Proposal:H.015825.6
Parish:Ouachita
Routes:LA 34
Description:LA 34: 0.3 MI S LA 617 - US 80
Type Construction:CLEARING AND GRUBBING, MILLING ASPHALT CONCRETE, ASPHALT AND CONCRETE PAVEMENT PATCHING, ASPHALT CONCRETE OVERLAY, LOOP DETECTORS, AND RELATED WORK.
Estimated Construction Cost:$7,270,117.11
| Rank | License | Bidder | Construction Bid |
| 1 | 30774 | Progressive Construction Co., LLC | $6,784,505.26 |
Line Number | Item Number | Item Description | Quantity | Unit of Measure | - 1 - Progressive Construction Co., LLC | | Unit Price | Total Amount | | 0001 | 201-01-00200 | Clearing and Grubbing (Selective) | 0.528 | LUMP | 80,000.00 | 80,000.00 | | 0002 | 202-02-02020 | Removal of Asphalt Pavement | 401.9 | SQYD | 25.50 | 10,248.45 | | 0003 | 202-02-06100 | Removal of Concrete Walks and Drives | 6 | SQYD | 160.00 | 960.00 | | 0004 | 202-02-06140 | Removal of Curbs (Concrete) | 5,915 | LNFT | 10.00 | 59,150.00 | | 0005 | 202-02-14500 | Removal of Guard Rail | 337.7 | LNFT | 8.75 | 2,954.88 | | 0006 | 202-02-40120 | Removal of Traffic Detectors and Associated Equipment | 1 | LUMP | 6,875.00 | 6,875.00 | | 0007 | 203-07-00100 | Borrow (Vehicular Measurement) | 10 | CUYD | 121.50 | 1,215.00 | | 0008 | 502-01-00100 | Asphalt Concrete | 2,274.4 | TON | 249.00 | 566,325.60 | | 0009 | 502-01-00200 | Asphalt Concrete, Drives, Turnouts and Miscellaneous | 167.2 | TON | 444.00 | 74,236.80 | | 0010 | 509-01-00100 | Milling Asphalt Pavement | 21,193 | SQYD | 10.25 | 217,228.25 | | 0011 | 509-02-00100 | Contractor Retained Reclaimed Asphalt Pavement | -883 | CUYD | 1.00 | -883.00 | | 0012 | 510-01-00250 | Pavement Patching (14 inch Minimum Thickness) | 1,227 | SQYD | 261.00 | 320,247.00 | | 0013 | 511-02-00100 | Sawing and Sealing Longitudinal Joints in Asphalt Concrete Overlay | 8,846 | LNFT | 3.00 | 26,538.00 | | 0014 | 511-03-00100 | Sawing and Sealing Transverse Joints in Asphalt Concrete Overlay | 6,668 | LNFT | 3.00 | 20,004.00 | | 0015 | 511-04-00100 | Sawcuts in Asphalt Concrete Lifts | 15,521 | LNFT | 1.40 | 21,729.40 | | 0016 | 602-02-00200 | Cleaning and Resealing Existing Longitudinal Pavement Joints | 46,039 | LNFT | 3.25 | 149,626.75 | | 0017 | 602-02-00300 | Cleaning and Resealing Existing Transverse Pavements Joints | 31,670 | LNFT | 3.40 | 107,678.00 | | 0018 | 602-10-00100 | Longitudinal Shoulder Joints | 7,043 | LNFT | 3.15 | 22,185.45 | | 0019 | 602-16-00101 | High Early Strength (HES) Concrete Pavement Full Depth Patching | 14,275.5 | SQYD | 240.50 | 3,433,257.75 | | 0020 | 702-03-00001 | Catch Basin (Remove and Replace Frame and Cover) | 4 | EACH | 6,800.00 | 27,200.00 | | 0021 | 702-04-00100 | Adjusting Manholes | 18 | EACH | 2,635.00 | 47,430.00 | | 0022 | 702-04-00200 | Adjusting Catch Basins | 22 | EACH | 6,800.00 | 149,600.00 | | 0023 | 702-09-00100 | Cleaning Existing Catch Basin | 2 | EACH | 1,000.00 | 2,000.00 | | 0024 | 704-03-00200 | Blocked Out Guard Rail - 31", (6'-3" Post Spacing) | 187.5 | LNFT | 39.00 | 7,312.50 | | 0025 | 704-06-00200 | Guard Rail Bridge Attachments (Single Thrie Beam) | 32 | LNFT | 94.50 | 3,024.00 | | 0026 | 704-07-00200 | Guard Rail Transitions (Double Thrie Beam) | 50 | LNFT | 150.00 | 7,500.00 | | 0027 | 704-10-00310 | Guard Rail End Treatment, NCHRP 350 - 31" (TL-3 Flared) | 2 | EACH | 4,222.00 | 8,444.00 | | 0028 | 706-04-00110 | Curb Ramps TYPE 2 | 20.8 | SQYD | 280.00 | 5,824.00 | | 0029 | 706-04-00110 | Curb Ramps TYPE 6 | 123.3 | SQYD | 280.00 | 34,524.00 | | 0030 | 706-04-00110 | Curb Ramps TYPE 7 | 345.8 | SQYD | 280.00 | 96,824.00 | | 0031 | 707-01-00100 | Concrete Curb | 5,915 | LNFT | 20.00 | 118,300.00 | | 0032 | 713-01-00100 | Temporary Signs and Barricades | 1 | LUMP | 150,000.00 | 150,000.00 | | 0033 | 713-02-00300 | Temporary Pavement Markings (8" Width) | 3,349 | LNFT | 0.17 | 569.33 | | 0034 | 713-02-00400 | Temporary Pavement Markings (12" Width) | 256 | LNFT | 0.30 | 76.80 | | 0035 | 713-02-00500 | Temporary Pavement Markings (24" Width) | 1,239 | LNFT | 0.50 | 619.50 | | 0036 | 713-03-01000 | Temporary Pavement Markings (Broken Line) (4" Width) (4' Length) | 8.444 | MILE | 333.00 | 2,811.85 | | 0037 | 713-03-02000 | Temporary Pavement Markings (Broken Line) (4" Width) (10' Length) | 7.416 | MILE | 778.00 | 5,769.65 | | 0038 | 713-04-01000 | Temporary Pavement Markings (Solid Line) (4" Width) | 12.211 | MILE | 1,000.00 | 12,211.00 | | 0039 | 713-05-00220 | Temporary Pavement Legends & Symbols (Arrow - Left Turn) | 32 | EACH | 27.75 | 888.00 | | 0040 | 713-05-00230 | Temporary Pavement Legends & Symbols (Arrow - Right Turn) | 4 | EACH | 27.75 | 111.00 | | 0041 | 713-05-00300 | Temporary Pavement Legends & Symbols (ONLY) | 6 | EACH | 27.75 | 166.50 | | 0042 | 713-05-00400 | Temporary Pavement Legends & Symbols (RR Crossing) | 10 | EACH | 50.00 | 500.00 | | 0043 | 714-01-00100 | Slab Sodding (Bermuda Grass) | 10 | SQYD | 54.50 | 545.00 | | 0044 | 716-01-00100 | Mulch (Vegetative) | 0.4 | TON | 8,060.00 | 3,224.00 | | 0045 | 717-01-00100 | Seeding | 18 | LB | 13.00 | 234.00 | | 0046 | 718-01-00100 | Fertilizer | 282 | LB | 1.50 | 423.00 | | 0047 | 727-01-00100 | Mobilization | 1 | LUMP | 690,000.00 | 690,000.00 | | 0048 | 729-16-00300 | Object Marker Assembly (Type 3) | 2 | EACH | 155.00 | 310.00 | | 0049 | 731-02-00100 | Reflectorized Raised Pavement Markers | 3,030 | EACH | 5.50 | 16,665.00 | | 0050 | 732-01-01040 | Plastic Pavement Striping (8" Width) (Thermoplastic 