Proposal:H.016158.6
Parish:St. Mary
Routes:US 90-W & LA 182
Description:LA 182: US 90 - GREENWOOD ST. OVERPASS
Type Construction:MILLING ASPHALT CONCRETE, PAVEMENT PATCHING, ASPHALT CONCRETE OVERLAY, ROADWAY REINFORCING MESH, CURB RAMPS, AND RELATED WORK.
Estimated Construction Cost:$7,515,047.45
| Rank | License | Bidder | Construction Bid |
| 1 | 73475 | Madden Gulf Coast, LLC | $6,599,868.36 |
| 2 | 06276 | Barriere Construction Co., LLC | $6,722,896.56 |
Line Number | Item Number | Item Description | Quantity | Unit of Measure | - 1 - Madden Gulf Coast, LLC | - 2 - Barriere Construction Co., LLC | | Unit Price | Total Amount | Unit Price | Total Amount | | 0001 | 202-02-02020 | Removal of Asphalt Pavement | 1,184 | SQYD | 8.00 | 9,472.00 | 11.00 | 13,024.00 | | 0002 | 202-02-06140 | Removal of Curbs (Concrete) | 133 | LNFT | 20.00 | 2,660.00 | 75.00 | 9,975.00 | | 0003 | 202-02-14500 | Removal of Guard Rail | 431.5 | LNFT | 10.00 | 4,315.00 | 16.00 | 6,904.00 | | 0004 | 203-07-00100 | Borrow (Vehicular Measurement) | 30 | CUYD | 350.00 | 10,500.00 | 65.00 | 1,950.00 | | 0005 | 204-06-00100 | Temporary Silt Fencing | 970 | LNFT | 5.00 | 4,850.00 | 3.50 | 3,395.00 | | 0006 | 502-01-00100 | Asphalt Concrete | 19,396 | TON | 118.00 | 2,288,728.00 | 139.00 | 2,696,044.00 | | 0007 | 502-01-00200 | Asphalt Concrete, Drives, Turnouts and Miscellaneous | 270 | TON | 200.00 | 54,000.00 | 219.00 | 59,130.00 | | 0008 | 509-01-00100 | Milling Asphalt Pavement | 90,272 | SQYD | 4.80 | 433,305.60 | 5.00 | 451,360.00 | | 0009 | 509-02-00100 | Contractor Retained Reclaimed Asphalt Pavement | -7,344 | CUYD | 0.01 | -73.44 | 0.01 | -73.44 | | 0010 | 510-01-00001 | Pavement Patching 21" Thickness | 2,377 | SQYD | 222.00 | 527,694.00 | 201.00 | 477,777.00 | | 0011 | 511-01-00100 | Saw Cutting Asphalt Concrete Pavement | 3,852 | INLF | 2.50 | 9,630.00 | 1.75 | 6,741.00 | | 0012 | 511-02-00100 | Sawing and Sealing Longitudinal Joints in Asphalt Concrete Overlay | 1,175 | LNFT | 3.65 | 4,288.75 | 5.00 | 5,875.00 | | 0013 | 511-03-00100 | Sawing and Sealing Transverse Joints in Asphalt Concrete Overlay | 1,310 | LNFT | 3.65 | 4,781.50 | 5.00 | 6,550.00 | | 0014 | 602-02-00200 | Cleaning and Resealing Existing Longitudinal Pavement Joints | 1,240 | LNFT | 4.25 | 5,270.00 | 3.75 | 4,650.00 | | 0015 | 602-02-00300 | Cleaning and Resealing Existing Transverse Pavements Joints | 1,475 | LNFT | 4.50 | 6,637.50 | 3.75 | 5,531.25 | | 0016 | 602-05-03120 | Full Depth Patching of Jointed Concrete Pavement (48.1 square yards and over) (8" Thick) | 474.3 | SQYD | 350.00 | 166,005.00 | 275.00 | 130,432.50 | | 0017 | 602-10-00100 | Longitudinal