 | | 0042 | 735-02-00100 | Mailbox Supports (Single) | 1 | EACH | 280.00 | 280.00 | 255.00 | 255.00 | 1,000.00 | 1,000.00 | 296.18 | 296.18 | | 0043 | 739-01-00100 | Hydro-Seeding | 0.37 | ACRE | 7,085.00 | 2,621.45 | 6,441.00 | 2,383.17 | 6,500.00 | 2,405.00 | 5,059.49 | 1,872.01 | | 0044 | 740-01-00100 | Construction Layout | 1 | LUMP | 5,000.00 | 5,000.00 | 11,300.00 | 11,300.00 | 6,000.00 | 6,000.00 | 123,577.54 | 123,577.54 | | 0045 | 815-03-00300 | Joint Seal (Poured) | 300 | LNFT | 5.50 | 1,650.00 | 65.00 | 19,500.00 | 10.00 | 3,000.00 | 5.81 | 1,743.00 | | 0046 | NS-500-00180 | Roadway Reinforcing Mesh (Complete Road System) | 10,381 | SQYD | 8.75 | 90,833.75 | 9.50 | 98,619.50 | 8.00 | 83,048.00 | 10.98 | 113,983.38 | | 0047 | NS-700-00810 | Impact Attenuator (Construction Zone)(Test Level 3) | 4 | EACH | 5,775.00 | 23,100.00 | 10,000.00 | 40,000.00 | 12,000.00 | 48,000.00 | 8,711.25 | 34,845.00 | | | | | | | | | | | | | | | | | | CONTRACTOR TOTAL | | | | 1,434,769.56 | | 1,754,069.09 | | 1,795,088.03 | | 1,859,503.06 |
|