Bid Tabulations for the Letting of 5/13/2026 LA DOTD Headquarters

Proposal:H.015823.6
Parish:Iberia
Routes:US 90
Description:US 90: LA 83 - LA 85
Type Construction:GRADING, MILLING ASPHALT CONCRETE, PAVEMENT PATCHING, SUBGRADE TREATMENT, CLASS II BASE COURSE, CEMENT TREATED BASE COURSE, ROADWAY REINFORCING MESH, TEMPORARY DEOUR ROAD, ASPHALT CONCRETE OVERLAY, AND RELATED WORK.
Estimated Construction Cost:$29,976,637.79
Rank License BidderConstruction Bid
133663Glenn Lege Construction LLC$23,115,522.17
234356Prairie Contractors LLC$23,535,456.17
352306SIEMA CONSTRUCTION, LLC$25,468,824.34
439462JB JAMES CONSTRUCTION LLC$27,548,414.35
512312Gilchrist Construction Company, LLC$28,305,721.05
606276Barriere Construction Co., LLC$29,526,810.22


Line
Number
Item NumberItem DescriptionQuantityUnit of
Measure
- 1 -
Glenn Lege Construction LLC
- 2 -
Prairie Contractors LLC
- 3 -
SIEMA CONSTRUCTION, LLC
- 4 -
JB JAMES CONSTRUCTION LLC
Unit PriceTotal
Amount
Unit PriceTotal
Amount
Unit PriceTotal
Amount
Unit PriceTotal
Amount
0001202-02-02020Removal of Asphalt Pavement 2,226.9   SQYD5.9113,160.9832.0071,260.8015.0033,403.5011.5025,609.35
0002202-02-03030Removal of Pavement Structure 63,235     SQYD8.27522,953.457.85496,394.758.00505,880.0025.001,580,875.00
0003202-02-04560Removal of Bridge Joint Preformed Silicone1,680     LNFT24.4241,025.6035.0058,800.005.008,400.0012.0020,160.00
0004202-02-14500Removal of Guard Rail 2,419.4   LNFT8.7221,097.1716.0038,710.4016.7540,524.9512.0029,032.80
0005202-02-32500Removal of Portland Cement Concrete Pavement 1,872     SQYD7.3113,684.3229.0054,288.0018.5034,632.0020.0037,440.00
0006203-01-00100General Excavation 22,621     CUYD11.03249,509.637.00158,347.0025.00565,525.0045.001,017,945.00
0007203-03-00100Embankment 2,514     CUYD35.3388,819.62100.00251,400.0093.00233,802.0060.00150,840.00
0008204-05-00100Temporary Sediment Check Dams (Hay) 148     EACH174.2325,786.04115.0017,020.00155.0022,940.00120.0017,760.00
0009204-06-00100Temporary Silt Fencing 47,764     LNFT2.47117,977.082.15102,692.602.0095,528.004.00191,056.00
0010302-02-04070Class II Base Course (4" Thick) (Crushed Stone or Recycled Portland Cement Concrete) 103,956.9   SQYD13.751,429,407.3810.501,091,547.4511.001,143,525.9022.002,287,051.80
0011302-02-08010Class II Base Course (8" Thick) (Soil Cement) 103,956.9   SQYD19.141,989,735.0720.502,131,116.4520.002,079,138.0022.002,287,051.80
0012302-03-00100Base Drain Outlet 95     EACH619.8758,887.65833.0079,135.00930.0088,350.00500.0047,500.00
0013305-01-04020Subgrade Layer (12" Thick) (Treated) 103,957     SQYD14.351,491,782.9511.801,226,692.6011.501,195,505.5012.001,247,484.00
0014502-01-00100Asphalt Concrete 95,720     TON125.0011,965,000.00118.0011,294,960.00132.5012,682,900.00120.9811,580,205.60
0015502-01-00200Asphalt Concrete, Drives, Turnouts and Miscellaneous 889.2   TON172.24153,155.81297.00264,092.40182.00161,834.40166.34147,909.53
