Bid Tabulations for the Letting of 3/11/2026 LA DOTD Headquarters

Proposal:H.014242.6
Parish:Winn
Routes:LA 124
Description:LA 124: BRIDGES NEAR WINNFIELD
Type Construction:CLEARING AND GRUBBING, REMOVAL OF PRECAST CONCRETE BRIDGES, GRADING, DRAINAGE STRUCTURES, PAVEMENT PATCHING, CLASS II BASE COURSE, LIME TREATMENT, ASPHALT CONCRETE PAVEMENT, PRECAST CONCRETE PILES, CONCRETE SLAB SPAN BRIDGES, AND RELATED WORK.
Estimated Construction Cost:$9,271,040.20
Rank License BidderConstruction Bid
155505MERRICK, LLC$10,330,565.30
239462JB JAMES CONSTRUCTION LLC$10,586,373.00
300044Guinn Construction, LLC$10,627,237.30
449239WL Bass Construction Inc.$10,811,203.90
512487Diamond B Construction Co., L.L.C.$11,286,194.60
639613Baker Pile Driving and Site Work, LLC$11,305,100.64
712312Gilchrist Construction Company, LLC$11,413,932.15
856994Matt L. Guinn Construction, LLC$11,456,036.90
927239Apeck Construction, LLC$11,464,093.05
1001516Elevate Heavy Civil Construction, LLC$11,786,413.45


Line
Number
Item NumberItem DescriptionQuantityUnit of
Measure
- 1 -
MERRICK, LLC
- 2 -
JB JAMES CONSTRUCTION LLC
- 3 -
Guinn Construction, LLC
- 4 -
WL Bass Construction Inc.
Unit PriceTotal
Amount
Unit PriceTotal
Amount
Unit PriceTotal
Amount
Unit PriceTotal
Amount
0001201-01-00100Clearing and Grubbing 4.54  LUMP213,000.00213,000.00400,000.00400,000.00150,000.00150,000.00193,000.00193,000.00
0002202-01-00100Removal of Structures and Obstructions 1     LUMP13,000.0013,000.0040,000.0040,000.0050,000.0050,000.009,920.009,920.00
0003202-02-03030Removal of Pavement Structure 6,141.1   SQYD8.0049,128.806.0036,846.6010.0061,411.008.0049,128.80
0004202-02-04501Removal of Bridge Str. No. 086401250108581 (97' x 27.3' Precast Bridge)2,648     LUMP35,000.0035,000.0080,000.0080,000.0030,000.0030,000.0045,000.0045,000.00
0005202-02-04501Removal of Bridge Str. No. 086401250108811 (134' x 27.3' Precast Bridge)3,658     LUMP45,000.0045,000.0080,000.0080,000.0040,000.0040,000.0055,000.0055,000.00
0006202-02-04501Removal of Bridge Str. No. 086401250108851 (153' x 27.3' Precast Bridge)4,177     LUMP50,000.0050,000.0080,000.0080,000.0046,000.0046,000.0060,000.0060,000.00
0007202-02-04501Removal of Bridge Str. No. 0864012501101821 (78' x 27.3' Precast Bridge)2,129     LUMP30,000.0030,000.0080,000.0080,000.0025,000.0025,000.0037,000.0037,000.00
0008202-02-04501Removal of Bridge Str. No. 86401250102801 (77' x 27.3' Precast Bridge)2,102     LUMP30,000.0030,000.0080,000.0080,000.0025,000.0025,000.0035,000.0035,000.00
0009202-02-14500Removal of Guard Rail 1,340.8   LNFT9.0012,067.204.005,363.2012.0016,089.6012.0016,089.60
0010202-03-38000Relocation of Sign 1     EACH600.00600.00450.00450.00200.00200.00250.00250.00
0011203-02-00100Drainage Excavation 6,812     CUYD15.00102,180.0010.0068,120.0015.00102,180.0019.00129,428.00
0012203-05-00100Excavation and Embankment 1     LUMP213,000.00213,000.00175,000.00175,000.00175,000.00175,000.00250,000.00250,000.00
0013204-05-00100Temporary Sediment Check Dams (Hay) 32     EACH170.005,440.00150.004,800.00200.006,400.00150.004,800.00
0014204-06-00100Temporary Silt Fencing 3,984     LNFT3.0011,952.006.0023,904.003.0011,952.002.509,960.00
0015302-02-08080Class II Base Course (8" Thick) (Asphalt Concrete Base) 7,069.3   SQYD85.00600,890.5084.00593,821.2092.00650,375.6085.00600,890.50
