Bid Tabulations for the Letting of 5/13/2026 LA DOTD Headquarters

Proposal:H.014246.6
Parish:Rapides
Routes:LA 1199
Description:LA 1199: SPRING CREEK & CREEK BRIDGES
Type Construction:CLEARING AND GRUBBING, GRADING, REMOVAL OF PRECAST BRIDGES, DRAINAGE STRUCTURES, PAVEMENT PATCHING, CLASS II BASE COURSE, LIME TREATMENT, ASPHALT CONCRETE PAVEMENT, PRECAST CONCRETE PILES, CONCRETE SLAB SPAN BRIDGES, AND RELATED WORK.
Estimated Construction Cost:$6,725,091.46
Rank License BidderConstruction Bid
101516Elevate Heavy Civil Construction, LLC$4,942,259.90
212487Diamond B Construction Co., L.L.C.$4,970,259.20
355505MERRICK, LLC$5,049,092.50
427239Apeck Construction, LLC$5,183,042.03
500044Guinn Construction, LLC$5,334,192.00
612312Gilchrist Construction Company, LLC$5,494,893.11
739613Baker Pile Driving and Site Work, LLC$5,499,401.79
839462JB JAMES CONSTRUCTION LLC$5,648,101.00
956994Matt L. Guinn Construction, LLC$5,799,668.40
1049239WL Bass Construction Inc.$5,931,849.55


Line
Number
Item NumberItem DescriptionQuantityUnit of
Measure
- 1 -
Elevate Heavy Civil Construction, LLC
- 2 -
Diamond B Construction Co., L.L.C.
- 3 -
MERRICK, LLC
- 4 -
Apeck Construction, LLC
Unit PriceTotal
Amount
Unit PriceTotal
Amount
Unit PriceTotal
Amount
Unit PriceTotal
Amount
0001201-01-00100Clearing and Grubbing 4.44  LUMP100,000.00100,000.00120,000.00120,000.0085,000.0085,000.00744,748.30744,748.30
0002202-01-00100Removal of Structures and Obstructions 1     LUMP10,000.0010,000.0035,000.0035,000.0020,000.0020,000.008,232.258,232.25
0003202-02-03030Removal of Pavement Structure 3,699     SQYD10.0036,990.007.0025,893.009.0033,291.0014.5153,672.49
0004202-02-04501Removal of Bridge Bridge Str. No. 084008402700611 (60' x 28' Precast Bridge with Timber Piles)1,680     LUMP50,000.0050,000.0030,000.0030,000.0040,000.0040,000.0020,184.5620,184.56
0005202-02-04501Removal of Bridge Bridge Str. No. 084008402701801 (40' x 28' Precast Bridge with Timber Piles)1,120     LUMP50,000.0050,000.0030,000.0030,000.0040,000.0040,000.0020,184.5620,184.56
0006202-02-04501Removal of Bridge Bridge Str. No. 084008402702861 (80' x 28' Precast Bridge with Timber Piles)2,240     LUMP50,000.0050,000.0045,000.0045,000.0075,000.0075,000.0030,276.8630,276.86
0007202-02-12000Removal of Fence 312     LNFT2.00624.0025.007,800.007.002,184.0011.703,650.40
0008202-02-14500Removal of Guard Rail 859.7   LNFT8.006,877.6025.0021,492.5010.008,597.0012.7310,943.98
0009202-03-38000Relocation of Sign 1     EACH150.00150.006,000.006,000.00600.00600.00178.83178.83
0010203-02-00100Drainage Excavation 4,315     CUYD10.0043,150.0018.0077,670.0020.0086,300.0021.7793,937.55
0011203-05-00100Excavation and Embankment 1     LUMP138,000.00138,000.0090,000.0090,000.00200,000.00200,000.00128,316.04128,316.04
0012204-05-00100Temporary Sediment Check Dams (Hay) 24     EACH150.003,600.00250.006,000.00185.004,440.00298.057,153.20
0013204-06-00100Temporary Silt Fencing 1,535     LNFT3.004,605.003.505,372.503.505,372.505.969,148.60
0014302-02-04010Class II Base Course (4" Thick) (Asphalt Concrete Base) 5,315.8   SQYD45.00239,211.0025.00132,895.0045.00239,211.0048.24256,434.19
0015304-01-00100Lime 18.85  TON350.006,597.50505.009,519.25350.006,597.50476.878,989.00
0016304-05-00100Lime Treatment (Type E) 1,330     SQYD10.0013,300.008.0010,640.003.003,990.001.191,582.70
