Proposal:H.015842.6
Parish:Tangipahoa
Routes:LA 22, US 51X
Description:US 51X: N. 7TH ST. - I-55 COA
Type Construction:GRADING, DRAINAGE STRUCTURES, MILLING ASPHALT CONCRETE, PAVEMENT PATCHING, ASPHALT CONCRETE OVERLAY, LOOP DETECTORS, AND RELATED WORK.
Estimated Construction Cost:$3,058,930.15
| Rank | License | Bidder | Construction Bid |
| 1 | 06276 | Barriere Construction Co., LLC | $2,190,199.24 |
| 2 | 73475 | Madden Gulf Coast, LLC | $2,802,615.15 |
| 3 | 02179 | Boh Bros. Construction Co., LLC. | $4,011,429.10 |
Line Number | Item Number | Item Description | Quantity | Unit of Measure | - 1 - Barriere Construction Co., LLC | - 2 - Madden Gulf Coast, LLC | - 3 - Boh Bros. Construction Co., LLC. | | Unit Price | Total Amount | Unit Price | Total Amount | Unit Price | Total Amount | | 0001 | 202-02-03030 | Removal of Pavement Structure | 588 | SQYD | 54.00 | 31,752.00 | 25.00 | 14,700.00 | 40.00 | 23,520.00 | | 0002 | 202-02-06080 | Removal of Concrete Combination Curb and Gutter | 1,504 | LNFT | 16.25 | 24,440.00 | 20.00 | 30,080.00 | 10.00 | 15,040.00 | | 0003 | 202-02-06120 | Removal of Curbs (Asphalt) | 96 | LNFT | 32.50 | 3,120.00 | 60.07 | 5,766.72 | 75.00 | 7,200.00 | | 0004 | 203-03-00100 | Embankment | 200 | CUYD | 48.50 | 9,700.00 | 60.00 | 12,000.00 | 65.00 | 13,000.00 | | 0005 | 203-07-00100 | Borrow (Vehicular Measurement) | 200 | CUYD | 71.00 | 14,200.00 | 60.00 | 12,000.00 | 65.00 | 13,000.00 | | 0006 | 204-02-00100 | Temporary Hay Bales | 8 | EACH | 50.00 | 400.00 | 49.50 | 396.00 | 75.00 | 600.00 | | 0007 | 204-06-00100 | Temporary Silt Fencing | 12,688 | LNFT | 1.00 | 12,688.00 | 2.00 | 25,376.00 | 2.00 | 25,376.00 | | 0008 | 502-01-00100 | Asphalt Concrete | 5,247.8 | TON | 157.00 | 823,904.60 | 145.00 | 760,931.00 | 180.00 | 944,604.00 | | 0009 | 502-01-00200 | Asphalt Concrete, Drives, Turnouts and Miscellaneous | 1,524.1 | TON | 50.00 | 76,205.00 | 230.00 | 350,543.00 | 325.00 | 495,332.50 | | 0010 | 509-01-00100 | Milling Asphalt Pavement | 67,573 | SQYD | 2.30 | 155,417.90 | 3.75 | 253,398.75 | 6.50 | 439,224.50 | | 0011 | 509-02-00100 | Contractor Retained Reclaimed Asphalt Pavement | -2,818 | CUYD | 0.01 | -28.18 | 0.01 | -28.18 | 0.10 | -281.80 | | 0012 | 510-01-00260 | Pavement Patching (16 inch Minimum Thickness) | 1,196 | SQYD | 165.00 | 197,340.00 | 195.00 | 233,220.00 | 350.00 | 418,600.00 | | 0013 | 511-01-00100 | Saw Cutting Asphalt Concrete Pavement | 3,796 | INLF | 2.15 | 8,161.40 | 2.75 | 10,439.00 | 1.25 | 4,745.00 | | 0014 | 511-04-00100 | Sawcuts in Asphalt Concrete Lifts | 12,293 | LNFT | 0.10 | 1,229.30 | 1.00 | 12,293.00 | 1.50 | 18,439.50 | | 0015 | 602-02-00200 | Cleaning and Resealing Existing Longitudinal Pavement Joints | 5,352 | LNFT | 3.25 | 17,394.00 | 3.50 | 18,732.00 | 4.50 | 24,084.00 | | 0016 | 602-02-00300 | Cleaning and Resealing Existing Transverse Pavements Joints | 2,685 | LNFT | 3.25 | 8,726.25 | 3.50 | 9,397.50 | 4.50 | 12,082.50 | | 0017 | 602-10-00100 | Longitudinal Shoulder Joints | 158 | LNFT | 14.00 | 2,212.00 | 20.00 | 3,160.00 | 35.00 | 5,530.00 | | 0018 | 701-04-01020 | Storm Drain Pipe Arch (18" Equiv. RCPA) | 10 | LNFT | 600.00 | 6,000.00 | 160.00 | 1,600.00 | 300.00 | 3,000.00 | | 0019 | 701-15-00100 | Concrete Collar | 1 | EACH | 4,350.00 | 4,350.00 | 3,200.00 | 3,200.00 | 3,500.00 | 3,500.00 | | 0020 | 702-03-00500 | Catch Basins (CB-06) | 1 | EACH | 11,000.00 | 11,000.00 | 12,325.00 | 12,325.00 | 15,000.00 | 15,000.00 | | 0021 | 706-03-00300 | Incidental Concrete Paving (6" Thick) | 336.1 | SQYD | 108.00 | 36,298.80 | 115.00 | 38,651.50 | 165.00 | 55,456.50 | | 0022 | 707-01-00100 | Concrete Curb | 2,063.2 | LNFT | 43.00 | 88,717.60 | 21.00 | 43,327.20 | 55.00 | 113,476.00 | | 0023 | 707-03-00100 | Combination Concrete Curb and Gutter | 293.9 | LNFT | 75.50 | 22,189.45 | 57.00 | 16,752.30 | 65.00 | 19,103.50 | | 0024 | 713-01-00100 | Temporary Signs and Barricades | 1 | LUMP | 210,000.00 | 210,000.00 | 432,000.00 | 432,000.00 | 525,000.00 | 525,000.00 | | 0025 | 713-02-00300 | Temporary Pavement Markings (8" Width) | 3,410.4 | LNFT | 0.20 | 682.08 | 0.15 | 511.56 | 0.25 | 852.60 | | 0026 | 713-02-00500 | Temporary Pavement Markings (24" Width) | 2,752 | LNFT | 0.40 | 1,100.80 | 0.35 | 963.20 | 0.50 | 1,376.00 | | 0027 | 713-03-01000 | Temporary Pavement Markings (Broken Line) (4" Width) (4' Length) | 6.008 | MILE | 345.00 | 2,072.76 | 400.00 | 2,403.20 | 550.00 | 3,304.40 | | 0028 | 713-03-02000 | Temporary Pavement Markings (Broken Line) (4" Width) (10' Length) | 11.498 | MILE | 650.00 | 7,473.70 | 600.00 | 6,898.80 | 800.00 | 9,198.40 | | 0029 | 713-04-01000 | Temporary Pavement Markings (Solid Line) (4" Width) | 17.27 | MILE | 863.00 | 14,904.01 | 800.00 | 13,816.00 | 1,000.00 | 17,270.00 | | 0030 | 713-05-00220 | Temporary Pavement Legends & Symbols (Arrow - Left Turn) | 104 | EACH | 16.20 | 1,684.80 | 15.00 | 1,560.00 | 25.00 | 2,600.00 | | 0031 | 713-05-00230 | Temporary Pavement Legends & Symbols (Arrow - Right Turn) | 8 | EACH | 16.20 | 129.60 | 15.00 | 120.00 | 25.00 | 200.00 | | 0032 | 713-11-00100 | Portable Changeable Message Signs | 5 | EACH | 8,650.00 | 43,250.00 | 3,500.00 | 17,500.00 | 8,000.00 | 40,000.00 | | 0033 | 726-01-00100 | Bedding Material | 5 | CUYD | 189.00 | 945.00 | 195.00 | 975.00 | 250.00 | 1,250.00 | | 0034 | 727-01-00100 | Mobilization | 1 | LUMP | 177,000.00 | 177,000.00 | 280,000.00 | 280,000.00 | 400,000.00 | 400,000.00 | | 0035 | 731-02-00100 | Reflectorized Raised Pavement Markers | 1,066 | EACH | 5.40 | 5,756.40 | 5.00 | 5,330.00 | 8.00 | 8,528.00 | | 0036 | 732-01-02080 | Plastic Pavement Striping (24" Width) (Thermoplastic 125 mil) | 1,376 | LNFT | 15.00 | 20,640.00 | 14.00 | 19,264.00 | 22.00 | 30,272.00 | | 0037 | 732-01-05000 | Plastic Pavement Striping (Dotted Line)(4" W)(2' L)(Thermo 125 mil) | 1,077 | LNFT | 1.60 | 1,723.20 | 1.50 | 1,615.50 | 2.00 | 2,154.00 | | 0038 | 732-01-05200 | Plastic Pavement Striping (Dotted Line)(8" W)(2' L)(Thermo 125 mil) | 1,955 | LNFT | 2.70 | 5,278.50 | 2.50 | 4,887.50 | 3.50 | 6,842.50 | | 0039 | 732-02-02000 | Plastic Pavement Striping (Solid Line) (4" Width) (Thermoplastic 90 mil) | 9.32 | MILE | 4,650.00 | 43,338.00 | 4,300.00 | 40,076.00 | 6,250.00 | 58,250.00 | | 0040 | 732-02-02040 | Plastic Pavement Striping (Solid Line) (8" Width) (Thermoplastic 90 mil) | 0.16 | MILE | 16,200.00 | 2,592.00 | 15,000.00 | 2,400.00 | 20,000.00 | 3,200.00 | | 0041 | 732-03-02000 | Plastic Pavement Striping (Broken Line) (4" Width) (Thermoplastic 90 mil) | 5.744 | MILE | 1,500.00 | 8,616.00 | 1,400.00 | 8,041.60 | 2,250.00 | 12,924.00 | | 0042 | 732-04-01080 | Plastic Pavement Legends and Symbols (Arrow - Left Turn) | 60 | EACH | 350.00 | 21,000.00 | 325.00 | 19,500.00 | 500.00 | 30,000.00 | | 0043 | 732-04-01100 | Plastic Pavement Legends and Symbols (Arrow - Right Turn) | 9 | EACH | 350.00 | 3,150.00 | 325.00 | 2,925.00 | 500.00 | 4,500.00 | | 0044 | 732-04-15020 | Plastic Pavement Legends and Symbols (ONLY) | 6 | EACH | 485.00 | 2,910.00 | 450.00 | 2,700.00 | 500.00 | 3,000.00 | | 0045 | 732-04-16000 | Plastic Pavement Legends and Symbols (Pedestrian Crossing) | 6 | EACH | 323.00 | 1,938.00 | 300.00 | 1,800.00 | 500.00 | 3,000.00 | | 0046 | 736-01-00100 | Trenching and Backfilling | 50 | LNFT | 14.00 | 700.00 | 13.00 | 650.00 | 20.00 | 1,000.00 | | 0047 | 736-09-00100 | Loop Detector | 1,350 | LNFT | 27.70 | 37,395.00 | 25.66 | 34,641.00 | 45.00 | 60,750.00 | | 0048 | 736-10-00200 | Underground Junction Box (Type E) | 2 | EACH | 1,250.00 | 2,500.00 | 1,130.00 | 2,260.00 | 2,500.00 | 5,000.00 | | 0049 | 736-11-00050 | Conduit (1/2" HDPE, Schedule 80) | 50 | LNFT | 13.00 | 650.00 | 12.00 | 600.00 | 25.00 | 1,250.00 | | 0050 | 737-05-00002 | Painted Curbs | 749 | LNFT | 2.16 | 1,617.84 | 2.00 | 1,498.00 | 5.00 | 3,745.00 | | 0051 | 737-06-00002 | Painted Islands | 333 | SQYD | 9.71 | 3,233.43 | 6.00 | 1,998.00 | 10.00 | 3,330.00 | | 0052 | 739-01-00100 | Hydro-Seeding | 0.1 | ACRE | 25,000.00 | 2,500.00 | 24,200.00 | 2,420.00 | 30,000.00 | 3,000.00 | | 0053 | 740-01-00100 | Construction Layout | 1 | LUMP | 10,000.00 | 10,000.00 | 25,000.00 | 25,000.00 | 100,000.00 | 100,000.00 | | | | | | | | | | | | | | | | CONTRACTOR TOTAL | | | | 2,190,199.24 | | 2,802,615.15 | | 4,011,429.10 |
|