Shoulder Joints | 410 | LNFT | 3.65 | 1,496.50 | 6.00 | 2,460.00 | | 0018 | 701-14-00100 | Cleaning Existing Pipes 18" & 36" | 1,700 | LNFT | 20.00 | 34,000.00 | 23.00 | 39,100.00 | | 0019 | 702-04-00150 | Adjusting Manholes w/Manhole Adjustment Rings | 8 | EACH | 500.00 | 4,000.00 | 300.00 | 2,400.00 | | 0020 | 704-03-00200 | Blocked Out Guard Rail - 31", (6'-3" Post Spacing) | 193.8 | LNFT | 34.25 | 6,637.65 | 35.00 | 6,783.00 | | 0021 | 704-07-00200 | Guard Rail Transitions (Double Thrie Beam) | 100 | LNFT | 117.00 | 11,700.00 | 125.00 | 12,500.00 | | 0022 | 704-10-00310 | Guard Rail End Treatment, NCHRP 350 - 31" (TL-3 Flared) | 4 | EACH | 3,125.00 | 12,500.00 | 3,500.00 | 14,000.00 | | 0023 | 706-04-00110 | Curb Ramps Type 4 | 107.4 | SQYD | 235.00 | 25,239.00 | 175.00 | 18,795.00 | | 0024 | 706-04-00110 | Curb Ramps Type 8 | 5,177 | SQYD | 268.00 | 1,387,436.00 | 95.00 | 491,815.00 | | 0025 | 706-04-00110 | Curb Ramps Type 8 Modified | 340 | SQYD | 271.00 | 92,140.00 | 200.00 | 68,000.00 | | 0026 | 707-01-00100 | Concrete Curb | 133 | LNFT | 55.00 | 7,315.00 | 65.00 | 8,645.00 | | 0027 | 713-01-00100 | Temporary Signs and Barricades | 1 | LUMP | 185,000.00 | 185,000.00 | 670,000.00 | 670,000.00 | | 0028 | 713-02-00300 | Temporary Pavement Markings (8" Width) | 3,450 | LNFT | 0.15 | 517.50 | 0.15 | 517.50 | | 0029 | 713-02-00500 | Temporary Pavement Markings (24" Width) | 2,928 | LNFT | 0.45 | 1,317.60 | 0.45 | 1,317.60 | | 0030 | 713-03-01000 | Temporary Pavement Markings (Broken Line) (4" Width) (4' Length) | 27.927 | MILE | 400.00 | 11,170.80 | 239.00 | 6,674.55 | | 0031 | 713-03-02000 | Temporary Pavement Markings (Broken Line) (4" Width) (10' Length) | 27.927 | MILE | 600.00 | 16,756.20 | 600.00 | 16,756.20 | | 0032 | 713-04-01000 | Temporary Pavement Markings (Solid Line) (4" Width) | 29.928 | MILE | 900.00 | 26,935.20 | 900.00 | 26,935.20 | | 0033 | 713-05-00190 | Temporary Pavement Legends & Symbols (Arrow - Straight) | 3 | EACH | 25.00 | 75.00 | 25.00 | 75.00 | | 0034 | 713-05-00220 | Temporary Pavement Legends & Symbols (Arrow - Left Turn) | 132 | EACH | 25.00 | 3,300.00 | 25.00 | 3,300.00 | | 0035 | 713-05-00230 | Temporary Pavement Legends & Symbols (Arrow - Right Turn) | 3 | EACH | 25.00 | 75.00 | 25.00 | 75.00 | | 0036 | 713-05-00240 | Temporary Pavement Legends & Symbols (Arrow - Merge) | 6 | EACH | 25.00 | 150.00 | 25.00 | 150.00 | | 0037 | 713-05-00300 | Temporary Pavement Legends & Symbols (ONLY) | 21 | EACH | 25.00 | 525.00 | 25.00 | 525.00 | | 0038 | 727-01-00100 | Mobilization | 1 | LUMP | 485,000.00 | 485,000.00 | 670,000.00 | 670,000.00 | | 0039 | 729-16-00200 | Object Marker