Search


Bid Tabulations for the Letting of 3/11/2026 LA DOTD Headquarters

Proposal:H.014872.6
Parish:Union
Routes:LA 3281, LA 348
Description:LA 348 AND LA 3281: REPAIRS
Type Construction:CLEARING AND GRUBBING, GRADING, DRAINAGE STRUCTURES, MILLING ASPHALT PAVEMENT, PAVEMENT PATCHING, IN-PLACE CEMENT STABILIZED BASE COURSE, ASPHALT CONCRETE, OVERLAY, AND RELATED WORK.
Estimated Construction Cost:$3,619,687.64
Rank License BidderConstruction Bid
112487Diamond B Construction Co., L.L.C.$3,932,982.56
205789D & J CONSTRUCTION CO., LLC$4,502,193.87


Line
Number
Item NumberItem DescriptionQuantityUnit of
Measure
- 1 -
Diamond B Construction Co., L.L.C.
- 2 -
D & J CONSTRUCTION CO., LLC
Unit PriceTotal
Amount
Unit PriceTotal
Amount
0001201-01-00100Clearing and Grubbing 0.025 LUMP15,000.0015,000.005,000.005,000.00
0002201-01-00200Clearing and Grubbing (Selective) 6.316 LUMP85,000.0085,000.00100,000.00100,000.00
0003202-01-00100Removal of Structures and Obstructions 1     LUMP15,000.0015,000.0035,000.0035,000.00
0004202-02-06100Removal of Concrete Walks and Drives 245     SQYD25.006,125.0035.008,575.00
0005202-02-06102Removal of Incidental Concrete Paving 375     SQYD45.0016,875.0015.005,625.00
0006202-02-14500Removal of Guard Rail 490     LNFT14.006,860.0030.0014,700.00
0007202-02-32180Removal of Pipe Headwalls 2     EACH15,000.0030,000.002,500.005,000.00
0008203-07-00100Borrow (Vehicular Measurement) 1,243     CUYD55.0068,365.0050.0062,150.00
0009203-10-00100Cleaning Existing Ditches 100     LNFT20.002,000.0010.001,000.00
0010204-06-00100Temporary Silt Fencing 552     LNFT9.004,968.006.003,312.00
0011303-01-00200In-Place Cement Stabilized Base Course (8-1/2" Thick) 5,446     SQYD20.00108,920.0030.00163,380.00
0012303-02-00100Removal of Existing Patches 50     SQYD56.002,800.0025.001,250.00
0013401-02-00100Aggregate Surface Course (Adjusted Vehicular Measurement) 1,544     CUYD205.00316,520.00200.00308,800.00
0014402-01-00101Traffic Maintenance Surfacing (Aggregate) (Vehicular Measurement) 77.2   CUYD150.0011,580.00150.0011,580.00
0015502-01-00100Asphalt Concrete 11,149.7   TON168.001,873,149.60195.002,174,191.50
0016502-01-00200Asphalt Concrete, Drives, Turnouts and Miscellaneous 796.9   TON275.00219,147.50195.00155,395.50
0017509-01-00100Milling Asphalt Pavement 2,631.778 SQYD17.0044,740.2315.0039,476.67
0018509-02-00100Contractor Retained Reclaimed Asphalt Pavement -73     CUYD1.00-73.001.00-73.00
0019510-01-00200Pavement Patching (12" Minimum Thickness) 1,009     SQYD185.00186,665.00320.00322,880.00
0020701-01-01001Cross Drain Pipe (24" RCP) 60     LNFT300.0018,000.00250.0015,000.00
0021701-02-01120Cross Drain Pipe Arch (60" Equiv. RCPA) 48     LNFT650.0031,200.00700.0033,600.00
0022701-02-02120Cross Drain Pipe Arch (42" Equiv. RCPA or 48" Equiv. CMPA) 48     LNFT400.0019,200.00500.0024,000.00
