Proposal:H.015549.6
Parish:East Baton Rouge
Description:CHANEY RD AND MILLDALE RD BRIDGES
Type Construction:CLEARING AND GRUBBING, REMOVAL OF CONCRETE BRIDGES, GRADING, DRAINAGE STRUCTURES, CLASS II BASE COURSE, LIME TREATMENT, ASPHALT CONCRETE PAVEMENT, PRECAST CONCRETE PILES, CONCRETE SLAB SPAN BRIDGE, PRECAST REINFORCED CONCRETE BOX CULVERTS, AND RELATED WORK.
Estimated Construction Cost:$3,149,330.30
| Rank | License | Bidder | Construction Bid |
| 1 | 55505 | MERRICK, LLC | $2,013,738.50 |
| 2 | 01516 | Elevate Heavy Civil Construction, LLC | $2,289,000.00 |
| 3 | 56994 | Matt L. Guinn Construction, LLC | $2,409,022.90 |
| 4 | 39462 | JB JAMES CONSTRUCTION LLC | $2,594,032.30 |
| 5 | 00044 | Guinn Construction, LLC | $2,690,337.00 |
| 6 | 00009 | Coastal Contractors, LLC | $2,695,101.60 |
| 7 | 48896 | Command Construction Industries LLC | $2,834,269.50 |
Line Number | Item Number | Item Description | Quantity | Unit of Measure | - 1 - MERRICK, LLC | - 2 - Elevate Heavy Civil Construction, LLC | - 3 - Matt L. Guinn Construction, LLC | - 4 - JB JAMES CONSTRUCTION LLC | | Unit Price | Total Amount | Unit Price | Total Amount | Unit Price | Total Amount | Unit Price | Total Amount | | 0001 | 201-01-00100 | Clearing and Grubbing | 0.53 | LUMP | 20,000.00 | 20,000.00 | 75,000.00 | 75,000.00 | 70,000.00 | 70,000.00 | 195,000.00 | 195,000.00 | | 0002 | 202-01-00100 | Removal of Structures and Obstructions | 1 | LUMP | 13,000.00 | 13,000.00 | 10,000.00 | 10,000.00 | 10,000.00 | 10,000.00 | 10,000.00 | 10,000.00 | | 0003 | 202-02-00010 | Removal of Removal of Mailboxes | 4 | EACH | 200.00 | 800.00 | 28.00 | 112.00 | 200.00 | 800.00 | 100.00 | 400.00 | | 0004 | 202-02-03030 | Removal of Pavement Structure | 1,053.3 | SQYD | 10.00 | 10,533.00 | 23.00 | 24,225.90 | 12.00 | 12,639.60 | 20.00 | 21,066.00 | | 0005 | 202-02-04501 | Removal of Bridge Removal of Bridge Str. No. 611730398905921 (27.6' Wide x 57.1' Long) Concrete Bridge | 1,576 | LUMP | 35,000.00 | 35,000.00 | 75,000.00 | 75,000.00 | 30,000.00 | 30,000.00 | 100,000.00 | 100,000.00 | | 0006 | 202-02-04501 | Removal of Bridge Removal of Bridge Str. No. 611730407905901 (31.2' Wide x 57.1' Long) Concrete Bridge | 1,782 | LUMP | 35,000.00 | 35,000.00 | 75,000.00 | 75,000.00 | 35,000.00 | 35,000.00 | 90,000.00 | 90,000.00 | | 0007 | 202-02-32120 | Removal of Pipe (Side Drain) (24" CMP, 18" RCP, 24" RCP) | 149 | LNFT | 25.00 | 3,725.00 | 25.00 | 3,725.00 | 70.00 | 10,430.00 | 25.00 | 3,725.00 | | 0008 | 203-02-00100 | Drainage Excavation | 180 | CUYD | 30.00 | 5,400.00 | 30.00 | 