0017402-01-00101Traffic Maintenance Surfacing (Aggregate) (Vehicular Measurement) 45     CUYD160.007,200.0065.002,925.00150.006,750.00132.475,961.15
0018502-01-00100Asphalt Concrete 1,175.3   TON235.00276,195.50275.00323,207.50250.00293,825.00236.93278,463.83
0019502-01-00200Asphalt Concrete, Drives, Turnouts and Miscellaneous 225.3   TON280.0063,084.00315.0070,969.50300.0067,590.00240.5254,189.16
0020510-01-00001Pavement Patching (14.5 inch minimum thickness)276     SQYD200.0055,200.00206.0056,856.00225.0062,100.00239.0865,986.08
0021511-01-00100Saw Cutting Asphalt Concrete Pavement 470     INLF2.00940.004.001,880.003.001,410.004.642,180.80
0022511-03-00100Sawing and Sealing Transverse Joints in Asphalt Concrete Overlay 648     LNFT12.007,776.0015.009,720.009.005,832.0012.698,223.12
0023511-04-00100Sawcuts in Asphalt Concrete Lifts 1,080     LNFT3.003,240.0015.0016,200.002.002,160.008.078,715.60
0024701-05-02062Side Drain Pipe (Erosion) (24" RPVCP/CMP) 111     LNFT70.007,770.00100.0011,100.00125.0013,875.00107.8311,969.13
0025701-05-02066Side Drain Pipe (Erosion) (24" RPVCP/CPEPDW/CPPPDW/CMP) 133     LNFT70.009,310.0095.0012,635.00125.0016,625.0095.3212,677.56
0026701-17-00100Trench Excavation Safety Protection (Depth >5 feet) 466     LNFT10.004,660.0010.004,660.008.003,728.005.962,777.36
0027702-03-00100Catch Basins (CB-01) 1     EACH6,000.006,000.0011,000.0011,000.007,000.007,000.007,203.057,203.05
0028704-03-00100Blocked Out Guard rail 31.3   LNFT34.001,064.2045.001,408.5030.00939.0053.651,679.25
0029704-03-00200Blocked Out Guard Rail - 31", (6'-3" Post Spacing) 606.3   LNFT34.0020,614.2035.0021,220.5030.0018,189.0041.7325,300.90
0030704-05-00100Guard Rail Anchor Sections (Trailing End) 6.3   LNFT160.001,008.00140.00882.00125.00787.50166.911,051.53
0031704-07-00200Guard Rail Transitions (Double Thrie Beam) 300     LNFT116.0034,800.00135.0040,500.00125.0037,500.00160.9548,285.00
0032704-10-00205Guard Rail End Treatment, MASH, (TL-3 Tangent) 11     EACH3,350.0036,850.004,150.0045,650.003,500.0038,500.004,947.5854,423.38
0033705-02-00100Combination Mesh & Barbed Wire Fence 378     LNFT16.006,048.0018.006,804.0020.007,560.0021.468,111.88
0034708-01-00100Right-of-Way Monument 34     EACH600.0020,400.00600.0020,400.00600.0020,400.00715.3124,320.54
0035708-02-00100Right-of-Way Monument Witness Post 34     EACH200.006,800.00200.006,800.00200.006,800.00238.448,106.96
0036711-03-00400Riprap (55 lb) 2,836     TON72.00204,192.0095.00269,420.0090.00255,240.0081.81232,013.16
0037711-04-00100Geotextile Fabric 3,500     SQYD3.0010,500.001.003,500.003.0010,500.003.0610,710.00
0038713-01-00100Temporary Signs and Barricades 1     LUMP46,000.0046,000.00135,000.00135,000.00100,000.00100,000.0065,689.5165,689.51
0039713-03-01020Temporary Pavement Markings (Broken Line) (4" W) (4' L) (Type 1 Removable) 0.156 MILE28,200.004,399.201,000.00156.0013,000.002,028.0013,205.772,060.10
0040713-04-01020Temporary Pavement Markings (Solid Line) (4"Width) (Type 1 Removable) 1.252 MILE10,800.0013,521.6011,000.0013,772.0013,000.0016,276.0012,957.8916,223.28
0041713-06-00100Temporary Reflectorized Raised Pavement Markers 1,081     EACH6.006,486.006.006,486.007.007,567.007.157,729.15
0042713-11-00100Portable Changeable Message Signs 1     EACH7,000.007,000.009,500.009,500.0013,000.0013,000.005,960.945,960.94