Assembly (Type 2) | 5 | EACH | 85.00 | 425.00 | 95.00 | 475.00 | | 0040 | 729-16-00300 | Object Marker Assembly (Type 3) | 4 | EACH | 85.00 | 340.00 | 95.00 | 380.00 | | 0041 | 731-02-00100 | Reflectorized Raised Pavement Markers | 4,711 | EACH | 4.00 | 18,844.00 | 4.00 | 18,844.00 | | 0042 | 732-01-01040 | Plastic Pavement Striping (8" Width) (Thermoplastic 90 mil) | 1,150 | LNFT | 3.00 | 3,450.00 | 3.00 | 3,450.00 | | 0043 | 732-01-01080 | Plastic Pavement Striping (24" Width) (Thermoplastic 90 mil) | 1,863 | LNFT | 12.00 | 22,356.00 | 12.00 | 22,356.00 | | 0044 | 732-01-02040 | Plastic Pavement Striping (8" Width) (Thermoplastic 125 mil) | 420 | LNFT | 3.00 | 1,260.00 | 3.00 | 1,260.00 | | 0045 | 732-01-02080 | Plastic Pavement Striping (24" Width) (Thermoplastic 125 mil) | 697 | LNFT | 12.00 | 8,364.00 | 12.00 | 8,364.00 | | 0046 | 732-02-02000 | Plastic Pavement Striping (Solid Line) (4" Width) (Thermoplastic 90 mil) | 13.592 | MILE | 4,200.00 | 57,086.40 | 4,200.00 | 57,086.40 | | 0047 | 732-03-02000 | Plastic Pavement Striping (Broken Line) (4" Width) (Thermoplastic 90 mil) | 9.309 | MILE | 1,200.00 | 11,170.80 | 1,200.00 | 11,170.80 | | 0048 | 732-03-02012 | Plastic Pavement Striping (Dotted Line)(4" W)(3' L)(Thermo 90 mil) | 0.235 | MILE | 13,000.00 | 3,055.00 | 15,000.00 | 3,525.00 | | 0049 | 732-03-02030 | Plastic Pavement Striping (Dotted Line)(8" W)(2' L)(Thermo 90 mil) | 0.087 | MILE | 13,000.00 | 1,131.00 | 15,000.00 | 1,305.00 | | 0050 | 732-04-01020 | Plastic Pavement Legends and Symbols (Arrow - Straight) | 3 | EACH | 350.00 | 1,050.00 | 350.00 | 1,050.00 | | 0051 | 732-04-01080 | Plastic Pavement Legends and Symbols (Arrow - Left Turn) | 44 | EACH | 350.00 | 15,400.00 | 350.00 | 15,400.00 | | 0052 | 732-04-01100 | Plastic Pavement Legends and Symbols (Arrow - Right Turn) | 1 | EACH | 350.00 | 350.00 | 350.00 | 350.00 | | 0053 | 732-04-01120 | Plastic Pavement Legends and Symbols (Arrow - Merge) | 2 | EACH | 600.00 | 1,200.00 | 600.00 | 1,200.00 | | 0054 | 732-04-15020 | Plastic Pavement Legends and Symbols (ONLY) | 7 | EACH | 450.00 | 3,150.00 | 450.00 | 3,150.00 | | 0055 | 732-05-00100 | Removal of Existing Markings | 0.987 | MILE | 15,000.00 | 14,805.00 | 15,000.00 | 14,805.00 | | 0056 | 739-01-00100 | Hydro-Seeding | 0.15 | ACRE | 10,000.00 | 1,500.00 | 16,400.00 | 2,460.00 | | 0057 | 740-01-00100 | Construction Layout | 1 | LUMP | 18,000.00 | 18,000.00 | 36,000.00 | 36,000.00 | | 0058 | NS-500-00180 | Roadway Reinforcing Mesh (Complete Road System) | 85,952 | SQYD | 6.65 | 571,580.80 | 6.75 | 580,176.00 | | | | | | | | | | | | | | CONTRACTOR TOTAL | | | | 6,599,868.36 | | 6,722,896.56 |
|