90 mil) | 3,349 | LNFT | 4.40 | 14,735.60 | | 0051 | 732-01-01060 | Plastic Pavement Striping (12" Width) (Thermoplastic 90 mil) | 256 | LNFT | 8.80 | 2,252.80 | | 0052 | 732-01-01080 | Plastic Pavement Striping (24" Width) (Thermoplastic 90 mil) | 392 | LNFT | 15.40 | 6,036.80 | | 0053 | 732-01-02080 | Plastic Pavement Striping (24" Width) (Thermoplastic 125 mil) | 717 | LNFT | 15.40 | 11,041.80 | | 0054 | 732-02-02000 | Plastic Pavement Striping (Solid Line) (4" Width) (Thermoplastic 90 mil) | 8.757 | MILE | 4,950.00 | 43,347.15 | | 0055 | 732-02-02020 | Plastic Pavement Striping (Solid Line) (6" Width) (Thermoplastic 90 mil) | 1.143 | MILE | 6,050.00 | 6,915.15 | | 0056 | 732-03-02000 | Plastic Pavement Striping (Broken Line) (4" Width) (Thermoplastic 90 mil) | 1.694 | MILE | 1,650.00 | 2,795.10 | | 0057 | 732-03-02010 | Plastic Pavement Striping (Dotted Line)(4" W)(2' L)(Thermo 90 mil) | 0.009 | MILE | 11,000.00 | 99.00 | | 0058 | 732-03-02020 | Plastic Pavement Striping (Broken Line) (6" Width) (Thermoplastic 90 mil) | 0.404 | MILE | 2,750.00 | 1,111.00 | | 0059 | 732-03-02030 | Plastic Pavement Striping (Dotted Line)(8" W)(2' L)(Thermo 90 mil) | 0.087 | MILE | 11,000.00 | 957.00 | | 0060 | 732-03-04001 | Plastic Pav't Striping (Broken) (7" Width) (Preformed Tape) (Retroreflectivity Level I) (Black and White Contrast) | 3.556 | MILE | 12,100.00 | 43,027.60 | | 0061 | 732-03-04021 | Plastic Pav't Striping (Broken) (9" Width) (Pref Tape) (Retroreflectivity Level I) (Black and White Contrast) | 0.606 | MILE | 14,300.00 | 8,665.80 | | 0062 | 732-04-01080 | Plastic Pavement Legends and Symbols (Arrow - Left Turn) | 32 | EACH | 440.00 | 14,080.00 | | 0063 | 732-04-01100 | Plastic Pavement Legends and Symbols (Arrow - Right Turn) | 4 | EACH | 440.00 | 1,760.00 | | 0064 | 732-04-15020 | Plastic Pavement Legends and Symbols (ONLY) | 6 | EACH | 715.00 | 4,290.00 | | 0065 | 732-04-18000 | Plastic Pavement Legends and Symbols (RR Crossing) | 6 | EACH | 1,320.00 | 7,920.00 | | 0066 | 732-05-00100 | Removal of Existing Markings | 2.566 | MILE | 14,300.00 | 36,693.80 | | 0067 | 735-01-00100 | Mailboxes | 2 | EACH | 1.10 | 2.20 | | 0068 | 735-02-00100 | Mailbox Supports (Single) | 2 | EACH | 825.00 | 1,650.00 | | 0069 | 736-01-00100 | Trenching and Backfilling | 10 | LNFT | 22.00 | 220.00 | | 0070 | 736-09-00100 | Loop Detector | 400 | LNFT | 55.00 | 22,000.00 | | 0071 | 736-11-00050 | Conduit (1/2" HDPE, Schedule 80) | 10 | LNFT | 22.00 | 220.00 | | 0072 | 740-01-00100 | Construction Layout | 1 | LUMP | 32,000.00 | 32,000.00 | | 0073 | 741-35-00100 | Adjust Valve or Meter Box | 4 | EACH | 2,500.00 | 10,000.00 | | | | | | | | | | | | CONTRACTOR TOTAL | | | | 6,784,505.26 |
|