0043720-01-01000Erosion Control System (Slope Protection) (Type A) 734     SQYD2.001,468.002.501,835.003.002,202.002.982,187.32
0044720-01-02000Erosion Control System, Flexible (Channel Liner) (Type C) 696     SQYD2.001,392.002.501,740.003.002,088.002.982,074.08
0045720-01-02020Erosion Control System, Flexible (Channel Liner) (Type D) 1,195     SQYD2.002,390.002.502,987.503.003,585.002.983,561.10
0046720-01-02040Erosion Control System, Flexible (Channel Liner) (Type E) 305     SQYD2.00610.002.50762.503.00915.002.98908.90
0047722-02-00100Project Site Laboratory (Equipped) 1     EACH58,000.0058,000.0010,000.0010,000.0013,000.0013,000.0082,618.5782,618.57
0048724-01-00100Rumble Strips (Centerline) 0.269 MILE502.00135.041,500.00403.501,500.00403.501,794.94482.84
0049724-02-00100Rumble Strips (Shoulder/Edge) 0.536 MILE504.00270.141,500.00804.001,500.00804.001,801.62965.67
0050726-01-00100Bedding Material 0.8   CUYD2,800.002,240.00800.00640.00300.00240.00298.05238.44
0051727-01-00100Mobilization 1     LUMP494,225.00494,225.00350,000.00350,000.00500,000.00500,000.00106,984.70106,984.70
0052729-01-00100Sign (Type A) 21     SQFT25.00525.0040.00840.0030.00630.0047.691,001.49
0053729-01-00200Mounting of Sign (Type A) 3     EACH20.0060.0025.0075.00300.00900.0029.8089.40
0054729-16-00300Object Marker Assembly (Type 3) 12     EACH90.001,080.00135.001,620.00125.001,500.00160.951,931.40
0055729-22-00100Perforated Square Tubing Post with 2-1/4" Anchor 6     EACH185.001,110.00150.00900.0030.00180.00178.831,072.98
0056731-01-00100Nonreflectorized Raised Pavement Markers 1,081     EACH12.0012,972.0012.0012,972.0013.0014,053.0014.3115,469.11
0057731-02-00100Reflectorized Raised Pavement Markers 77     EACH6.00462.006.00462.007.00539.007.15550.55
0058732-02-02000Plastic Pavement Striping (Solid Line) (4" Width) (Thermoplastic 90 mil) 1.252 MILE5,900.007,386.805,900.007,386.807,000.008,764.007,078.858,862.72
0059732-03-02000Plastic Pavement Striping (Broken Line) (4" Width) (Thermoplastic 90 mil) 0.156 MILE2,500.00390.003,100.00483.603,500.00546.003,912.82610.40
0060735-01-00100Mailboxes 3     EACH30.0090.0035.00105.00100.00300.0041.73125.19
0061735-02-00100Mailbox Supports (Single) 3     EACH255.00765.00300.00900.00200.00600.00357.661,072.98
0062739-01-00100Hydro-Seeding 4.44  ACRE2,610.0011,588.403,000.0013,320.003,500.0015,540.003,576.5615,879.93
0063740-01-00100Construction Layout 1     LUMP87,000.0087,000.0047,000.0047,000.0076,000.0076,000.0020,462.2420,462.24
0064804-01-00400Precast Concrete Piles (18") 4,180     LNFT190.00794,200.00197.00823,460.00160.00668,800.0071.90300,542.00
0065805-01-00100Class A1 Concrete (Slab Span) 532.3   CUYD960.00511,008.001,400.00745,220.001,300.00691,990.001,694.88902,184.62
0066805-01-00300Class A1 Concrete (Bent Cap) 171.72  CUYD1,976.00339,318.722,300.00394,956.002,200.00377,784.002,414.98414,700.37
0067805-18-00100Concrete Finish (Class 2 Rubbed Finish) 4,148     SQFT3.0012,444.003.0012,444.002.5010,370.007.6631,773.68
0068805-18-00200Concrete Finish (Class 3 Special Finish) 4,148     SQFT4.0016,592.003.5014,518.003.0012,444.007.6631,773.68
0069806-01-00100Deformed Reinforcing Steel 126,687     LB2.00253,374.001.15145,690.051.50190,030.501.30164,693.10
0070810-01-00120Concrete Bridge Railing (36 inch Height) 600     LNFT290.00174,000.00215.00129,000.00175.00105,000.00239.63143,778.00