0016304-01-00100Lime 25.04  TON250.006,260.00240.006,009.60500.0012,520.00425.0010,642.00
0017304-05-00100Lime Treatment (Type E) 1,767     SQYD2.504,417.508.0014,136.005.008,835.007.0012,369.00
0018401-02-00100Aggregate Surface Course (Adjusted Vehicular Measurement) 9     CUYD300.002,700.00300.002,700.00250.002,250.00140.001,260.00
0019402-01-00101Traffic Maintenance Surfacing (Aggregate) (Vehicular Measurement) 100     CUYD125.0012,500.00250.0025,000.00150.0015,000.00138.0013,800.00
0020502-01-00100Asphalt Concrete 1,571.8   TON245.00385,091.00235.00369,373.00275.00432,245.00240.00377,232.00
0021502-01-00200Asphalt Concrete, Drives, Turnouts and Miscellaneous 278.2   TON330.0091,806.00300.0083,460.00350.0097,370.00300.0083,460.00
0022510-01-00001Pavement Patching (14.5 inch minimum thickness)368     SQYD230.0084,640.00210.0077,280.00242.0089,056.00250.0092,000.00
0023511-01-00100Saw Cutting Asphalt Concrete Pavement 1,227     INLF4.004,908.003.003,681.002.002,454.002.002,454.00
0024511-03-00100Sawing and Sealing Transverse Joints in Asphalt Concrete Overlay 864     LNFT12.0010,368.007.006,048.005.004,320.0010.008,640.00
0025511-04-00100Sawcuts in Asphalt Concrete Lifts 1,440     LNFT3.004,320.002.002,880.003.004,320.002.002,880.00
0026701-05-02045Side Drain Pipe (Erosion) (18" RPVCP/CPEPDW/CPPPDW) 140     LNFT100.0014,000.00117.0016,380.0075.0010,500.0090.0012,600.00
0027701-05-02087Side Drain Pipe (Erosion) (30" RPVCP/CPEPDW/CPPPDW/CPPPTW) 94     LNFT140.0013,160.00165.0015,510.00185.0017,390.00110.0010,340.00
0028701-17-00100Trench Excavation Safety Protection (Depth >5 feet) 140     LNFT10.001,400.001.00140.0010.001,400.00140.0019,600.00
0029702-08-00100Side Drain Safety End (Type 1) 1     EACH5,000.005,000.004,000.004,000.003,500.003,500.003,500.003,500.00
0030704-03-00200Blocked Out Guard Rail - 31", (6'-3" Post Spacing) 1,150     LNFT32.0036,800.0029.0033,350.0038.0043,700.0029.0033,350.00
0031704-07-00200Guard Rail Transitions (Double Thrie Beam) 400     LNFT125.0050,000.00115.0046,000.00145.0058,000.00115.0046,000.00
0032704-10-00205Guard Rail End Treatment, MASH, (TL-3 Tangent) 16     EACH3,500.0056,000.004,000.0064,000.004,450.0071,200.003,300.0052,800.00
0033708-01-00100Right-of-Way Monument 48     EACH650.0031,200.00600.0028,800.00900.0043,200.00600.0028,800.00
0034708-02-00100Right-of-Way Monument Witness Post 48     EACH225.0010,800.00200.009,600.00300.0014,400.00200.009,600.00
0035711-03-00400Riprap (55 lb) 2,187.2   TON85.00185,912.0090.00196,848.00100.00218,720.00100.00218,720.00
0036711-03-00500Riprap (130 lb) 4,351.5   TON90.00391,635.00115.00500,422.50102.00443,853.00110.00478,665.00
0037711-04-00100Geotextile Fabric 5,979     SQYD4.0023,916.002.0011,958.002.0011,958.004.0023,916.00
0038713-01-00100Temporary Signs and Barricades 1     LUMP130,000.00130,000.00180,000.00180,000.0065,000.0065,000.00500,000.00500,000.00
0039713-04-01020Temporary Pavement Markings (Solid Line) (4"Width) (Type 1 Removable) 2.04  MILE9,500.0019,380.009,000.0018,360.0010,000.0020,400.008,950.0018,258.00
0040713-06-00100Temporary Reflectorized Raised Pavement Markers 69     EACH6.00414.005.00345.0010.00690.005.00345.00