0023701-02-02240Cross Drain Pipe Arch (72" Equiv. RCPA or 84" Equiv. CMPA) 60     LNFT750.0045,000.001,000.0060,000.00
0024701-15-00100Concrete Collar 8     EACH2,500.0020,000.002,500.0020,000.00
0025701-17-00100Trench Excavation Safety Protection (Depth >5 feet) 216     LNFT2.00432.005.001,080.00
0026702-04-00100Adjusting Manholes 1     EACH5,500.005,500.004,000.004,000.00
0027704-01-01020Guard Rail (Single Thrie Beam) (6'-3" post spacing) 311.3   LNFT140.0043,582.00140.0043,582.00
0028704-03-00200Blocked Out Guard Rail - 31", (6'-3" Post Spacing) 81.3   LNFT35.002,845.5040.003,252.00
0029704-10-00204Guard Rail End Treatment, MASH, (TL-2 Tangent) 1     EACH3,900.003,900.004,000.004,000.00
0030704-10-00310Guard Rail End Treatment, NCHRP 350 - 31" (TL-3 Flared) 3     EACH3,900.0011,700.004,200.0012,600.00
0031706-02-00200Concrete Drive (6" Thick) 244.8   SQYD155.0037,944.00150.0036,720.00
0032711-01-04020Riprap (55 lb, 24" Thick) 91     SQYD175.0015,925.00200.0018,200.00
0033711-01-05000Riprap (130 lb, 24" Thick) 50     SQYD265.0013,250.00275.0013,750.00
0034711-04-00100Geotextile Fabric 141     SQYD10.001,410.007.00987.00
0035713-01-00100Temporary Signs and Barricades 1     LUMP85,000.0085,000.00160,000.00160,000.00
0036713-03-01000Temporary Pavement Markings (Broken Line) (4" Width) (4' Length) 11.17  MILE154.001,720.18300.003,351.00
0037713-03-02000Temporary Pavement Markings (Broken Line) (4" Width) (10' Length) 3.519 MILE650.002,287.35600.002,111.40
0038713-04-01000Temporary Pavement Markings (Solid Line) (4" Width) 40.642 MILE950.0038,609.90900.0036,577.80
0039716-01-00100Mulch (Vegetative) 6     TON950.005,700.001,200.007,200.00
0040717-01-00100Seeding 175     LB16.502,887.5022.003,850.00
0041718-01-00100Fertilizer 2,909     LB1.002,909.001.002,909.00
0042726-01-00100Bedding Material 145.6   CUYD190.0027,664.00185.0026,936.00
0043727-01-00100Mobilization 1     LUMP368,000.00368,000.00420,000.00420,000.00
0044729-16-00200Object Marker Assembly (Type 2) 18     EACH120.002,160.00125.002,250.00
0045729-16-00300Object Marker Assembly (Type 3) 9     EACH140.001,260.00145.001,305.00
0046731-02-00100Reflectorized Raised Pavement Markers 862     EACH6.005,172.008.006,896.00
0047732-02-02000Plastic Pavement Striping (Solid Line) (4" Width) (Thermoplastic 90 mil) 14.058 MILE5,000.0070,290.006,000.0084,348.00
0048732-03-02000Plastic Pavement Striping (Broken Line) (4" Width) (Thermoplastic 90 mil) 1.173 MILE1,600.001,876.802,000.002,346.00
0049735-01-00100Mailboxes 15     EACH1.0015.0040.00600.00
0050735-02-00100Mailbox Supports (Single) 13     EACH350.004,550.00350.004,550.00
0051735-03-00100Mailbox Supports (Double) 1     EACH350.00350.00450.00450.00
0052740-01-00100Construction Layout 1     LUMP25,000.0025,000.0025,000.0025,000.00
0053741-35-00100Adjust Valve or Meter Box 1     EACH4,000.004,000.003,500.003,500.00
         
  CONTRACTOR TOTAL   3,932,982.56 4,502,193.87