0071813-01-00100Concrete Approach Slabs (Cast-in-Place) 4,320     SQFT104.00449,280.0095.00410,400.0095.00410,400.00117.58507,945.60
0072814-01-00100Elastomeric Bearing Pads (Non-Reinforced) 420     SFIN200.0084,000.00160.0067,200.00150.0063,000.00110.7046,494.00
0073815-03-00300Joint Seal (Poured) 648     LNFT15.009,720.0025.0016,200.0015.009,720.006.734,361.04
             
  CONTRACTOR TOTAL   4,942,259.90 4,970,259.20 5,049,092.50 5,183,042.03



Line
Number
Item NumberItem DescriptionQuantityUnit of
Measure
- 5 -
Guinn Construction, LLC
- 6 -
Gilchrist Construction Company, LLC
- 7 -
Baker Pile Driving and Site Work, LLC
- 8 -
JB JAMES CONSTRUCTION LLC
Unit PriceTotal
Amount
Unit PriceTotal
Amount
Unit PriceTotal
Amount
Unit PriceTotal
Amount
0001201-01-00100Clearing and Grubbing 4.44  LUMP140,000.00140,000.00200,000.00200,000.0088,657.0388,657.03400,000.00400,000.00
0002202-01-00100Removal of Structures and Obstructions 1     LUMP15,000.0015,000.0050,000.0050,000.009,421.469,421.4620,000.0020,000.00
0003202-02-03030Removal of Pavement Structure 3,699     SQYD15.0055,485.0016.0059,184.008.1830,257.828.0029,592.00
0004202-02-04501Removal of Bridge Bridge Str. No. 084008402700611 (60' x 28' Precast Bridge with Timber Piles)1,680     LUMP30,000.0030,000.0050,000.0050,000.0041,127.6841,127.6870,000.0070,000.00
0005202-02-04501Removal of Bridge Bridge Str. No. 084008402701801 (40' x 28' Precast Bridge with Timber Piles)1,120     LUMP25,000.0025,000.0050,000.0050,000.0034,139.2734,139.2770,000.0070,000.00
0006202-02-04501Removal of Bridge Bridge Str. No. 084008402702861 (80' x 28' Precast Bridge with Timber Piles)2,240     LUMP40,000.0040,000.0050,000.0050,000.0049,271.3549,271.3570,000.0070,000.00
0007202-02-12000Removal of Fence 312     LNFT5.001,560.002.00624.0011.873,703.442.00624.00
0008202-02-14500Removal of Guard Rail 859.7   LNFT8.006,877.6013.0011,176.109.007,737.3010.008,597.00
0009202-03-38000Relocation of Sign 1     EACH200.00200.0025.0025.0027.5027.50150.00150.00
0010203-02-00100Drainage Excavation 4,315     CUYD25.00107,875.0033.00142,395.0021.0090,615.0035.00151,025.00
0011203-05-00100Excavation and Embankment 1     LUMP150,000.00150,000.00427,500.00427,500.0098,835.0298,835.02200,000.00200,000.00
0012204-05-00100Temporary Sediment Check Dams (Hay) 24     EACH250.006,000.00150.003,600.00422.2710,134.48150.003,600.00
0013204-06-00100Temporary Silt Fencing 1,535     LNFT3.004,605.003.004,605.004.757,291.257.0010,745.00
0014302-02-04010Class II Base Course (4" Thick) (Asphalt Concrete Base) 5,315.8   SQYD55.00292,369.0042.00223,263.6049.75264,461.0545.00239,211.00
0015304-01-00100Lime 18.85  TON500.009,425.00500.009,425.00475.008,953.75300.005,655.00
0016304-05-00100Lime Treatment (Type E) 1,330     SQYD25.0033,250.0022.0029,260.0014.2018,886.008.0010,640.00
0017402-01-00101Traffic Maintenance Surfacing (Aggregate) (Vehicular Measurement) 45     CUYD100.004,500.00100.004,500.00191.578,620.65200.009,000.00
0018502-01-00100Asphalt Concrete 1,175.3   TON250.00293,825.00250.00293,825.00249.00292,649.70225.00264,442.50
0019502-01-00200Asphalt Concrete, Drives, Turnouts and Miscellaneous 225.3   TON300.0067,590.00250.0056,325.00312.0070,293.60280.0063,084.00
0020510-01-00001Pavement Patching (14.5 inch minimum thickness)276     SQYD225.0062,100.00200.0055,200.00220.0060,720.00235.0064,860.00
0021511-01-00100Saw Cutting Asphalt Concrete Pavement 470     INLF10.004,700.0020.009,400.006.463,036.204.001,880.00
