Proposal:H.014242.6
Parish:Winn
Routes:LA 124
Description:LA 124: BRIDGES NEAR WINNFIELD
Type Construction:CLEARING AND GRUBBING, REMOVAL OF PRECAST CONCRETE BRIDGES, GRADING, DRAINAGE STRUCTURES, PAVEMENT PATCHING, CLASS II BASE COURSE, LIME TREATMENT, ASPHALT CONCRETE PAVEMENT, PRECAST CONCRETE PILES, CONCRETE SLAB SPAN BRIDGES, AND RELATED WORK.
Estimated Construction Cost:$9,271,040.20
| Rank | License | Bidder | Construction Bid |
| 1 | 55505 | MERRICK, LLC | $10,330,565.30 |
| 2 | 39462 | JB JAMES CONSTRUCTION LLC | $10,586,373.00 |
| 3 | 00044 | Guinn Construction, LLC | $10,627,237.30 |
| 4 | 49239 | WL Bass Construction Inc. | $10,811,203.90 |
| 5 | 12487 | Diamond B Construction Co., L.L.C. | $11,286,194.60 |
| 6 | 39613 | Baker Pile Driving and Site Work, LLC | $11,305,100.64 |
| 7 | 12312 | Gilchrist Construction Company, LLC | $11,413,932.15 |
| 8 | 56994 | Matt L. Guinn Construction, LLC | $11,456,036.90 |
| 9 | 27239 | Apeck Construction, LLC | $11,464,093.05 |
| 10 | 01516 | Elevate Heavy Civil Construction, LLC | $11,786,413.45 |
Line Number | Item Number | Item Description | Quantity | Unit of Measure | - 1 - MERRICK, LLC | - 2 - JB JAMES CONSTRUCTION LLC | - 3 - Guinn Construction, LLC | - 4 - WL Bass Construction Inc. | | Unit Price | Total Amount | Unit Price | Total Amount | Unit Price | Total Amount | Unit Price | Total Amount | | 0001 | 201-01-00100 | Clearing and Grubbing | 4.54 | LUMP | 213,000.00 | 213,000.00 | 400,000.00 | 400,000.00 | 150,000.00 | 150,000.00 | 193,000.00 | 193,000.00 | | 0002 | 202-01-00100 | Removal of Structures and Obstructions | 1 | LUMP | 13,000.00 | 13,000.00 | 40,000.00 | 40,000.00 | 50,000.00 | 50,000.00 | 9,920.00 | 9,920.00 | | 0003 | 202-02-03030 | Removal of Pavement Structure | 6,141.1 | SQYD | 8.00 | 49,128.80 | 6.00 | 36,846.60 | 10.00 | 61,411.00 | 8.00 | 49,128.80 | | 0004 | 202-02-04501 | Removal of Bridge Str. No. 086401250108581 (97' x 27.3' Precast Bridge) | 2,648 | LUMP | 35,000.00 | 35,000.00 | 80,000.00 | 80,000.00 | 30,000.00 | 30,000.00 | 45,000.00 | 45,000.00 | | 0005 | 202-02-04501 | Removal of Bridge Str. No. 086401250108811 (134' x 27.3' Precast Bridge) | 3,658 | LUMP | 45,000.00 | 45,000.00 | 80,000.00 | 80,000.00 | 40,000.00 | 40,000.00 | 55,000.00 | 55,000.00 | | 0006 | 202-02-04501 | Removal of Bridge Str. No. 086401250108851 (153' x 27.3' Precast Bridge) | 4,177 | LUMP | 50,000.00 | 50,000.00 | 80,000.00 | 80,000.00 | 46,000.00 | 46,000.00 | 60,000.00 | 60,000.00 | | 0007 | 202-02-04501 | Removal of Bridge Str. No. 0864012501101821 (78' x 27.3' Precast Bridge) | 2,129 | LUMP | 30,000.00 | 30,000.00 | 80,000.00 | 80,000.00 | 25,000.00 | 25,000.00 | 37,000.00 | 37,000.00 | | 0008 | 202-02-04501 | Removal of Bridge Str. No. 86401250102801 (77' x 27.3' Precast Bridge) | 2,102 | LUMP | 30,000.00 | 30,000.00 | 80,000.00 | 80,000.00 | 25,000.00 | 25,000.00 | 35,000.00 | 35,000.00 | | 0009 | 202-02-14500 | Removal of Guard Rail | 1,340.8 | LNFT | 9.00 | 12,067.20 | 4.00 | 5,363.20 | 12.00 | 16,089.60 | 12.00 | 16,089.60 | | 0010 | 202-03-38000 | Relocation of Sign | 1 | EACH | 600.00 | 600.00 | 450.00 | 450.00 | 200.00 | 200.00 | 250.00 | 250.00 | | 0011 | 203-02-00100 | Drainage Excavation | 6,812 | CUYD | 15.00 | 102,180.00 | 10.00 | 68,120.00 | 15.00 | 102,180.00 | 19.00 | 129,428.00 | | 0012 | 203-05-00100 | Excavation and Embankment | 1 | LUMP | 213,000.00 | 213,000.00 | 175,000.00 | 175,000.00 | 175,000.00 | 175,000.00 | 250,000.00 | 250,000.00 | | 0013 | 204-05-00100 | Temporary Sediment Check Dams (Hay) | 32 | EACH | 170.00 | 5,440.00 | 150.00 | 4,800.00 | 200.00 | 6,400.00 | 150.00 | 4,800.00 | | 0014 | 204-06-00100 | Temporary Silt Fencing | 3,984 | LNFT | 3.00 | 11,952.00 | 6.00 | 23,904.00 | 3.00 | 11,952.00 | 2.50 | 9,960.00 | | 0015 | 302-02-08080 | Class II Base Course (8" Thick) (Asphalt Concrete Base) | 7,069.3 | SQYD | 85.00 | 600,890.50 | 84.00 | 593,821.20 | 92.00 | 650,375.60 | 85.00 | 600,890.50 | | 0016 | 304-01-00100 | Lime | 25.04 | TON | 250.00 | 6,260.00 | 240.00 | 6,009.60 | 500.00 | 12,520.00 | 425.00 | 10,642.00 | | 0017 | 304-05-00100 | Lime Treatment (Type E) | 1,767 | SQYD | 2.50 | 4,417.50 | 8.00 | 14,136.00 | 5.00 | 8,835.00 | 7.00 | 12,369.00 | | 0018 | 401-02-00100 | Aggregate Surface Course (Adjusted Vehicular Measurement) | 9 | CUYD | 300.00 | 2,700.00 | 300.00 | 2,700.00 | 250.00 | 2,250.00 | 140.00 | 1,260.00 | | 0019 | 402-01-00101 | Traffic Maintenance Surfacing (Aggregate) (Vehicular Measurement) | 100 | CUYD | 125.00 | 12,500.00 | 250.00 | 25,000.00 | 150.00 | 15,000.00 | 138.00 | 13,800.00 | | 0020 | 502-01-00100 | Asphalt Concrete | 1,571.8 | TON | 245.00 | 385,091.00 | 235.00 | 369,373.00 | 275.00 | 432,245.00 | 240.00 | 377,232.00 | | 0021 | 502-01-00200 | Asphalt Concrete, Drives, Turnouts and Miscellaneous | 278.2 | TON | 330.00 | 91,806.00 | 300.00 | 83,460.00 | 350.00 | 97,370.00 | 300.00 | 83,460.00 | | 0022 | 510-01-00001 | Pavement Patching (14.5 inch minimum thickness) | 368 | SQYD | 230.00 | 84,640.00 | 210.00 | 77,280.00 | 242.00 | 89,056.00 | 250.00 | 92,000.00 | | 0023 | 511-01-00100 | Saw Cutting Asphalt Concrete Pavement | 1,227 | INLF | 4.00 | 4,908.00 | 3.00 | 3,681.00 | 2.00 | 2,454.00 | 2.00 | 2,454.00 | | 0024 | 511-03-00100 | Sawing and Sealing Transverse Joints in Asphalt Concrete Overlay | 864 | LNFT | 12.00 | 10,368.00 | 7.00 | 6,048.00 | 5.00 | 4,320.00 | 10.00 | 8,640.00 | | 0025 | 511-04-00100 | Sawcuts in Asphalt Concrete Lifts | 1,440 | LNFT | 3.00 | 4,320.00 | 2.00 | 2,880.00 | 3.00 | 4,320.00 | 2.00 | 2,880.00 | | 0026 | 701-05-02045 | Side Drain Pipe (Erosion) (18" RPVCP/CPEPDW/CPPPDW) | 140 | LNFT | 100.00 | 14,000.00 | 117.00 | 16,380.00 | 75.00 | 10,500.00 | 90.00 | 12,600.00 | | 0027 | 701-05-02087 | Side Drain Pipe (Erosion) (30" RPVCP/CPEPDW/CPPPDW/CPPPTW) | 94 | LNFT | 140.00 | 13,160.00 | 165.00 | 15,510.00 | 185.00 | 17,390.00 | 110.00 | 10,340.00 | | 0028 | 701-17-00100 | Trench Excavation Safety Protection (Depth >5 feet) | 140 | LNFT | 10.00 | 1,400.00 | 1.00 | 140.00 | 10.00 | 1,400.00 | 140.00 | 19,600.00 | | 0029 | 702-08-00100 | Side Drain Safety End (Type 1) | 1 | EACH | 5,000.00 | 5,000.00 | 4,000.00 | 4,000.00 | 3,500.00 | 3,500.00 | 3,500.00 | 3,500.00 | | 0030 | 704-03-00200 | Blocked Out Guard Rail - 31", (6'-3" Post Spacing) | 1,150 | LNFT | 32.00 | 36,800.00 | 29.00 | 33,350.00 | 38.00 | 43,700.00 | 29.00 | 33,350.00 | | 0031 | 704-07-00200 | Guard Rail Transitions (Double Thrie Beam) | 400 | LNFT | 125.00 | 50,000.00 | 115.00 | 46,000.00 | 145.00 | 58,000.00 | 115.00 | 46,000.00 | | 0032 | 704-10-00205 | Guard Rail End Treatment, MASH, (TL-3 Tangent) | 16 | EACH | 3,500.00 | 56,000.00 | 4,000.00 | 64,000.00 | 4,450.00 | 71,200.00 | 3,300.00 | 52,800.00 | | 0033 | 708-01-00100 | Right-of-Way Monument | 48 | EACH | 650.00 | 31,200.00 | 600.00 | 28,800.00 | 900.00 | 43,200.00 | 600.00 | 28,800.00 | | 0034 | 708-02-00100 | Right-of-Way Monument Witness Post | 48 | EACH | 225.00 | 10,800.00 | 200.00 | 9,600.00 | 300.00 | 14,400.00 | 200.00 | 9,600.00 | | 0035 | 711-03-00400 | Riprap (55 lb) | 2,187.2 | TON | 85.00 | 185,912.00 | 90.00 | 196,848.00 | 100.00 | 218,720.00 | 100.00 | 218,720.00 | | 0036 | 711-03-00500 | Riprap (130 lb) | 4,351.5 | TON | 90.00 | 391,635.00 | 115.00 | 500,422.50 | 102.00 | 443,853.00 | 110.00 | 478,665.00 | | 0037 | 711-04-00100 | Geotextile Fabric | 5,979 | SQYD | 4.00 | 23,916.00 | 2.00 | 11,958.00 | 2.00 | 11,958.00 | 4.00 | 23,916.00 | | 0038 | 713-01-00100 | Temporary Signs and Barricades | 1 | LUMP | 130,000.00 | 130,000.00 | 180,000.00 | 180,000.00 | 65,000.00 | 65,000.00 | 500,000.00 | 500,000.00 | | 0039 | 713-04-01020 | Temporary Pavement Markings (Solid Line) (4"Width) (Type 1 Removable) | 2.04 | MILE | 9,500.00 | 19,380.00 | 9,000.00 | 18,360.00 | 10,000.00 | 20,400.00 | 8,950.00 | 18,258.00 | | 0040 | 713-06-00100 | Temporary