0041720-01-01000Erosion Control System (Slope Protection) (Type A) 161     SQYD6.00966.003.00483.0010.001,610.002.00322.00
0042720-01-02020Erosion Control System, Flexible (Channel Liner) (Type D) 78     SQYD6.00468.003.00234.0010.00780.002.00156.00
0043720-01-02060Erosion Control System, Flexible (Channel Liner) (Type F) 108     SQYD6.00648.003.00324.0010.001,080.002.00216.00
0044724-01-00100Rumble Strips (Centerline) 0.347 MILE1,500.00520.50300.00104.101,000.00347.001,000.00347.00
0045724-02-00100Rumble Strips (Shoulder/Edge) 0.694 MILE1,500.001,041.00300.00208.201,000.00694.001,000.00694.00
0046727-01-00100Mobilization 1     LUMP1,000,000.001,000,000.001,050,000.001,050,000.00850,000.00850,000.001,081,000.001,081,000.00
0047729-16-00300Object Marker Assembly (Type 3) 16     EACH100.001,600.0085.001,360.00150.002,400.0085.001,360.00
0048731-01-00100Nonreflectorized Raised Pavement Markers 2,214     EACH9.0019,926.009.0019,926.0012.0026,568.009.0019,926.00
0049731-02-00100Reflectorized Raised Pavement Markers 69     EACH9.00621.005.00345.0010.00690.005.00345.00
0050732-02-02000Plastic Pavement Striping (Solid Line) (4" Width) (Thermoplastic 90 mil) 1.064 MILE9,200.009,788.808,000.008,512.0010,000.0010,640.008,000.008,512.00
0051732-03-02000Plastic Pavement Striping (Broken Line) (4" Width) (Thermoplastic 90 mil) 0.51  MILE4,000.002,040.003,700.001,887.005,000.002,550.003,500.001,785.00
0052739-01-00100Hydro-Seeding 4.54  ACRE3,200.0014,528.003,000.0013,620.003,500.0015,890.002,800.0012,712.00
0053740-01-00100Construction Layout 1     LUMP85,000.0085,000.0030,000.0030,000.0060,000.0060,000.00150,000.00150,000.00
0054804-01-00400Precast Concrete Piles (18") 12,020     LNFT160.001,923,200.00140.001,682,800.00160.001,923,200.00180.002,163,600.00
0055804-17-00100Construction Site Survey 1     LUMP13,000.0013,000.0045,000.0045,000.0015,000.0015,000.0010,000.0010,000.00
0056804-18-00100Vibration Monitoring 6     DAY1,500.009,000.001,550.009,300.001,550.009,300.00340.002,040.00
0057805-01-00100Class A1 Concrete (Slab Span) 1,250.2   CUYD1,375.001,719,025.001,300.001,625,260.001,750.002,187,850.00750.00937,650.00
0058805-01-00300Class A1 Concrete (Bent Cap) 361.26  CUYD2,500.00903,150.002,100.00758,646.002,250.00812,835.00800.00289,008.00
0059805-18-00100Concrete Finish (Class 2 Rubbed Finish) 9,408     SQFT3.0028,224.002.0018,816.002.0018,816.002.0018,816.00
0060805-18-00200Concrete Finish (Class 3 Special Finish) 9,408     SQFT3.0028,224.002.0018,816.002.0018,816.002.0018,816.00
0061806-01-00100Deformed Reinforcing Steel 423,166     LB1.50634,749.001.60677,065.601.35571,274.103.501,481,081.00
0062810-01-00120Concrete Bridge Railing (36 inch Height) 1,400     LNFT155.00217,000.00210.00294,000.00200.00280,000.00140.00196,000.00
0063813-01-00100Concrete Approach Slabs (Cast-in-Place) 5,760     SQFT95.00547,200.00130.00748,800.00100.00576,000.00125.00720,000.00
0064814-01-00100Elastomeric Bearing Pads (Non-Reinforced) 980     SFIN165.00161,700.0090.0088,200.00133.60130,928.00100.0098,000.00
0065815-03-00300Joint Seal (Poured) 1,404     LNFT15.0021,060.0020.0028,080.0020.0028,080.0030.0042,120.00
             
  CONTRACTOR TOTAL   10,330,565.30 10,586,373.00 10,627,237.30 10,811,203.90



Line
Number
Item NumberItem DescriptionQuantityUnit of
Measure
- 5 -
Diamond B Construction Co., L.L.C.