0022511-03-00100Sawing and Sealing Transverse Joints in Asphalt Concrete Overlay 648     LNFT10.006,480.0020.0012,960.0013.488,735.0412.007,776.00
0023511-04-00100Sawcuts in Asphalt Concrete Lifts 1,080     LNFT6.006,480.0010.0010,800.0011.0011,880.002.002,160.00
0024701-05-02062Side Drain Pipe (Erosion) (24" RPVCP/CMP) 111     LNFT130.0014,430.00100.0011,100.00136.8815,193.68260.0028,860.00
0025701-05-02066Side Drain Pipe (Erosion) (24" RPVCP/CPEPDW/CPPPDW/CMP) 133     LNFT130.0017,290.00100.0013,300.00136.4718,150.51260.0034,580.00
0026701-17-00100Trench Excavation Safety Protection (Depth >5 feet) 466     LNFT10.004,660.0012.005,592.0053.8425,089.440.50233.00
0027702-03-00100Catch Basins (CB-01) 1     EACH6,500.006,500.0010,000.0010,000.006,323.256,323.2513,000.0013,000.00
0028704-03-00100Blocked Out Guard rail 31.3   LNFT36.001,126.8025.00782.5042.001,314.6034.001,064.20
0029704-03-00200Blocked Out Guard Rail - 31", (6'-3" Post Spacing) 606.3   LNFT37.0022,433.1025.0015,157.5028.0016,976.4034.0020,614.20
0030704-05-00100Guard Rail Anchor Sections (Trailing End) 6.3   LNFT175.001,102.50100.00630.00182.001,146.60160.001,008.00
0031704-07-00200Guard Rail Transitions (Double Thrie Beam) 300     LNFT125.0037,500.00100.0030,000.00111.5033,450.00120.0036,000.00
0032704-10-00205Guard Rail End Treatment, MASH, (TL-3 Tangent) 11     EACH3,550.0039,050.003,000.0033,000.003,777.8341,556.133,350.0036,850.00
0033705-02-00100Combination Mesh & Barbed Wire Fence 378     LNFT15.005,670.0016.006,048.0021.178,002.2616.006,048.00
0034708-01-00100Right-of-Way Monument 34     EACH800.0027,200.00600.0020,400.00699.6723,788.78600.0020,400.00
0035708-02-00100Right-of-Way Monument Witness Post 34     EACH400.0013,600.00200.006,800.00242.078,230.38200.006,800.00
0036711-03-00400Riprap (55 lb) 2,836     TON100.00283,600.00100.00283,600.00117.02331,868.72120.00340,320.00
0037711-04-00100Geotextile Fabric 3,500     SQYD4.0014,000.006.0021,000.004.7516,625.002.007,000.00
0038713-01-00100Temporary Signs and Barricades 1     LUMP55,000.0055,000.00150,000.00150,000.0051,480.0051,480.0070,000.0070,000.00
0039713-03-01020Temporary Pavement Markings (Broken Line) (4" W) (4' L) (Type 1 Removable) 0.156 MILE13,000.002,028.001.000.1613,000.002,028.0015,000.002,340.00
0040713-04-01020Temporary Pavement Markings (Solid Line) (4"Width) (Type 1 Removable) 1.252 MILE13,000.0016,276.001.001.2519,060.0023,863.1211,000.0013,772.00
0041713-06-00100Temporary Reflectorized Raised Pavement Markers 1,081     EACH8.509,188.507.007,567.005.926,399.526.006,486.00
0042713-11-00100Portable Changeable Message Signs 1     EACH25,000.0025,000.0025,000.0025,000.0023,331.3223,331.3225,000.0025,000.00
0043720-01-01000Erosion Control System (Slope Protection) (Type A) 734     SQYD2.001,468.001.501,101.003.132,297.422.001,468.00
0044720-01-02000Erosion Control System, Flexible (Channel Liner) (Type C) 696     SQYD2.001,392.001.751,218.003.392,359.442.001,392.00
0045720-01-02020Erosion Control System, Flexible (Channel Liner) (Type D) 1,195     SQYD3.003,585.001.752,091.253.754,481.252.002,390.00
0046720-01-02040Erosion Control System, Flexible (Channel Liner) (Type E) 305     SQYD5.001,525.001.75533.754.851,479.252.00610.00
0047722-02-00100Project Site Laboratory (Equipped) 1     EACH20,000.0020,000.0020,000.0020,000.0039,817.3239,817.3220,000.0020,000.00