Reflectorized Raised Pavement Markers | 69 | EACH | 6.00 | 414.00 | 5.00 | 345.00 | 10.00 | 690.00 | 5.00 | 345.00 | | 0041 | 720-01-01000 | Erosion Control System (Slope Protection) (Type A) | 161 | SQYD | 6.00 | 966.00 | 3.00 | 483.00 | 10.00 | 1,610.00 | 2.00 | 322.00 | | 0042 | 720-01-02020 | Erosion Control System, Flexible (Channel Liner) (Type D) | 78 | SQYD | 6.00 | 468.00 | 3.00 | 234.00 | 10.00 | 780.00 | 2.00 | 156.00 | | 0043 | 720-01-02060 | Erosion Control System, Flexible (Channel Liner) (Type F) | 108 | SQYD | 6.00 | 648.00 | 3.00 | 324.00 | 10.00 | 1,080.00 | 2.00 | 216.00 | | 0044 | 724-01-00100 | Rumble Strips (Centerline) | 0.347 | MILE | 1,500.00 | 520.50 | 300.00 | 104.10 | 1,000.00 | 347.00 | 1,000.00 | 347.00 | | 0045 | 724-02-00100 | Rumble Strips (Shoulder/Edge) | 0.694 | MILE | 1,500.00 | 1,041.00 | 300.00 | 208.20 | 1,000.00 | 694.00 | 1,000.00 | 694.00 | | 0046 | 727-01-00100 | Mobilization | 1 | LUMP | 1,000,000.00 | 1,000,000.00 | 1,050,000.00 | 1,050,000.00 | 850,000.00 | 850,000.00 | 1,081,000.00 | 1,081,000.00 | | 0047 | 729-16-00300 | Object Marker Assembly (Type 3) | 16 | EACH | 100.00 | 1,600.00 | 85.00 | 1,360.00 | 150.00 | 2,400.00 | 85.00 | 1,360.00 | | 0048 | 731-01-00100 | Nonreflectorized Raised Pavement Markers | 2,214 | EACH | 9.00 | 19,926.00 | 9.00 | 19,926.00 | 12.00 | 26,568.00 | 9.00 | 19,926.00 | | 0049 | 731-02-00100 | Reflectorized Raised Pavement Markers | 69 | EACH | 9.00 | 621.00 | 5.00 | 345.00 | 10.00 | 690.00 | 5.00 | 345.00 | | 0050 | 732-02-02000 | Plastic Pavement Striping (Solid Line) (4" Width) (Thermoplastic 90 mil) | 1.064 | MILE | 9,200.00 | 9,788.80 | 8,000.00 | 8,512.00 | 10,000.00 | 10,640.00 | 8,000.00 | 8,512.00 | | 0051 | 732-03-02000 | Plastic Pavement Striping (Broken Line) (4" Width) (Thermoplastic 90 mil) | 0.51 | MILE | 4,000.00 | 2,040.00 | 3,700.00 | 1,887.00 | 5,000.00 | 2,550.00 | 3,500.00 | 1,785.00 | | 0052 | 739-01-00100 | Hydro-Seeding | 4.54 | ACRE | 3,200.00 | 14,528.00 | 3,000.00 | 13,620.00 | 3,500.00 | 15,890.00 | 2,800.00 | 12,712.00 | | 0053 | 740-01-00100 | Construction Layout | 1 | LUMP | 85,000.00 | 85,000.00 | 30,000.00 | 30,000.00 | 60,000.00 | 60,000.00 | 150,000.00 | 150,000.00 | | 0054 | 804-01-00400 | Precast Concrete Piles (18") | 12,020 | LNFT | 160.00 | 1,923,200.00 | 140.00 | 1,682,800.00 | 160.00 | 1,923,200.00 | 180.00 | 2,163,600.00 | | 0055 | 804-17-00100 | Construction Site Survey | 1 | LUMP | 13,000.00 | 13,000.00 | 45,000.00 | 45,000.00 | 15,000.00 | 15,000.00 | 10,000.00 | 10,000.00 | | 0056 | 804-18-00100 | Vibration Monitoring | 6 | DAY | 1,500.00 | 9,000.00 | 1,550.00 | 9,300.00 | 1,550.00 | 9,300.00 | 340.00 | 2,040.00 | | 0057 | 805-01-00100 | Class A1 Concrete (Slab Span) | 1,250.2 | CUYD | 1,375.00 | 1,719,025.00 | 1,300.00 | 1,625,260.00 | 1,750.00 | 2,187,850.00 | 750.00 | 937,650.00 | | 0058 | 805-01-00300 | Class A1 Concrete (Bent Cap) | 361.26 | CUYD | 2,500.00 | 903,150.00 | 2,100.00 | 758,646.00 | 2,250.00 | 812,835.00 | 800.00 | 289,008.00 | | 0059 | 805-18-00100 | Concrete Finish (Class 2 Rubbed Finish) | 9,408 | SQFT | 3.00 | 28,224.00 | 2.00 | 18,816.00 | 2.00 | 18,816.00 | 2.00 | 18,816.00 | | 0060 | 805-18-00200 | Concrete Finish (Class 3 Special Finish) | 9,408 | SQFT | 3.00 | 28,224.00 | 2.00 | 18,816.00 | 2.00 | 18,816.00 | 2.00 | 18,816.00 | | 0061 | 806-01-00100 | Deformed Reinforcing Steel | 423,166 | LB | 1.50 | 634,749.00 | 1.60 | 677,065.60 | 1.35 | 571,274.10 | 3.50 | 1,481,081.00 | | 0062 | 810-01-00120 | Concrete Bridge Railing (36 inch Height) | 1,400 | LNFT | 155.00 | 217,000.00 | 210.00 | 294,000.00 | 200.00 | 280,000.00 | 140.00 | 196,000.00 | | 0063 | 813-01-00100 | Concrete Approach Slabs (Cast-in-Place) | 5,760 | SQFT | 95.00 | 547,200.00 | 130.00 | 748,800.00 | 100.00 | 576,000.00 | 125.00 | 720,000.00 | | 0064 | 814-01-00100 | Elastomeric Bearing Pads (Non-Reinforced) | 980 | SFIN | 165.00 | 161,700.00 | 90.00 | 88,200.00 | 133.60 | 130,928.00 | 100.00 | 98,000.00 | | 0065 | 815-03-00300 | Joint Seal (Poured) | 1,404 | LNFT | 15.00 | 21,060.00 | 20.00 | 28,080.00 | 20.00 | 28,080.00 | 30.00 | 42,120.00 | | | | | | | | | | | | | | | | | | CONTRACTOR TOTAL | | | | 10,330,565.30 | | 10,586,373.00 | | 10,627,237.30 | | 10,811,203.90 |