0016509-01-00100Milling Asphalt Pavement 62,735     SQYD2.72170,639.203.50219,572.503.00188,205.002.77173,775.95
0017509-02-00100Contractor Retained Reclaimed Asphalt Pavement -3,196     CUYD0.01-31.960.01-31.960.01-31.960.01-31.96
0018510-01-00300Pavement Patching (18" Minimum Thickness) 1,067     SQYD232.27247,832.09219.00233,673.00215.00229,405.00196.59209,761.53
0019510-01-00400Pavement Patching (24" Minimum Thickness) 107     SQYD355.5138,039.57256.0027,392.00386.0041,302.00352.8537,754.95
0020511-01-00100Saw Cutting Asphalt Concrete Pavement 5,876     INLF0.875,112.122.2513,221.001.005,876.000.754,407.00
0021511-03-00100Sawing and Sealing Transverse Joints in Asphalt Concrete Overlay 260     LNFT20.155,239.0015.003,900.009.752,535.0018.004,680.00
0022601-05-00100Saw Cutting Portland Cement Concrete Pavement 2,856     INLF1.163,312.963.509,996.001.504,284.001.002,856.00
0023602-02-00200Cleaning and Resealing Existing Longitudinal Pavement Joints 39,082     LNFT3.26127,407.324.25166,098.504.00156,328.003.00117,246.00
0024602-02-00300Cleaning and Resealing Existing Transverse Pavements Joints 27,916     LNFT3.3092,122.804.25118,643.004.00111,664.003.0083,748.00
0025704-03-00200Blocked Out Guard Rail - 31", (6'-3" Post Spacing) 1,531.5   LNFT39.4960,478.9442.5065,088.7544.5068,151.7534.0052,071.00
0026704-07-00200Guard Rail Transitions (Double Thrie Beam) 250     LNFT135.9033,975.00160.0040,000.00138.0034,500.00120.0030,000.00
0027704-10-00310Guard Rail End Treatment, NCHRP 350 - 31" (TL-3 Flared) 10     EACH3,687.7636,877.604,500.0045,000.003,745.0037,450.003,200.0032,000.00
0028707-01-00100Concrete Curb 27     LNFT59.811,614.87400.0010,800.00226.006,102.0060.001,620.00
0029713-01-00100Temporary Signs and Barricades 1     LUMP494,662.25494,662.25350,000.00350,000.00500,000.00500,000.00300,000.00300,000.00
0030713-02-00300Temporary Pavement Markings (8" Width) 17,657     LNFT0.173,001.690.01176.570.305,297.100.508,828.50
0031713-02-00500Temporary Pavement Markings (24" Width) 2,676     LNFT0.531,418.280.0126.760.601,605.601.002,676.00
0032713-03-01000Temporary Pavement Markings (Broken Line) (4" Width) (4' Length) 26.136 MILE813.0521,249.87650.0016,988.40826.0021,588.34800.0020,908.80
0033713-03-02000Temporary Pavement Markings (Broken Line) (4" Width) (10' Length) 26.134 MILE813.0521,248.25700.0018,293.80826.0021,586.68700.0018,293.80
0034713-04-01000Temporary Pavement Markings (Solid Line) (4" Width) 80.876 MILE1,045.3584,543.73900.0072,788.401,239.00100,205.36900.0072,788.40
0035713-06-00100Temporary Reflectorized Raised Pavement Markers 4,588     EACH4.6521,334.205.0022,940.007.0032,116.004.0018,352.00
0036713-08-00100Temporary Precast Concrete Barrier (Department Furnished) 1,947     EACH286.80558,399.60400.00778,800.00247.00480,909.00370.00720,390.00
0037713-11-00100Portable Changeable Message Signs 2     EACH59,085.00118,170.0025,000.0050,000.0018,500.0037,000.0025,000.0050,000.00
0038722-02-00100Project Site Laboratory (Equipped) 1     EACH39,652.6039,652.6030,000.0030,000.0025,000.0025,000.0030,000.0030,000.00