0048724-01-00100Rumble Strips (Centerline) 0.269 MILE1,000.00269.001,500.00403.502,230.00599.871,500.00403.50
0049724-02-00100Rumble Strips (Shoulder/Edge) 0.536 MILE1,000.00536.001,500.00804.001,400.00750.401,500.00804.00
0050726-01-00100Bedding Material 0.8   CUYD1,000.00800.00125.00100.002,308.001,846.401,000.00800.00
0051727-01-00100Mobilization 1     LUMP500,000.00500,000.00400,000.00400,000.00532,733.32532,733.32555,000.00555,000.00
0052729-01-00100Sign (Type A) 21     SQFT75.001,575.0025.00525.0048.991,028.7925.00525.00
0053729-01-00200Mounting of Sign (Type A) 3     EACH100.00300.00250.00750.00425.441,276.3220.0060.00
0054729-16-00300Object Marker Assembly (Type 3) 12     EACH150.001,800.00100.001,200.00136.611,639.3290.001,080.00
0055729-22-00100Perforated Square Tubing Post with 2-1/4" Anchor 6     EACH150.00900.0025.00150.00102.72616.32185.001,110.00
0056731-01-00100Nonreflectorized Raised Pavement Markers 1,081     EACH15.0016,215.0012.0012,972.0018.0219,479.6212.0012,972.00
0057731-02-00100Reflectorized Raised Pavement Markers 77     EACH8.00616.006.00462.0027.862,145.226.00462.00
0058732-02-02000Plastic Pavement Striping (Solid Line) (4" Width) (Thermoplastic 90 mil) 1.252 MILE7,000.008,764.006,000.007,512.0013,560.0016,977.126,000.007,512.00
0059732-03-02000Plastic Pavement Striping (Broken Line) (4" Width) (Thermoplastic 90 mil) 0.156 MILE4,500.00702.003,300.00514.805,650.00881.403,000.00468.00
0060735-01-00100Mailboxes 3     EACH100.00300.0050.00150.00205.44616.3230.0090.00
0061735-02-00100Mailbox Supports (Single) 3     EACH100.00300.00100.00300.00260.44781.32255.00765.00
0062739-01-00100Hydro-Seeding 4.44  ACRE3,000.0013,320.003,000.0013,320.003,590.0015,939.602,600.0011,544.00
0063740-01-00100Construction Layout 1     LUMP45,000.0045,000.0050,000.0050,000.0030,178.2630,178.2650,000.0050,000.00
0064804-01-00400Precast Concrete Piles (18") 4,180     LNFT160.00668,800.00160.00668,800.00177.80743,204.00180.00752,400.00
0065805-01-00100Class A1 Concrete (Slab Span) 532.3   CUYD1,500.00798,450.001,200.00638,760.001,437.90765,394.171,225.00652,067.50
0066805-01-00300Class A1 Concrete (Bent Cap) 171.72  CUYD2,250.00386,370.002,000.00343,440.002,633.00452,138.762,300.00394,956.00
0067805-18-00100Concrete Finish (Class 2 Rubbed Finish) 4,148     SQFT1.506,222.004.0016,592.004.1117,048.281.456,014.60
0068805-18-00200Concrete Finish (Class 3 Special Finish) 4,148     SQFT2.008,296.004.0016,592.004.1117,048.282.008,296.00
0069806-01-00100Deformed Reinforcing Steel 126,687     LB1.50190,030.501.10139,355.701.36172,294.321.50190,030.50
0070810-01-00120Concrete Bridge Railing (36 inch Height) 600     LNFT300.00180,000.00275.00165,000.00294.67176,802.00200.00120,000.00
0071813-01-00100Concrete Approach Slabs (Cast-in-Place) 4,320     SQFT100.00432,000.00125.00540,000.00123.15532,008.00100.00432,000.00
0072814-01-00100Elastomeric Bearing Pads (Non-Reinforced) 420     SFIN150.0063,000.00100.0042,000.00134.9756,687.4090.0037,800.00
0073815-03-00300Joint Seal (Poured) 648     LNFT35.0022,680.0025.0016,200.0022.5014,580.0018.0011,664.00
             
  CONTRACTOR TOTAL   5,334,192.00 5,494,893.11 5,499,401.79 5,648,101.00



Line
Number
Item NumberItem DescriptionQuantityUnit of
Measure
- 9 -
Matt L. Guinn Construction, LLC
- 10 -
WL Bass Construction Inc.