Line Number | Item Number | Item Description | Quantity | Unit of Measure | - 5 - Diamond B Construction Co., L.L.C. | - 6 - Baker Pile Driving and Site Work, LLC | - 7 - Gilchrist Construction Company, LLC | - 8 - Matt L. Guinn Construction, LLC | | Unit Price | Total Amount | Unit Price | Total Amount | Unit Price | Total Amount | Unit Price | Total Amount | | 0001 | 201-01-00100 | Clearing and Grubbing | 4.54 | LUMP | 150,000.00 | 150,000.00 | 84,000.00 | 84,000.00 | 500,000.00 | 500,000.00 | 235,000.00 | 235,000.00 | | 0002 | 202-01-00100 | Removal of Structures and Obstructions | 1 | LUMP | 50,000.00 | 50,000.00 | 5,600.00 | 5,600.00 | 25,000.00 | 25,000.00 | 30,000.00 | 30,000.00 | | 0003 | 202-02-03030 | Removal of Pavement Structure | 6,141.1 | SQYD | 14.00 | 85,975.40 | 5.60 | 34,390.16 | 11.00 | 67,552.10 | 9.00 | 55,269.90 | | 0004 | 202-02-04501 | Removal of Bridge Str. No. 086401250108581 (97' x 27.3' Precast Bridge) | 2,648 | LUMP | 35,000.00 | 35,000.00 | 31,098.56 | 31,098.56 | 100,000.00 | 100,000.00 | 60,000.00 | 60,000.00 | | 0005 | 202-02-04501 | Removal of Bridge Str. No. 086401250108811 (134' x 27.3' Precast Bridge) | 3,658 | LUMP | 50,000.00 | 50,000.00 | 32,838.27 | 32,838.27 | 100,000.00 | 100,000.00 | 78,000.00 | 78,000.00 | | 0006 | 202-02-04501 | Removal of Bridge Str. No. 086401250108851 (153' x 27.3' Precast Bridge) | 4,177 | LUMP | 35,000.00 | 35,000.00 | 35,697.97 | 35,697.97 | 125,000.00 | 125,000.00 | 80,000.00 | 80,000.00 | | 0007 | 202-02-04501 | Removal of Bridge Str. No. 0864012501101821 (78' x 27.3' Precast Bridge) | 2,129 | LUMP | 85,000.00 | 85,000.00 | 29,358.84 | 29,358.84 | 100,000.00 | 100,000.00 | 35,000.00 | 35,000.00 | | 0008 | 202-02-04501 | Removal of Bridge Str. No. 86401250102801 (77' x 27.3' Precast Bridge) | 2,102 | LUMP | 95,000.00 | 95,000.00 | 29,358.84 | 29,358.84 | 100,000.00 | 100,000.00 | 40,000.00 | 40,000.00 | | 0009 | 202-02-14500 | Removal of Guard Rail | 1,340.8 | LNFT | 25.00 | 33,520.00 | 9.00 | 12,067.20 | 9.00 | 12,067.20 | 9.00 | 12,067.20 | | 0010 | 202-03-38000 | Relocation of Sign | 1 | EACH | 5,000.00 | 5,000.00 | 294.00 | 294.00 | 260.00 | 260.00 | 1,000.00 | 1,000.00 | | 0011 | 203-02-00100 | Drainage Excavation | 6,812 | CUYD | 12.00 | 81,744.00 | 12.15 | 82,765.80 | 22.00 | 149,864.00 | 20.00 | 136,240.00 | | 0012 | 203-05-00100 | Excavation and Embankment | 1 | LUMP | 135,000.00 | 135,000.00 | 168,000.00 | 168,000.00 | 300,000.00 | 300,000.00 | 180,000.00 | 180,000.00 | | 0013 | 204-05-00100 | Temporary Sediment Check Dams (Hay) | 32 | EACH | 150.00 | 4,800.00 | 162.40 | 5,196.80 | 140.00 | 4,480.00 | 200.00 | 6,400.00 | | 0014 | 204-06-00100 | Temporary Silt Fencing | 3,984 | LNFT | 2.00 | 7,968.00 | 2.24 | 8,924.16 | 3.00 | 11,952.00 | 3.00 | 11,952.00 | | 0015 | 302-02-08080 | Class II Base Course (8" Thick) (Asphalt Concrete Base) | 7,069.3 | SQYD | 65.00 | 459,504.50 | 94.00 | 664,514.20 | 75.00 | 530,197.50 | 85.00 | 600,890.50 | | 0016 | 304-01-00100 | Lime | 25.04 | TON | 450.00 | 11,268.00 | 798.00 | 19,981.92 | 575.00 | 14,398.00 | 350.00 | 8,764.00 | | 0017 | 304-05-00100 | Lime Treatment (Type E) | 1,767 | SQYD | 6.00 | 10,602.00 | 17.64 | 31,169.88 | 30.00 | 53,010.00 | 15.00 | 26,505.00 | | 0018 | 401-02-00100 | Aggregate Surface Course (Adjusted Vehicular Measurement) | 9 | CUYD | 145.00 | 1,305.00 | 254.21 | 2,287.89 | 200.00 | 1,800.00 | 200.00 | 1,800.00 | | 0019 | 402-01-00101 | Traffic Maintenance Surfacing (Aggregate) (Vehicular Measurement) | 100 | CUYD | 145.00 | 14,500.00 | 200.85 | 20,085.00 | 175.00 | 17,500.00 | 140.00 | 14,000.00 | | 0020 | 502-01-00100 | Asphalt Concrete | 1,571.8 | TON | 190.00 | 298,642.00 | 263.20 | 413,697.76 | 220.00 | 345,796.00 | 275.00 | 432,245.00 | | 0021 | 502-01-00200 | Asphalt Concrete, Drives, Turnouts and Miscellaneous | 278.2 | TON | 290.00 | 80,678.00 | 336.00 | 93,475.20 | 220.00 | 61,204.00 | 335.00 | 93,197.00 | | 0022 | 510-01-00001 | Pavement Patching (14.5 inch minimum thickness) | 368 | SQYD | 212.00 | 78,016.00 | 235.20 | 86,553.60 | 230.00 | 84,640.00 | 245.00 | 90,160.00 | | 0023 | 511-01-00100 | Saw Cutting Asphalt Concrete Pavement | 1,227 | INLF | 3.00 | 3,681.00 | 6.57 | 8,061.39 | 12.00 | 14,724.00 | 6.00 | 7,362.00 | | 0024 | 511-03-00100 | Sawing and Sealing Transverse Joints in Asphalt Concrete Overlay | 864 | LNFT | 12.00 | 10,368.00 | 6.85 | 5,918.40 | 18.00 | 15,552.00 | 6.00 | 5,184.00 | | 0025 | 511-04-00100 | Sawcuts in Asphalt Concrete Lifts | 1,440 | LNFT | 12.00 | 17,280.00 | 9.25 | 13,320.00 | 20.00 | 28,800.00 | 15.00 | 21,600.00 | | 0026 | 701-05-02045 | Side Drain Pipe (Erosion) (18" RPVCP/CPEPDW/CPPPDW) | 140 | LNFT | 110.00 | 15,400.00 | 108.24 | 15,153.60 | 125.00 | 17,500.00 | 120.00 | 16,800.00 | | 0027 | 701-05-02087 | Side Drain Pipe (Erosion) (30" RPVCP/CPEPDW/CPPPDW/CPPPTW) | 94 | LNFT | 112.00 | 10,528.00 | 220.11 | 20,690.34 | 210.00 | 19,740.00 | 170.00 | 15,980.00 | | 0028 | 701-17-00100 | Trench Excavation Safety Protection (Depth >5 feet) | 140 | LNFT | 36.00 | 5,040.00 | 200.00 | 28,000.00 | 60.00 | 8,400.00 | 5.00 | 700.00 | | 0029 | 702-08-00100 | Side Drain Safety End (Type 1) | 1 | EACH | 2,500.00 | 2,500.00 | 5,040.00 | 5,040.00 | 11,000.00 | 11,000.00 | 3,750.00 | 3,750.00 | | 0030 | 704-03-00200 | Blocked Out Guard Rail - 31", (6'-3" Post Spacing) | 1,150 | LNFT | 35.00 | 40,250.00 | 28.00 | 32,200.00 | 30.00 | 34,500.00 | 55.00 | 63,250.00 | | 0031 | 704-07-00200 | Guard Rail Transitions (Double Thrie Beam) | 400 | LNFT | 135.00 | 54,000.00 | 112.00 | 44,800.00 | 116.00 | 46,400.00 | 148.00 | 59,200.00 | | 0032 | 704-10-00205 | Guard Rail End Treatment, MASH, (TL-3 Tangent) | 16 | EACH | 4,000.00 | 64,000.00 | 3,920.00 | 62,720.00 | 3,400.00 | 54,400.00 | 4,150.00 | 66,400.00 | | 0033 | 708-01-00100 | Right-of-Way Monument | 48 | EACH | 600.00 | 28,800.00 | 746.12 | 35,813.76 | 610.00 | 29,280.00 | 650.00 | 31,200.00 | | 0034 | 708-02-00100 | Right-of-Way Monument Witness Post | 48 | EACH | 200.00 | 9,600.00 | 298.12 | 14,309.76 | 210.00 | 10,080.00 | 250.00 | 12,000.00 | | 0035 | 711-03-00400 | Riprap (55 lb) | 2,187.2 | TON | 105.00 | 229,656.00 | 89.60 | 195,973.12 | 90.00 | 196,848.00 | 120.00 | 262,464.00 | | 0036 | 711-03-00500 | Riprap (130 lb) | 4,351.5 | TON | 105.00 | 456,907.50 | 112.00 | 487,368.00 | 90.00 | 391,635.00 | 130.00 | 565,695.00 | | 0037 | 711-04-00100 | Geotextile Fabric | 5,979 | SQYD | 1.00 | 5,979.00 | 3.82 | 22,839.78 | 3.50 | 20,926.50 | 4.00 | 23,916.00 | | 0038 | 713-01-00100 | Temporary Signs and Barricades | 1 | LUMP | 450,000.00 | 450,000.00 | 20,207.04 | 20,207.04 | 250,000.00 | 250,000.00 | 145,000.00 | 145,000.00 | | 0039 | 713-04-01020 | Temporary Pavement Markings (Solid Line) (4"Width) (Type 1 Removable) | 2.04 | MILE | 9,000.00 | 18,360.00 | 10,024.00 | 20,448.96 | 10,000.00 | 20,400.00 | 8,500.00 | 17,340.00 | | 0040 | 713-06-00100 | Temporary Reflectorized Raised Pavement Markers | 69 | EACH | 5.00 | 345.00 | 5.60 | 386.40 | 5.10 | 351.90 | 7.00 | 483.00 | | 0041 | 720-01-01000 | Erosion Control System (Slope Protection) (Type A) | 161 | SQYD | 2.00 | 322.00 | 2.41 | 388.01 | 2.85 | 458.85 | 6.00 | 966.00 | | 0042 | 720-01-02020 | Erosion Control System, Flexible (Channel Liner) (Type D) | 78 | SQYD | 2.00 | 156.00 | 3.30 | 257.40 | 2.95 | 230.10 | 5.00 | 390.00 | | 0043 | 720-01-02060 | Erosion Control System, Flexible (Channel Liner) (Type F) | 108 | SQYD | 2.00 | 216.00 | 3.30 | 356.40 | 3.00 | 324.00 | 5.00 | 540.00 | | 0044 | 724-01-00100 | Rumble Strips (Centerline) | 0.347 | MILE | 1,100.00 | 381.70 | 6,150.00 | 2,134.05 | 1,000.00 | 347.00 | 3,500.00 | 1,214.50 | | 0045 | 724-02-00100 | Rumble Strips (Shoulder/Edge) | 0.694 | MILE | 1,000.00 | 694.00 | 3,250.00 | 2,255.50 | 1,000.00 | 694.00 | 3,500.00 | 2,429.00 | | 0046 | 727-01-00100 | Mobilization | 1 | LUMP | 975,000.00 | 975,000.00 | 799,482.19 | 799,482.19 | 1,000,000.00 | 1,000,000.00 | 900,000.00 | 900,000.00 | | 0047 | 729-16-00300 | Object Marker Assembly (Type 3) | 16 | EACH | 135.00 | 2,160.00 | 334.37 | 5,349.92 | 90.00 | 1,440.00 | 200.00 | 3,200.00 | | 0048 | 731-01-00100 | Nonreflectorized Raised Pavement Markers | 2,214 | EACH | 9.00 | 19,926.00 | 10.73 | 23,756.22 | 10.00 | 22,140.00 | 7.00 | 15,498.00 | | 0049 | 731-02-00100 | Reflectorized Raised Pavement Markers | 69 | EACH | 5.00 | 345.00 | 18.21 | 1,256.49 | 6.00 | 414.00 | 7.00 | 483.00 | | 0050 | 732-02-02000 | Plastic Pavement Striping (Solid Line) (4" Width) (Thermoplastic 90 mil) | 1.064 | MILE | 8,000.00 | 8,512.00 | 9,780.00 | 10,405.92 | 8,000.00 | 8,512.00 | 8,500.00 | 9,044.00 | | 0051 | 732-03-02000 | Plastic Pavement Striping (Broken Line) (4" Width) (Thermoplastic 90 mil) | 0.51 | MILE | 3,500.00 | 1,785.00 | 5,626.00 | 2,869.26 | 4,000.00 | 2,040.00 | 4,250.00 | 2,167.50 | | 0052 | 739-01-00100 | Hydro-Seeding | 4.54 | ACRE | 3,000.00 | 13,620.00 | 3,410.00 | 15,481.40 | 3,000.00 | 13,620.00 | 3,000.00 | 13,620.00 | | 0053 | 740-01-00100 | Construction Layout | 1 | LUMP | 172,000.00 | 172,000.00 | 96,120.94 | 96,120.94 | 140,000.00 | 140,000.00 | 70,000.00 | 70,000.00 | | 0054 | 804-01-00400 | Precast Concrete Piles (18") | 12,020 | LNFT | 200.00 | 2,404,000.00 | 180.38 | 2,168,167.60 | 215.00 | 2,584,300.00 | 158.00 | 1,899,160.00 | | 0055 | 804-17-00100 | Construction Site Survey | 1 | LUMP | 10,000.00 | 10,000.00 | 67,200.00 | 67,200.00 | 67,000.00 | 67,000.00 | 70,000.00 | 70,000.00 | | 0056 | 804-18-00100 | Vibration Monitoring | 6 | DAY | 1,500.00 | 9,000.00 | 1,026.67 | 6,160.02 | 1,000.00 | 6,000.00 | 1,500.00 | 9,000.00 | | 0057 | 805-01-00100 | Class A1 Concrete (Slab Span) | 1,250.2 | CUYD | 1,400.00 | 1,750,280.00 | 1,713.00 | 2,141,592.60 | 1,000.00 | 1,250,200.00 | 1,725.00 | 2,156,595.00 | | 0058 | 805-01-00300 | Class A1 Concrete (Bent Cap) | 361.26 | CUYD | 2,900.00 | 1,047,654.00 | 3,131.00 | 1,131,105.06 | 1,800.00 | 650,268.00 | 2,700.00 | 975,402.00 | | 0059 | 805-18-00100 | Concrete Finish (Class 2 Rubbed Finish) | 9,408 | SQFT | 3.00 | 28,224.00 | 4.97 | 46,757.76 | 2.50 | 23,520.00 | 2.00 | 18,816.00 | | 0060 | 805-18-00200 | Concrete Finish (Class 3 Special Finish) | 9,408 | SQFT | 3.25 | 30,576.00 | 2.86 | 26,906.88 | 2.50 | 23,520.00 | 2.00 | 18,816.00 | | 0061 | 806-01-00100 | Deformed Reinforcing Steel | 423,166 | LB | 1.25 | 528,957.50 | 1.41 | 596,664.06 | 1.00 | 423,166.00 | 1.55 | 655,907.30 | | 0062 | 810-01-00120 | Concrete Bridge Railing (36 inch Height) | 1,400 | LNFT | 215.00 | 301,000.00 | 269.30 | 377,020.00 | 250.00 | 350,000.00 | 200.00 | 280,000.00 | | 0063 | 813-01-00100 | Concrete Approach Slabs (Cast-in-Place) | 5,760 | SQFT | 112.00 | 645,120.00 | 117.26 | 675,417.60 | 150.00 | 864,000.00 | 115.00 | 662,400.00 | | 0064 | 814-01-00100 | Elastomeric Bearing Pads (Non-Reinforced) | 980 | SFIN | 90.00 | 88,200.00 | 128.98 | 126,400.40 | 80.00 | 78,400.00 | 120.00 | 117,600.00 | | 0065 | 815-03-00300 | Joint Seal (Poured) | 1,404 | LNFT | 12.00 | 16,848.00 | 40.59 | 56,988.36 | 20.00 | 28,080.00 | 18.50 | 25,974.00 | | | | | | | | | | | | | | | | | | CONTRACTOR TOTAL | | | | 11,286,194.60 | | 11,305,100.64 | | 11,413,932.15 | | 11,456,036.90 |