0039724-02-00100Rumble Strips (Shoulder/Edge) 17.48  MILE1,161.5020,303.021,200.0020,976.00439.007,673.72300.005,244.00
0040725-01-00100Temporary Detour Roads 2,072.3   SQYD185.05383,479.12250.00518,075.00204.75424,303.43240.00497,352.00
0041727-01-00100Mobilization 1     LUMP844,915.50844,915.501,600,000.001,600,000.002,300,000.002,300,000.002,720,000.002,720,000.00
0042729-16-00200Object Marker Assembly (Type 2) 163     EACH75.5012,306.50145.0023,635.0077.0012,551.0065.0010,595.00
0043729-16-00300Object Marker Assembly (Type 3) 23     EACH104.542,404.42155.003,565.00106.002,438.0090.002,070.00
0044731-01-00100Nonreflectorized Raised Pavement Markers 19,762     EACH11.62229,634.4412.00237,144.0012.00237,144.009.00177,858.00
0045731-02-00100Reflectorized Raised Pavement Markers 5,403     EACH5.8131,391.436.0032,418.007.0037,821.004.0021,612.00
0046732-01-01040Plastic Pavement Striping (8" Width) (Thermoplastic 90 mil) 10,338     LNFT4.0742,075.664.0041,352.003.2533,598.504.0041,352.00
0047732-01-01080Plastic Pavement Striping (24" Width) (Thermoplastic 90 mil) 2,676     LNFT16.2643,511.7616.0042,816.0013.0034,788.0012.0032,112.00
0048732-02-02000Plastic Pavement Striping (Solid Line) (4" Width) (Thermoplastic 90 mil) 27.722 MILE5,226.75144,895.965,500.00152,471.006,841.00189,646.204,500.00124,749.00
0049732-03-02000Plastic Pavement Striping (Broken Line) (4" Width) (Thermoplastic 90 mil) 8.739 MILE1,393.8012,180.421,500.0013,108.503,303.0028,864.921,200.0010,486.80
0050732-03-02040Plastic Pavement Striping (Dotted Line)(8" W)(3' L)(Thermo 90 mil) 1.33  MILE9,292.0012,358.3610,000.0013,300.0014,154.0018,824.828,200.0010,906.00
0051732-03-02102Plastic Pav't Striping (Broken) (4" W) (Preformed Tape Retroreflectivity I or Thermo 90 mil)(Black and White Contrast) 5.121 MILE4,878.3024,981.775,250.0026,885.2510,614.0054,354.294,200.0021,508.20
0052732-05-00100Removal of Existing Markings 10.087 MILE6,969.0070,296.307,250.0073,130.7510,020.00101,071.746,000.0060,522.00
0053739-01-00100Hydro-Seeding 5.32  ACRE3,252.2017,301.703,500.0018,620.003,130.0016,651.602,700.0014,364.00
0054740-01-00100Construction Layout 1     LUMP172,624.35172,624.35200,000.00200,000.0092,642.0092,642.00285,000.00285,000.00
0055815-03-00200Joint Seal (Preformed Silicone) 1,680     LNFT24.4241,025.60150.00252,000.00111.00186,480.0080.00134,400.00
0056NS-500-00180Roadway Reinforcing Mesh (Complete Road System) 72,867     SQYD8.39611,354.136.50473,635.509.00655,803.009.50692,236.50
0057NS-700-00810Impact Attenuator (Construction Zone)(Test Level 3) 13     EACH2,323.0030,199.0012,500.00162,500.002,400.0031,200.002,000.0026,000.00
             
  CONTRACTOR TOTAL   23,115,522.17 23,535,456.17 25,468,824.34 27,548,414.35



Line
Number
Item NumberItem DescriptionQuantityUnit of
Measure
- 5 -
Gilchrist Construction Company, LLC
- 6 -
Barriere Construction Co., LLC
Unit PriceTotal
Amount
Unit PriceTotal