Unit PriceTotal
Amount
Unit PriceTotal
Amount
0001201-01-00100Clearing and Grubbing 4.44  LUMP105,000.00105,000.00348,000.00348,000.00
0002202-01-00100Removal of Structures and Obstructions 1     LUMP70,000.0070,000.0012,050.0012,050.00
0003202-02-03030Removal of Pavement Structure 3,699     SQYD10.0036,990.005.0018,495.00
0004202-02-04501Removal of Bridge Bridge Str. No. 084008402700611 (60' x 28' Precast Bridge with Timber Piles)1,680     LUMP40,000.0040,000.0080,000.0080,000.00
0005202-02-04501Removal of Bridge Bridge Str. No. 084008402701801 (40' x 28' Precast Bridge with Timber Piles)1,120     LUMP40,000.0040,000.0070,000.0070,000.00
0006202-02-04501Removal of Bridge Bridge Str. No. 084008402702861 (80' x 28' Precast Bridge with Timber Piles)2,240     LUMP50,000.0050,000.00100,000.00100,000.00
0007202-02-12000Removal of Fence 312     LNFT10.003,120.001.00312.00
0008202-02-14500Removal of Guard Rail 859.7   LNFT20.0017,194.0013.0011,176.10
0009202-03-38000Relocation of Sign 1     EACH400.00400.001,000.001,000.00
0010203-02-00100Drainage Excavation 4,315     CUYD25.00107,875.0025.00107,875.00
0011203-05-00100Excavation and Embankment 1     LUMP175,000.00175,000.00300,000.00300,000.00
0012204-05-00100Temporary Sediment Check Dams (Hay) 24     EACH500.0012,000.00150.003,600.00
0013204-06-00100Temporary Silt Fencing 1,535     LNFT5.007,675.004.006,140.00
0014302-02-04010Class II Base Course (4" Thick) (Asphalt Concrete Base) 5,315.8   SQYD48.00255,158.4040.00212,632.00
0015304-01-00100Lime 18.85  TON400.007,540.00400.007,540.00
0016304-05-00100Lime Treatment (Type E) 1,330     SQYD10.0013,300.008.0010,640.00
0017402-01-00101Traffic Maintenance Surfacing (Aggregate) (Vehicular Measurement) 45     CUYD210.009,450.00135.006,075.00
0018502-01-00100Asphalt Concrete 1,175.3   TON300.00352,590.00167.00196,275.10
0019502-01-00200Asphalt Concrete, Drives, Turnouts and Miscellaneous 225.3   TON390.0087,867.00250.0056,325.00
0020510-01-00001Pavement Patching (14.5 inch minimum thickness)276     SQYD250.0069,000.00300.0082,800.00
0021511-01-00100Saw Cutting Asphalt Concrete Pavement 470     INLF10.004,700.001.00470.00
0022511-03-00100Sawing and Sealing Transverse Joints in Asphalt Concrete Overlay 648     LNFT20.0012,960.0010.006,480.00
0023511-04-00100Sawcuts in Asphalt Concrete Lifts 1,080     LNFT7.007,560.001.001,080.00
0024701-05-02062Side Drain Pipe (Erosion) (24" RPVCP/CMP) 111     LNFT110.0012,210.00120.0013,320.00
0025701-05-02066Side Drain Pipe (Erosion) (24" RPVCP/CPEPDW/CPPPDW/CMP) 133     LNFT110.0014,630.00130.0017,290.00
0026701-17-00100Trench Excavation Safety Protection (Depth >5 feet) 466     LNFT20.009,320.0040.0018,640.00
0027702-03-00100Catch Basins (CB-01) 1     EACH8,000.008,000.0010,000.0010,000.00
0028704-03-00100Blocked Out Guard rail 31.3   LNFT80.002,504.0025.00782.50
0029704-03-00200Blocked Out Guard Rail - 31", (6'-3" Post Spacing) 606.3   LNFT55.0033,346.5025.0015,157.50
0030704-05-00100Guard Rail Anchor Sections (Trailing End) 6.3   LNFT150.00945.00100.00630.00
0031704-07-00200Guard Rail Transitions (Double Thrie Beam) 300     LNFT145.0043,500.00100.0030,000.00
0032704-10-00205Guard Rail End Treatment, MASH, (TL-3 Tangent) 11     EACH4,200.0046,200.003,000.0033,000.00
0033705-02-00100Combination Mesh & Barbed Wire Fence 378     LNFT25.009,450.0016.006,048.00
0034708-01-00100Right-of-Way Monument 34     EACH750.0025,500.00600.0020,400.00
0035708-02-00100Right-of-Way Monument Witness Post 34     EACH300.0010,200.00200.006,800.00
0036711-03-00400Riprap (55 lb) 2,836     TON91.50259,494.00120.00340,320.00