Line Number | Item Number | Item Description | Quantity | Unit of Measure | - 9 - Apeck Construction, LLC | - 10 - Elevate Heavy Civil Construction, LLC | | Unit Price | Total Amount | Unit Price | Total Amount | | 0001 | 201-01-00100 | Clearing and Grubbing | 4.54 | LUMP | 2,059,961.22 | 2,059,961.22 | 950,000.00 | 950,000.00 | | 0002 | 202-01-00100 | Removal of Structures and Obstructions | 1 | LUMP | 28,113.56 | 28,113.56 | 20,000.00 | 20,000.00 | | 0003 | 202-02-03030 | Removal of Pavement Structure | 6,141.1 | SQYD | 14.85 | 91,195.34 | 5.50 | 33,776.05 | | 0004 | 202-02-04501 | Removal of Bridge Str. No. 086401250108581 (97' x 27.3' Precast Bridge) | 2,648 | LUMP | 32,657.03 | 32,657.03 | 100,000.00 | 100,000.00 | | 0005 | 202-02-04501 | Removal of Bridge Str. No. 086401250108811 (134' x 27.3' Precast Bridge) | 3,658 | LUMP | 48,985.56 | 48,985.56 | 100,000.00 | 100,000.00 | | 0006 | 202-02-04501 | Removal of Bridge Str. No. 086401250108851 (153' x 27.3' Precast Bridge) | 4,177 | LUMP | 53,351.76 | 53,351.76 | 100,000.00 | 100,000.00 | | 0007 | 202-02-04501 | Removal of Bridge Str. No. 0864012501101821 (78' x 27.3' Precast Bridge) | 2,129 | LUMP | 24,492.82 | 24,492.82 | 100,000.00 | 100,000.00 | | 0008 | 202-02-04501 | Removal of Bridge Str. No. 86401250102801 (77' x 27.3' Precast Bridge) | 2,102 | LUMP | 28,843.22 | 28,843.22 | 100,000.00 | 100,000.00 | | 0009 | 202-02-14500 | Removal of Guard Rail | 1,340.8 | LNFT | 14.92 | 20,004.74 | 5.00 | 6,704.00 | | 0010 | 202-03-38000 | Relocation of Sign | 1 | EACH | 757.41 | 757.41 | 2,000.00 | 2,000.00 | | 0011 | 203-02-00100 | Drainage Excavation | 6,812 | CUYD | 22.08 | 150,408.96 | 9.00 | 61,308.00 | | 0012 | 203-05-00100 | Excavation and Embankment | 1 | LUMP | 112,795.45 | 112,795.45 | 290,000.00 | 290,000.00 | | 0013 | 204-05-00100 | Temporary Sediment Check Dams (Hay) | 32 | EACH | 178.59 | 5,714.88 | 150.00 | 4,800.00 | | 0014 | 204-06-00100 | Temporary Silt Fencing | 3,984 | LNFT | 3.57 | 14,222.88 | 2.50 | 9,960.00 | | 0015 | 302-02-08080 | Class II Base Course (8" Thick) (Asphalt Concrete Base) | 7,069.3 | SQYD | 92.05 | 650,729.07 | 84.00 | 593,821.20 | | 0016 | 304-01-00100 | Lime | 25.04 | TON | 666.44 | 16,687.66 | 200.00 | 5,008.00 | | 0017 | 304-05-00100 | Lime Treatment (Type E) | 1,767 | SQYD | 5.29 | 9,347.43 | 10.00 | 17,670.00 | | 0018 | 401-02-00100 | Aggregate Surface Course (Adjusted Vehicular Measurement) | 9 | CUYD | 158.75 | 1,428.75 | 290.00 | 2,610.00 | | 0019 | 402-01-00101 | Traffic Maintenance Surfacing (Aggregate) (Vehicular Measurement) | 100 | CUYD | 178.59 | 17,859.00 | 200.00 | 20,000.00 | | 0020 | 502-01-00100 | Asphalt Concrete | 1,571.8 | TON | 275.16 | 432,496.49 | 240.00 | 377,232.00 | | 0021 | 502-01-00200 | Asphalt Concrete, Drives, Turnouts and Miscellaneous | 278.2 | TON | 195.46 | 54,376.97 | 300.00 | 83,460.00 | | 0022 | 510-01-00001 | Pavement Patching (14.5 inch minimum thickness) | 368 | SQYD | 233.72 | 86,008.96 | 210.00 | 77,280.00 | | 0023 | 511-01-00100 | Saw Cutting Asphalt Concrete Pavement | 1,227 | INLF | 6.84 | 8,392.68 | 3.00 | 3,681.00 | | 0024 | 511-03-00100 | Sawing and Sealing Transverse Joints in Asphalt Concrete Overlay | 864 | LNFT | 20.16 | 17,418.24 | 8.00 | 6,912.00 | | 0025 | 511-04-00100 | Sawcuts in Asphalt Concrete Lifts | 1,440 | LNFT | 12.10 | 17,424.00 | 2.00 | 2,880.00 | | 0026 | 701-05-02045 | Side Drain Pipe (Erosion) (18" RPVCP/CPEPDW/CPPPDW) | 140 | LNFT | 122.53 | 17,154.20 | 80.00 | 11,200.00 | | 0027 | 701-05-02087 | Side Drain Pipe (Erosion) (30" RPVCP/CPEPDW/CPPPDW/CPPPTW) | 94 | LNFT | 174.86 | 16,436.84 | 180.00 | 16,920.00 | | 0028 | 701-17-00100 | Trench Excavation Safety Protection (Depth >5 feet) | 140 | LNFT | 5.95 | 833.00 | 15.00 | 2,100.00 | | 0029 | 702-08-00100 | Side Drain Safety End (Type 1) | 1 | EACH | 3,734.65 | 3,734.65 | 4,500.00 | 4,500.00 | | 0030 | 704-03-00200 | Blocked Out Guard Rail - 31", (6'-3" Post Spacing) | 1,150 | LNFT | 39.29 | 45,183.50 | 29.00 | 33,350.00 | | 0031 | 704-07-00200 | Guard Rail Transitions (Double Thrie Beam) | 400 | LNFT | 154.78 | 61,912.00 | 115.00 | 46,000.00 | | 0032 | 704-10-00205 | Guard Rail End Treatment, MASH, (TL-3 Tangent) | 16 | EACH | 4,762.43 | 76,198.88 | 3,300.00 | 52,800.00 | | 0033 | 708-01-00100 | Right-of-Way Monument | 48 | EACH | 714.36 | 34,289.28 | 600.00 | 28,800.00 | | 0034 | 708-02-00100 | Right-of-Way Monument Witness Post | 48 | EACH | 238.12 | 11,429.76 | 200.00 | 9,600.00 | | 0035 | 711-03-00400 | Riprap (55 lb) | 2,187.2 | TON | 95.58 | 209,052.58 | 85.00 | 185,912.00 | | 0036 | 711-03-00500 | Riprap (130 lb) | 4,351.5 | TON | 100.50 | 437,325.75 | 100.00 | 435,150.00 | | 0037 | 711-04-00100 | Geotextile Fabric | 5,979 | SQYD | 2.13 | 12,735.27 | 3.00 | 17,937.00 | | 0038 | 713-01-00100 | Temporary Signs and Barricades | 1 | LUMP | 100,230.93 | 100,230.93 | 240,000.00 | 240,000.00 | | 0039 | 713-04-01020 | Temporary Pavement Markings (Solid Line) (4"Width) (Type 1 Removable) | 2.04 | MILE | 10,655.94 | 21,738.12 | 9,000.00 | 18,360.00 | | 0040 | 713-06-00100 | Temporary Reflectorized Raised Pavement Markers | 69 | EACH | 5.95 | 410.55 | 5.00 | 345.00 | | 0041 | 720-01-01000 | Erosion Control System (Slope Protection) (Type A) | 161 | SQYD | 2.38 | 383.18 | 2.00 | 322.00 | | 0042 | 720-01-02020 | Erosion Control System, Flexible (Channel Liner) (Type D) | 78 | SQYD | 2.38 | 185.64 | 2.00 | 156.00 | | 0043 | 720-01-02060 | Erosion Control System, Flexible (Channel Liner) (Type F) | 108 | SQYD | 2.38 | 257.04 | 2.00 | 216.00 | | 0044 | 724-01-00100 | Rumble Strips (Centerline) | 0.347 | MILE | 360.26 | 125.01 | 500.00 | 173.50 | | 0045 | 724-02-00100 | Rumble Strips (Shoulder/Edge) | 0.694 | MILE | 360.27 | 250.03 | 500.00 | 347.00 | | 0046 | 727-01-00100 | Mobilization | 1 | LUMP | 263,315.46 | 263,315.46 | 1,180,000.00 | 1,180,000.00 | | 0047 | 729-16-00300 | Object Marker Assembly (Type 3) | 16 | EACH | 160.73 | 2,571.68 | 90.00 | 1,440.00 | | 0048 | 731-01-00100 | Nonreflectorized Raised Pavement Markers | 2,214 | EACH | 10.72 | 23,734.08 | 9.00 | 19,926.00 | | 0049 | 731-02-00100 | Reflectorized Raised Pavement Markers | 69 | EACH | 5.95 | 410.55 | 5.00 | 345.00 | | 0050 | 732-02-02000 | Plastic Pavement Striping (Solid Line) (4" Width) (Thermoplastic 90 mil) | 1.064 | MILE | 9,578.57 | 10,191.60 | 8,000.00 | 8,512.00 | | 0051 | 732-03-02000 | Plastic Pavement Striping (Broken Line) (4" Width) (Thermoplastic 90 mil) | 0.51 | MILE | 4,167.12 | 2,125.23 | 3,500.00 | 1,785.00 | | 0052 | 739-01-00100 | Hydro-Seeding | 4.54 | ACRE | 3,333.70 | 15,135.00 | 2,800.00 | 12,712.00 | | 0053 | 740-01-00100 | Construction Layout | 1 | LUMP | 68,117.13 | 68,117.13 | 250,000.00 | 250,000.00 | | 0054 | 804-01-00400 | Precast Concrete Piles (18") | 12,020 | LNFT | 78.58 | 944,531.60 | 145.00 | 1,742,900.00 | | 0055 | 804-17-00100 | Construction Site Survey | 1 | LUMP | 11,667.96 | 11,667.96 | 10,000.00 | 10,000.00 | | 0056 | 804-18-00100 | Vibration Monitoring | 6 | DAY | 2,024.03 | 12,144.18 | 1,500.00 | 9,000.00 | | 0057 | 805-01-00100 | Class A1 Concrete (Slab Span) | 1,250.2 | CUYD | 1,845.75 | 2,307,556.65 | 1,250.00 | 1,562,750.00 | | 0058 | 805-01-00300 | Class A1 Concrete (Bent Cap) | 361.26 | CUYD | 2,662.97 | 962,024.54 | 2,500.00 | 903,150.00 | | 0059 | 805-18-00100 | Concrete Finish (Class 2 Rubbed Finish) | 9,408 | SQFT | 7.45 | 70,089.60 | 2.50 | 23,520.00 | | 0060 | 805-18-00200 | Concrete Finish (Class 3 Special Finish) | 9,408 | SQFT | 7.45 | 70,089.60 | 3.00 | 28,224.00 | | 0061 | 806-01-00100 | Deformed Reinforcing Steel | 423,166 | LB | 1.31 | 554,347.46 | 1.45 | 613,590.70 | | 0062 | 810-01-00120 | Concrete Bridge Railing (36 inch Height) | 1,400 | LNFT | 267.20 | 374,080.00 | 240.00 | 336,000.00 | | 0063 | 813-01-00100 | Concrete Approach Slabs (Cast-in-Place) | 5,760 | SQFT | 109.67 | 631,699.20 | 135.00 | 777,600.00 | | 0064 | 814-01-00100 | Elastomeric Bearing Pads (Non-Reinforced) | 980 | SFIN | 91.12 | 89,297.60 | 110.00 | 107,800.00 | | 0065 | 815-03-00300 | Joint Seal (Poured) | 1,404 | LNFT | 12.41 | 17,423.64 | 17.00 | 23,868.00 | | | | | | | | | | | | | | CONTRACTOR TOTAL | | | | 11,464,093.05 | | 11,786,413.45 |
|