Amount
0001202-02-02020Removal of Asphalt Pavement 2,226.9   SQYD16.0035,630.409.7521,712.28
0002202-02-03030Removal of Pavement Structure 63,235     SQYD16.001,011,760.0011.00695,585.00
0003202-02-04560Removal of Bridge Joint Preformed Silicone1,680     LNFT31.0052,080.0037.0062,160.00
0004202-02-14500Removal of Guard Rail 2,419.4   LNFT8.0019,355.209.0021,774.60
0005202-02-32500Removal of Portland Cement Concrete Pavement 1,872     SQYD13.0024,336.0010.0018,720.00
0006203-01-00100General Excavation 22,621     CUYD14.00316,694.005.00113,105.00
0007203-03-00100Embankment 2,514     CUYD37.0093,018.0045.75115,015.50
0008204-05-00100Temporary Sediment Check Dams (Hay) 148     EACH150.0022,200.00153.0022,644.00
0009204-06-00100Temporary Silt Fencing 47,764     LNFT2.0095,528.002.50119,410.00
0010302-02-04070Class II Base Course (4" Thick) (Crushed Stone or Recycled Portland Cement Concrete) 103,956.9   SQYD11.001,143,525.907.50779,676.75
0011302-02-08010Class II Base Course (8" Thick) (Soil Cement) 103,956.9   SQYD26.002,702,879.4021.752,261,062.58
0012302-03-00100Base Drain Outlet 95     EACH800.0076,000.001,135.00107,825.00
0013305-01-04020Subgrade Layer (12" Thick) (Treated) 103,957     SQYD19.001,975,183.0010.251,065,559.25
0014502-01-00100Asphalt Concrete 95,720     TON140.0013,400,800.00153.5014,693,020.00
0015502-01-00200Asphalt Concrete, Drives, Turnouts and Miscellaneous 889.2   TON325.00288,990.00213.00189,399.60
0016509-01-00100Milling Asphalt Pavement 62,735     SQYD5.50345,042.506.00376,410.00
0017509-02-00100Contractor Retained Reclaimed Asphalt Pavement -3,196     CUYD1.00-3,196.000.01-31.96
0018510-01-00300Pavement Patching (18" Minimum Thickness) 1,067     SQYD300.00320,100.00237.00252,879.00
0019510-01-00400Pavement Patching (24" Minimum Thickness) 107     SQYD350.0037,450.00418.0044,726.00
0020511-01-00100Saw Cutting Asphalt Concrete Pavement 5,876     INLF4.0023,504.000.854,994.60
0021511-03-00100Sawing and Sealing Transverse Joints in Asphalt Concrete Overlay 260     LNFT30.007,800.002.70702.00
0022601-05-00100Saw Cutting Portland Cement Concrete Pavement 2,856     INLF2.005,712.002.707,711.20
0023602-02-00200Cleaning and Resealing Existing Longitudinal Pavement Joints 39,082     LNFT4.00156,328.002.75107,475.50
0024602-02-00300Cleaning and Resealing Existing Transverse Pavements Joints 27,916     LNFT4.00111,664.002.7576,769.00
0025704-03-00200Blocked Out Guard Rail - 31", (6'-3" Post Spacing) 1,531.5   LNFT34.0052,071.0040.5062,025.75
0026704-07-00200Guard Rail Transitions (Double Thrie Beam) 250     LNFT117.0029,250.00139.7534,937.50
0027704-10-00310Guard Rail End Treatment, NCHRP 350 - 31" (TL-3 Flared) 10     EACH3,200.0032,000.003,800.0038,000.00
0028707-01-00100Concrete Curb 27     LNFT360.009,720.00600.0016,200.00
0029713-01-00100Temporary Signs and Barricades 1     LUMP225,000.00225,000.001,475,000.001,475,000.00
0030713-02-00300Temporary Pavement Markings (8" Width) 17,657     LNFT0.254,414.250.152,648.55