- 6 -
Baker Pile Driving and Site Work, LLC
- 7 -
Gilchrist Construction Company, LLC
- 8 -
Matt L. Guinn Construction, LLC
Unit PriceTotal
Amount
Unit PriceTotal
Amount
Unit PriceTotal
Amount
Unit PriceTotal
Amount
0001201-01-00100Clearing and Grubbing 4.54  LUMP150,000.00150,000.0084,000.0084,000.00500,000.00500,000.00235,000.00235,000.00
0002202-01-00100Removal of Structures and Obstructions 1     LUMP50,000.0050,000.005,600.005,600.0025,000.0025,000.0030,000.0030,000.00
0003202-02-03030Removal of Pavement Structure 6,141.1   SQYD14.0085,975.405.6034,390.1611.0067,552.109.0055,269.90
0004202-02-04501Removal of Bridge Str. No. 086401250108581 (97' x 27.3' Precast Bridge)2,648     LUMP35,000.0035,000.0031,098.5631,098.56100,000.00100,000.0060,000.0060,000.00
0005202-02-04501Removal of Bridge Str. No. 086401250108811 (134' x 27.3' Precast Bridge)3,658     LUMP50,000.0050,000.0032,838.2732,838.27100,000.00100,000.0078,000.0078,000.00
0006202-02-04501Removal of Bridge Str. No. 086401250108851 (153' x 27.3' Precast Bridge)4,177     LUMP35,000.0035,000.0035,697.9735,697.97125,000.00125,000.0080,000.0080,000.00
0007202-02-04501Removal of Bridge Str. No. 0864012501101821 (78' x 27.3' Precast Bridge)2,129     LUMP85,000.0085,000.0029,358.8429,358.84100,000.00100,000.0035,000.0035,000.00
0008202-02-04501Removal of Bridge Str. No. 86401250102801 (77' x 27.3' Precast Bridge)2,102     LUMP95,000.0095,000.0029,358.8429,358.84100,000.00100,000.0040,000.0040,000.00
0009202-02-14500Removal of Guard Rail 1,340.8   LNFT25.0033,520.009.0012,067.209.0012,067.209.0012,067.20
0010202-03-38000Relocation of Sign 1     EACH5,000.005,000.00294.00294.00260.00260.001,000.001,000.00
0011203-02-00100Drainage Excavation 6,812     CUYD12.0081,744.0012.1582,765.8022.00149,864.0020.00136,240.00
0012203-05-00100Excavation and Embankment 1     LUMP135,000.00135,000.00168,000.00168,000.00300,000.00300,000.00180,000.00180,000.00
0013204-05-00100Temporary Sediment Check Dams (Hay) 32     EACH150.004,800.00162.405,196.80140.004,480.00200.006,400.00
0014204-06-00100Temporary Silt Fencing 3,984     LNFT2.007,968.002.248,924.163.0011,952.003.0011,952.00
0015302-02-08080Class II Base Course (8" Thick) (Asphalt Concrete Base) 7,069.3   SQYD65.00459,504.5094.00664,514.2075.00530,197.5085.00600,890.50
0016304-01-00100Lime 25.04  TON450.0011,268.00798.0019,981.92575.0014,398.00350.008,764.00
0017304-05-00100Lime Treatment (Type E) 1,767     SQYD6.0010,602.0017.6431,169.8830.0053,010.0015.0026,505.00
0018401-02-00100Aggregate Surface Course (Adjusted Vehicular Measurement) 9     CUYD145.001,305.00254.212,287.89200.001,800.00200.001,800.00
0019402-01-00101Traffic Maintenance Surfacing (Aggregate) (Vehicular Measurement) 100     CUYD145.0014,500.00200.8520,085.00175.0017,500.00140.0014,000.00
0020502-01-00100Asphalt Concrete 1,571.8   TON190.00298,642.00263.20413,697.76220.00345,796.00275.00432,245.00
0021502-01-00200Asphalt Concrete, Drives, Turnouts and Miscellaneous 278.2   TON290.0080,678.00336.0093,475.20220.0061,204.00335.0093,197.00