0037711-04-00100Geotextile Fabric 3,500     SQYD4.0014,000.004.0014,000.00
0038713-01-00100Temporary Signs and Barricades 1     LUMP135,000.00135,000.00200,400.00200,400.00
0039713-03-01020Temporary Pavement Markings (Broken Line) (4" W) (4' L) (Type 1 Removable) 0.156 MILE6,000.00936.0010,800.001,684.80
0040713-04-01020Temporary Pavement Markings (Solid Line) (4"Width) (Type 1 Removable) 1.252 MILE6,000.007,512.0010,800.0013,521.60
0041713-06-00100Temporary Reflectorized Raised Pavement Markers 1,081     EACH7.007,567.006.006,486.00
0042713-11-00100Portable Changeable Message Signs 1     EACH7,500.007,500.0030,100.0030,100.00
0043720-01-01000Erosion Control System (Slope Protection) (Type A) 734     SQYD10.007,340.002.001,468.00
0044720-01-02000Erosion Control System, Flexible (Channel Liner) (Type C) 696     SQYD10.006,960.002.001,392.00
0045720-01-02020Erosion Control System, Flexible (Channel Liner) (Type D) 1,195     SQYD10.0011,950.002.002,390.00
0046720-01-02040Erosion Control System, Flexible (Channel Liner) (Type E) 305     SQYD10.003,050.002.00610.00
0047722-02-00100Project Site Laboratory (Equipped) 1     EACH25,000.0025,000.0010,000.0010,000.00
0048724-01-00100Rumble Strips (Centerline) 0.269 MILE10,000.002,690.001,500.00403.50
0049724-02-00100Rumble Strips (Shoulder/Edge) 0.536 MILE10,000.005,360.001,500.00804.00
0050726-01-00100Bedding Material 0.8   CUYD250.00200.00180.00144.00
0051727-01-00100Mobilization 1     LUMP500,000.00500,000.00593,100.00593,100.00
0052729-01-00100Sign (Type A) 21     SQFT200.004,200.0025.00525.00
0053729-01-00200Mounting of Sign (Type A) 3     EACH250.00750.00250.00750.00
0054729-16-00300Object Marker Assembly (Type 3) 12     EACH140.001,680.00100.001,200.00
0055729-22-00100Perforated Square Tubing Post with 2-1/4" Anchor 6     EACH400.002,400.0025.00150.00
0056731-01-00100Nonreflectorized Raised Pavement Markers 1,081     EACH14.0015,134.0012.0012,972.00
0057731-02-00100Reflectorized Raised Pavement Markers 77     EACH8.00616.006.00462.00
0058732-02-02000Plastic Pavement Striping (Solid Line) (4" Width) (Thermoplastic 90 mil) 1.252 MILE7,000.008,764.005,900.007,386.80
0059732-03-02000Plastic Pavement Striping (Broken Line) (4" Width) (Thermoplastic 90 mil) 0.156 MILE4,000.00624.003,900.00608.40
0060735-01-00100Mailboxes 3     EACH300.00900.0050.00150.00
0061735-02-00100Mailbox Supports (Single) 3     EACH200.00600.00100.00300.00
0062739-01-00100Hydro-Seeding 4.44  ACRE5,000.0022,200.002,650.0011,766.00
0063740-01-00100Construction Layout 1     LUMP60,000.0060,000.00192,000.00192,000.00
0064804-01-00400Precast Concrete Piles (18") 4,180     LNFT162.00677,160.00220.00919,600.00
0065805-01-00100Class A1 Concrete (Slab Span) 532.3   CUYD1,700.00904,910.00350.00186,305.00
0066805-01-00300Class A1 Concrete (Bent Cap) 171.72  CUYD2,400.00412,128.00350.0060,102.00
0067805-18-00100Concrete Finish (Class 2 Rubbed Finish) 4,148     SQFT3.0012,444.002.008,296.00
0068805-18-00200Concrete Finish (Class 3 Special Finish) 4,148     SQFT3.0012,444.002.008,296.00
0069806-01-00100Deformed Reinforcing Steel 126,687     LB1.50190,030.504.75601,763.25
0070810-01-00120Concrete Bridge Railing (36 inch Height) 600     LNFT255.00153,000.00300.00180,000.00
0071813-01-00100Concrete Approach Slabs (Cast-in-Place) 4,320     SQFT120.00518,400.00150.00648,000.00
0072814-01-00100Elastomeric Bearing Pads (Non-Reinforced) 420     SFIN205.0086,100.00120.0050,400.00
0073815-03-00300Joint Seal (Poured) 648     LNFT30.0019,440.0020.0012,960.00
         
  CONTRACTOR TOTAL   5,799,668.40 5,931,849.55