0031713-02-00500Temporary Pavement Markings (24" Width) 2,676     LNFT0.501,338.000.551,471.80
0032713-03-01000Temporary Pavement Markings (Broken Line) (4" Width) (4' Length) 26.136 MILE250.006,534.00290.007,579.44
0033713-03-02000Temporary Pavement Markings (Broken Line) (4" Width) (10' Length) 26.134 MILE700.0018,293.80850.0022,213.90
0034713-04-01000Temporary Pavement Markings (Solid Line) (4" Width) 80.876 MILE1,050.0084,919.801,100.0088,963.60
0035713-06-00100Temporary Reflectorized Raised Pavement Markers 4,588     EACH6.0027,528.004.8522,251.80
0036713-08-00100Temporary Precast Concrete Barrier (Department Furnished) 1,947     EACH550.001,070,850.00405.00788,535.00
0037713-11-00100Portable Changeable Message Signs 2     EACH27,000.0054,000.0030,500.0061,000.00
0038722-02-00100Project Site Laboratory (Equipped) 1     EACH35,000.0035,000.0089,500.0089,500.00
0039724-02-00100Rumble Strips (Shoulder/Edge) 17.48  MILE1,100.0019,228.001,450.0025,346.00
0040725-01-00100Temporary Detour Roads 2,072.3   SQYD265.00549,159.50175.00362,652.50
0041727-01-00100Mobilization 1     LUMP2,000,000.002,000,000.003,650,000.003,650,000.00
0042729-16-00200Object Marker Assembly (Type 2) 163     EACH65.0010,595.0075.0012,225.00
0043729-16-00300Object Marker Assembly (Type 3) 23     EACH90.002,070.00107.502,472.50
0044731-01-00100Nonreflectorized Raised Pavement Markers 19,762     EACH10.00197,620.0012.00237,144.00
0045731-02-00100Reflectorized Raised Pavement Markers 5,403     EACH6.0032,418.005.0027,015.00
0046732-01-01040Plastic Pavement Striping (8" Width) (Thermoplastic 90 mil) 10,338     LNFT3.0031,014.004.2543,936.50
0047732-01-01080Plastic Pavement Striping (24" Width) (Thermoplastic 90 mil) 2,676     LNFT11.0029,436.0017.0045,492.00
0048732-02-02000Plastic Pavement Striping (Solid Line) (4" Width) (Thermoplastic 90 mil) 27.722 MILE5,800.00160,787.605,450.00151,084.90
0049732-03-02000Plastic Pavement Striping (Broken Line) (4" Width) (Thermoplastic 90 mil) 8.739 MILE2,800.0024,469.201,450.0012,671.55
0050732-03-02040Plastic Pavement Striping (Dotted Line)(8" W)(3' L)(Thermo 90 mil) 1.33  MILE12,000.0015,960.009,700.0012,901.00
0051732-03-02102Plastic Pav't Striping (Broken) (4" W) (Preformed Tape Retroreflectivity I or Thermo 90 mil)(Black and White Contrast) 5.121 MILE9,000.0046,089.005,100.0026,117.10
0052732-05-00100Removal of Existing Markings 10.087 MILE8,500.0085,739.507,275.0073,382.93
0053739-01-00100Hydro-Seeding 5.32  ACRE2,800.0014,896.003,175.0016,891.00
0054740-01-00100Construction Layout 1     LUMP250,000.00250,000.0094,100.0094,100.00
0055815-03-00200Joint Seal (Preformed Silicone) 1,680     LNFT125.00210,000.00149.25250,740.00
0056NS-500-00180Roadway Reinforcing Mesh (Complete Road System) 72,867     SQYD8.00582,936.008.00582,936.00
0057NS-700-00810Impact Attenuator (Construction Zone)(Test Level 3) 13     EACH10,000.00130,000.002,390.0031,070.00
         
  CONTRACTOR TOTAL   28,305,721.05 29,526,810.22