0022510-01-00001Pavement Patching (14.5 inch minimum thickness)368     SQYD212.0078,016.00235.2086,553.60230.0084,640.00245.0090,160.00
0023511-01-00100Saw Cutting Asphalt Concrete Pavement 1,227     INLF3.003,681.006.578,061.3912.0014,724.006.007,362.00
0024511-03-00100Sawing and Sealing Transverse Joints in Asphalt Concrete Overlay 864     LNFT12.0010,368.006.855,918.4018.0015,552.006.005,184.00
0025511-04-00100Sawcuts in Asphalt Concrete Lifts 1,440     LNFT12.0017,280.009.2513,320.0020.0028,800.0015.0021,600.00
0026701-05-02045Side Drain Pipe (Erosion) (18" RPVCP/CPEPDW/CPPPDW) 140     LNFT110.0015,400.00108.2415,153.60125.0017,500.00120.0016,800.00
0027701-05-02087Side Drain Pipe (Erosion) (30" RPVCP/CPEPDW/CPPPDW/CPPPTW) 94     LNFT112.0010,528.00220.1120,690.34210.0019,740.00170.0015,980.00
0028701-17-00100Trench Excavation Safety Protection (Depth >5 feet) 140     LNFT36.005,040.00200.0028,000.0060.008,400.005.00700.00
0029702-08-00100Side Drain Safety End (Type 1) 1     EACH2,500.002,500.005,040.005,040.0011,000.0011,000.003,750.003,750.00
0030704-03-00200Blocked Out Guard Rail - 31", (6'-3" Post Spacing) 1,150     LNFT35.0040,250.0028.0032,200.0030.0034,500.0055.0063,250.00
0031704-07-00200Guard Rail Transitions (Double Thrie Beam) 400     LNFT135.0054,000.00112.0044,800.00116.0046,400.00148.0059,200.00
0032704-10-00205Guard Rail End Treatment, MASH, (TL-3 Tangent) 16     EACH4,000.0064,000.003,920.0062,720.003,400.0054,400.004,150.0066,400.00
0033708-01-00100Right-of-Way Monument 48     EACH600.0028,800.00746.1235,813.76610.0029,280.00650.0031,200.00
0034708-02-00100Right-of-Way Monument Witness Post 48     EACH200.009,600.00298.1214,309.76210.0010,080.00250.0012,000.00
0035711-03-00400Riprap (55 lb) 2,187.2   TON105.00229,656.0089.60195,973.1290.00196,848.00120.00262,464.00
0036711-03-00500Riprap (130 lb) 4,351.5   TON105.00456,907.50112.00487,368.0090.00391,635.00130.00565,695.00
0037711-04-00100Geotextile Fabric 5,979     SQYD1.005,979.003.8222,839.783.5020,926.504.0023,916.00
0038713-01-00100Temporary Signs and Barricades 1     LUMP450,000.00450,000.0020,207.0420,207.04250,000.00250,000.00145,000.00145,000.00
0039713-04-01020Temporary Pavement Markings (Solid Line) (4"Width) (Type 1 Removable) 2.04  MILE9,000.0018,360.0010,024.0020,448.9610,000.0020,400.008,500.0017,340.00
0040713-06-00100Temporary Reflectorized Raised Pavement Markers 69     EACH5.00345.005.60386.405.10351.907.00483.00
0041720-01-01000Erosion Control System (Slope Protection) (Type A) 161     SQYD2.00322.002.41388.012.85458.856.00966.00
0042720-01-02020Erosion Control System, Flexible (Channel Liner) (Type D) 78     SQYD2.00156.003.30257.402.95230.105.00390.00
0043720-01-02060Erosion Control System, Flexible (Channel Liner) (Type F) 108     SQYD2.00216.003.30356.403.00324.005.00540.00
0044724-01-00100Rumble Strips (Centerline) 0.347 MILE1,100.00381.706,150.002,134.051,000.00347.003,500.001,214.50
0045724-02-00100Rumble Strips (Shoulder/Edge) 0.694 MILE1,000.00694.003,250.002,255.501,000.00694.003,500.002,429.00
0046727-01-00100Mobilization 1     LUMP975,000.00975,000.00799,482.19799,482.191,000,000.001,000,000.00900,000.00900,000.00
0047729-16-00300Object Marker Assembly (Type 3) 16     EACH135.002,160.00334.375,349.9290.001,440.00200.003,200.00
0048731-01-00100Nonreflectorized Raised Pavement Markers 2,214     EACH9.0019,926.0010.7323,756.2210.0022,140.007.0015,498.00
0049731-02-00100Reflectorized Raised Pavement Markers 69     EACH5.00345.0018.211,256.496.00414.007.00483.00
0050732-02-02000Plastic Pavement Striping (Solid Line) (4" Width) (Thermoplastic 90 mil) 1.064 MILE8,000.008,512.009,780.0010,405.928,000.008,512.008,500.009,044.00
0051732-03-02000Plastic Pavement Striping (Broken Line) (4" Width) (Thermoplastic 90 mil) 0.51  MILE3,500.001,785.005,626.002,869.264,000.002,040.004,250.002,167.50
0052739-01-00100Hydro-Seeding 4.54  ACRE3,000.0013,620.003,410.0015,481.403,000.0013,620.003,000.0013,620.00
0053740-01-00100Construction Layout 1     LUMP172,000.00172,000.0096,120.9496,120.94140,000.00140,000.0070,000.0070,000.00
0054804-01-00400Precast Concrete Piles (18") 12,020     LNFT200.002,404,000.00180.382,168,167.60215.002,584,300.00158.001,899,160.00
0055804-17-00100Construction Site Survey 1     LUMP10,000.0010,000.0067,200.0067,200.0067,000.0067,000.0070,000.0070,000.00
0056804-18-00100Vibration Monitoring 6     DAY1,500.009,000.001,026.676,160.021,000.006,000.001,500.009,000.00
0057805-01-00100Class A1 Concrete (Slab Span) 1,250.2   CUYD1,400.001,750,280.001,713.002,141,592.601,000.001,250,200.001,725.002,156,595.00
0058805-01-00300Class A1 Concrete (Bent Cap) 361.26  CUYD2,900.001,047,654.003,131.001,131,105.061,800.00650,268.002,700.00975,402.00
0059805-18-00100Concrete Finish (Class 2 Rubbed Finish) 9,408     SQFT3.0028,224.004.9746,757.762.5023,520.002.0018,816.00
0060805-18-00200Concrete Finish (Class 3 Special Finish) 9,408     SQFT3.2530,576.002.8626,906.882.5023,520.002.0018,816.00
0061806-01-00100Deformed Reinforcing Steel 423,166     LB1.25528,957.501.41596,664.061.00423,166.001.55655,907.30
0062810-01-00120Concrete Bridge Railing (36 inch Height) 1,400     LNFT215.00301,000.00269.30377,020.00250.00350,000.00200.00280,000.00
0063813-01-00100Concrete Approach Slabs (Cast-in-Place) 5,760     SQFT112.00645,120.00117.26675,417.60150.00864,000.00115.00662,400.00
0064814-01-00100Elastomeric Bearing Pads (Non-Reinforced) 980     SFIN90.0088,200.00128.98126,400.4080.0078,400.00120.00117,600.00
0065815-03-00300Joint Seal (Poured) 1,404     LNFT12.0016,848.0040.5956,988.3620.0028,080.0018.5025,974.00
             
  CONTRACTOR TOTAL   11,286,194.60 11,305,100.64 11,413,932.15 11,456,036.90



Line
Number
Item NumberItem DescriptionQuantityUnit of
Measure
- 9 -
Apeck Construction, LLC
- 10 -
Elevate Heavy Civil Construction, LLC
Unit PriceTotal
Amount
Unit PriceTotal
Amount
0001201-01-00100Clearing and Grubbing 4.54  LUMP2,059,961.222,059,961.22950,000.00950,000.00
0002202-01-00100Removal of Structures and Obstructions 1     LUMP28,113.5628,113.5620,000.0020,000.00
0003202-02-03030Removal of Pavement Structure 6,141.1   SQYD14.8591,195.345.5033,776.05
0004202-02-04501Removal of Bridge Str. No. 086401250108581 (97' x 27.3' Precast Bridge)2,648     LUMP32,657.0332,657.03100,000.00100,000.00
0005202-02-04501Removal of Bridge Str. No. 086401250108811 (134' x 27.3' Precast Bridge)3,658     LUMP48,985.5648,985.56100,000.00100,000.00
0006202-02-04501Removal of Bridge Str. No. 086401250108851 (153' x 27.3' Precast Bridge)4,177     LUMP53,351.7653,351.76100,000.00100,000.00
0007202-02-04501Removal of Bridge Str. No. 0864012501101821 (78' x 27.3' Precast Bridge)2,129     LUMP24,492.8224,492.82100,000.00100,000.00
0008202-02-04501Removal of Bridge Str. No. 86401250102801 (77' x 27.3' Precast Bridge)2,102     LUMP28,843.2228,843.22100,000.00100,000.00
0009202-02-14500Removal of Guard Rail 1,340.8   LNFT14.9220,004.745.006,704.00
0010202-03-38000Relocation of Sign 1     EACH757.41757.412,000.002,000.00
0011203-02-00100Drainage Excavation 6,812     CUYD22.08150,408.969.0061,308.00
0012203-05-00100Excavation and Embankment 1     LUMP112,795.45112,795.45290,000.00290,000.00
0013204-05-00100Temporary Sediment Check Dams (Hay) 32     EACH178.595,714.88150.004,800.00
0014204-06-00100Temporary Silt Fencing 3,984     LNFT3.5714,222.882.509,960.00
0015302-02-08080Class II Base Course (8" Thick) (Asphalt Concrete Base) 7,069.3   SQYD92.05650,729.0784.00593,821.20
0016304-01-00100Lime 25.04  TON666.4416,687.66200.005,008.00
0017304-05-00100Lime Treatment (Type E) 1,767     SQYD5.299,347.4310.0017,670.00
0018401-02-00100Aggregate Surface Course (Adjusted Vehicular Measurement) 9     CUYD158.751,428.75290.002,610.00
0019402-01-00101Traffic Maintenance Surfacing (Aggregate) (Vehicular Measurement) 100     CUYD178.5917,859.00200.0020,000.00
0020502-01-00100Asphalt Concrete 1,571.8   TON275.16432,496.49240.00377,232.00
0021502-01-00200Asphalt Concrete, Drives, Turnouts and Miscellaneous 278.2   TON195.4654,376.97300.0083,460.00
0022510-01-00001Pavement Patching (14.5 inch minimum thickness)368     SQYD233.7286,008.96210.0077,280.00
0023511-01-00100Saw Cutting Asphalt Concrete Pavement 1,227     INLF6.848,392.683.003,681.00
0024511-03-00100Sawing and Sealing Transverse Joints in Asphalt Concrete Overlay 864     LNFT20.1617,418.248.006,912.00
0025511-04-00100Sawcuts in Asphalt Concrete Lifts 1,440     LNFT12.1017,424.002.002,880.00
0026701-05-02045Side Drain Pipe (Erosion) (18" RPVCP/CPEPDW/CPPPDW) 140     LNFT122.5317,154.2080.0011,200.00
0027701-05-02087Side Drain Pipe (Erosion) (30" RPVCP/CPEPDW/CPPPDW/CPPPTW) 94     LNFT174.8616,436.84180.0016,920.00
0028701-17-00100Trench Excavation Safety Protection (Depth >5 feet) 140     LNFT5.95833.0015.002,100.00
0029702-08-00100Side Drain Safety End (Type 1) 1     EACH3,734.653,734.654,500.004,500.00
0030704-03-00200Blocked Out Guard Rail - 31", (6'-3" Post Spacing) 1,150     LNFT39.2945,183.5029.0033,350.00
0031704-07-00200Guard Rail Transitions (Double Thrie Beam) 400     LNFT154.7861,912.00115.0046,000.00
0032704-10-00205Guard Rail End Treatment, MASH, (TL-3 Tangent) 16     EACH4,762.4376,198.883,300.0052,800.00
0033708-01-00100Right-of-Way Monument 48     EACH714.3634,289.28600.0028,800.00
0034708-02-00100Right-of-Way Monument Witness Post 48     EACH238.1211,429.76200.009,600.00
0035711-03-00400Riprap (55 lb) 2,187.2   TON95.58209,052.5885.00185,912.00
0036711-03-00500Riprap (130 lb) 4,351.5   TON100.50437,325.75100.00435,150.00
0037711-04-00100Geotextile Fabric 5,979     SQYD2.1312,735.273.0017,937.00
0038713-01-00100Temporary Signs and Barricades 1     LUMP100,230.93100,230.93240,000.00240,000.00
0039713-04-01020Temporary Pavement Markings (Solid Line) (4"Width) (Type 1 Removable) 2.04  MILE10,655.9421,738.129,000.0018,360.00
0040713-06-00100Temporary Reflectorized Raised Pavement Markers 69     EACH5.95410.555.00345.00
0041720-01-01000Erosion Control System (Slope Protection) (Type A) 161     SQYD2.38383.182.00322.00
0042720-01-02020Erosion Control System, Flexible (Channel Liner) (Type D) 78     SQYD2.38185.642.00156.00
0043720-01-02060Erosion Control System, Flexible (Channel Liner) (Type F) 108     SQYD2.38257.042.00216.00
0044724-01-00100Rumble Strips (Centerline) 0.347 MILE360.26125.01500.00173.50
0045724-02-00100Rumble Strips (Shoulder/Edge) 0.694 MILE360.27250.03500.00347.00
0046727-01-00100Mobilization 1     LUMP263,315.46263,315.461,180,000.001,180,000.00
0047729-16-00300Object Marker Assembly (Type 3) 16     EACH160.732,571.6890.001,440.00
0048731-01-00100Nonreflectorized Raised Pavement Markers 2,214     EACH10.7223,734.089.0019,926.00
0049731-02-00100Reflectorized Raised Pavement Markers 69     EACH5.95410.555.00345.00
0050732-02-02000Plastic Pavement Striping (Solid Line) (4" Width) (Thermoplastic 90 mil) 1.064 MILE9,578.5710,191.608,000.008,512.00
0051732-03-02000Plastic Pavement Striping (Broken Line) (4" Width) (Thermoplastic 90 mil) 0.51  MILE4,167.122,125.233,500.001,785.00
0052739-01-00100Hydro-Seeding 4.54  ACRE3,333.7015,135.002,800.0012,712.00
0053740-01-00100Construction Layout 1     LUMP68,117.1368,117.13250,000.00250,000.00
0054804-01-00400Precast Concrete Piles (18") 12,020     LNFT78.58944,531.60145.001,742,900.00
0055804-17-00100Construction Site Survey 1     LUMP11,667.9611,667.9610,000.0010,000.00
0056804-18-00100Vibration Monitoring 6     DAY2,024.0312,144.181,500.009,000.00
0057805-01-00100Class A1 Concrete (Slab Span) 1,250.2   CUYD1,845.752,307,556.651,250.001,562,750.00
0058805-01-00300Class A1 Concrete (Bent Cap) 361.26  CUYD2,662.97962,024.542,500.00903,150.00
0059805-18-00100Concrete Finish (Class 2 Rubbed Finish) 9,408     SQFT7.4570,089.602.5023,520.00
0060805-18-00200Concrete Finish (Class 3 Special Finish) 9,408     SQFT7.4570,089.603.0028,224.00
0061806-01-00100Deformed Reinforcing Steel 423,166     LB1.31554,347.461.45613,590.70
0062810-01-00120Concrete Bridge Railing (36 inch Height) 1,400     LNFT267.20374,080.00240.00336,000.00
0063813-01-00100Concrete Approach Slabs (Cast-in-Place) 5,760     SQFT109.67631,699.20135.00777,600.00
0064814-01-00100Elastomeric Bearing Pads (Non-Reinforced) 980     SFIN91.1289,297.60110.00107,800.00
0065815-03-00300Joint Seal (Poured) 1,404     LNFT12.4117,423.6417.0023,868.00
         
  CONTRACTOR TOTAL   11,464,093.05 11,786,413.45