5,400.00 | 35.00 | 6,300.00 | 25.00 | 4,500.00 | | 0009 | 203-05-00100 | Excavation and Embankment | 1 | LUMP | 90,000.00 | 90,000.00 | 110,000.00 | 110,000.00 | 38,000.00 | 38,000.00 | 90,000.00 | 90,000.00 | | 0010 | 204-05-00100 | Temporary Sediment Check Dams (Hay) | 8 | EACH | 200.00 | 1,600.00 | 150.00 | 1,200.00 | 300.00 | 2,400.00 | 150.00 | 1,200.00 | | 0011 | 204-06-00100 | Temporary Silt Fencing | 1,319 | LNFT | 4.00 | 5,276.00 | 3.00 | 3,957.00 | 3.50 | 4,616.50 | 8.50 | 11,211.50 | | 0012 | 302-02-08570 | Class II Base Course (8-1/2" Thick) (Crushed Stone or Recycled Portland Cement Concrete) | 1,430.1 | SQYD | 40.00 | 57,204.00 | 39.00 | 55,773.90 | 48.00 | 68,644.80 | 45.00 | 64,354.50 | | 0013 | 302-03-00100 | Base Drain Outlet | 6 | EACH | 450.00 | 2,700.00 | 1,000.00 | 6,000.00 | 850.00 | 5,100.00 | 1,500.00 | 9,000.00 | | 0014 | 304-01-00100 | Lime | 18.94 | TON | 350.00 | 6,629.00 | 350.00 | 6,629.00 | 700.00 | 13,258.00 | 300.00 | 5,682.00 | | 0015 | 304-05-00100 | Lime Treatment (Type E) | 1,431 | SQYD | 3.00 | 4,293.00 | 6.00 | 8,586.00 | 20.00 | 28,620.00 | 15.00 | 21,465.00 | | 0016 | 401-02-00100 | Aggregate Surface Course (Adjusted Vehicular Measurement) | 211 | CUYD | 140.00 | 29,540.00 | 160.00 | 33,760.00 | 200.00 | 42,200.00 | 150.00 | 31,650.00 | | 0017 | 402-01-00101 | Traffic Maintenance Surfacing (Aggregate) (Vehicular Measurement) | 100 | CUYD | 90.00 | 9,000.00 | 179.00 | 17,900.00 | 175.00 | 17,500.00 | 170.00 | 17,000.00 | | 0018 | 502-01-00100 | Asphalt Concrete | 295.6 | TON | 210.00 | 62,076.00 | 180.00 | 53,208.00 | 485.00 | 143,366.00 | 200.00 | 59,120.00 | | 0019 | 502-01-00200 | Asphalt Concrete, Drives, Turnouts and Miscellaneous | 32.1 | TON | 390.00 | 12,519.00 | 165.00 | 5,296.50 | 600.00 | 19,260.00 | 375.00 | 12,037.50 | | 0020 | 511-01-00100 | Saw Cutting Asphalt Concrete Pavement | 248 | INLF | 15.00 | 3,720.00 | 3.00 | 744.00 | 20.00 | 4,960.00 | 4.00 | 992.00 | | 0021 | 701-05-01066 | Side Drain Pipe (24" RCP) | 462 | LNFT | 120.00 | 55,440.00 | 105.00 | 48,510.00 | 90.00 | 41,580.00 | 120.00 | 55,440.00 | | 0022 | 701-05-01087 | Side Drain Pipe (30" RCP/RPVCP) | 128 | LNFT | 145.00 | 18,560.00 | 138.00 | 17,664.00 | 125.00 | 16,000.00 | 150.00 | 19,200.00 | | 0023 | 701-05-01102 | Side Drain Pipe (36" RCP/RPVCP/CMP) | 131 | LNFT | 165.00 | 21,615.00 | 225.00 | 29,475.00 | 175.00 | 22,925.00 | 200.00 | 26,200.00 | | 0024 | 702-03-00100 | Catch Basins (CB-01) | 1 | EACH | 8,000.00 | 8,000.00 | 5,400.00 | 5,400.00 | 10,000.00 | 10,000.00 | 8,000.00 | 8,000.00 | | 0025 | 702-08-00100 | Side Drain Safety End (Type 1) | 6 | EACH | 5,000.00 | 30,000.00 | 5,700.00 | 34,200.00 | 4,000.00 | 24,000.00 | 3,600.00 | 21,600.00 | | 0026 | 702-08-00200 | Side Drain Safety End (Type 2) | 2 | EACH | 10,000.00 | 20,000.00 | 7,600.00 | 15,200.00 | 4,000.00 | 8,000.00 | 10,000.00 | 20,000.00 | | 0027 | 704-03-00200 | Blocked Out Guard Rail - 31", (6'-3" Post Spacing) | 12.5 | LNFT | 25.00 | 312.50 | 30.00 | 375.00 | 60.00 | 750.00 | 20.00 | 250.00 | | 0028 | 704-07-00200 | Guard Rail Transitions (Double Thrie Beam) | 100 | LNFT | 100.00 | 10,000.00 | 120.00 | 12,000.00 | 145.00 | 14,500.00 | 80.00 | 8,000.00 | | 0029 | 704-10-00204 | Guard Rail End Treatment, MASH, (TL-2 Tangent) | 1 | EACH | 3,500.00 | 3,500.00 | 3,100.00 | 3,100.00 | 4,700.00 | 4,700.00 | 2,250.00 | 2,250.00 | | 0030 | 704-10-00205 | Guard Rail End Treatment, MASH, (TL-3 Tangent) | 3 | EACH | 2,500.00 | 7,500.00 | 3,400.00 | 10,200.00 | 5,000.00 | 15,000.00 | 3,000.00 | 9,000.00 | | 0031 | 711-02-00400 | Riprap (55 lb) | 400 | CUYD | 160.00 | 64,000.00 | 225.00 | 90,000.00 | 205.00 | 82,000.00 | 230.00 | 92,000.00 | | 0032 | 711-04-00100 | Geotextile Fabric | 798 | SQYD | 4.00 | 3,192.00 | 3.00 | 2,394.00 | 6.50 | 5,187.00 | 3.00 | 2,394.00 | | 0033 | 713-01-00100 | Temporary Signs and Barricades | 1 | LUMP | 50,000.00 | 50,000.00 | 24,000.00 | 24,000.00 | 50,000.00 | 50,000.00 | 50,000.00 | 50,000.00 | | 0034 | 726-01-00100 | Bedding Material | 120.9 | CUYD | 180.00 | 21,762.00 | 130.00 | 15,717.00 | 190.00 | 22,971.00 | 150.00 | 18,135.00 | | 0035 | 727-01-00100 | Mobilization | 1 | LUMP | 190,000.00 | 190,000.00 | 231,400.00 | 231,400.00 | 200,000.00 | 200,000.00 | 260,000.00 | 260,000.00 | | 0036 | 729-16-00300 | Object Marker Assembly (Type 3) | 8 | EACH | 300.00 | 2,400.00 | 85.00 | 680.00 | 300.00 | 2,400.00 | 250.00 | 2,000.00 | | 0037 | 731-02-00100 | Reflectorized Raised Pavement Markers | 27 | EACH | 30.00 | 810.00 | 25.00 | 675.00 | 25.00 | 675.00 | 25.00 | 675.00 | | 0038 | 732-02-02000 | Plastic Pavement Striping (Solid Line) (4" Width) (Thermoplastic 90 mil) | 0.402 | MILE | 8,000.00 | 3,216.00 | 7,500.00 | 3,015.00 | 20,000.00 | 8,040.00 | 7,500.00 | 3,015.00 | | 0039 | 735-01-00100 | Mailboxes | 4 | EACH | 125.00 | 500.00 | 25.00 | 100.00 | 500.00 | 2,000.00 | 25.00 | 100.00 | | 0040 | 735-02-00100 | Mailbox Supports (Single) | 4 | EACH | 125.00 | 500.00 | 250.00 | 1,000.00 | 200.00 | 800.00 | 250.00 | 1,000.00 | | 0041 | 739-01-00100 | Hydro-Seeding | 0.53 | ACRE | 6,000.00 | 3,180.00 | 5,500.00 | 2,915.00 | 10,000.00 | 5,300.00 | 5,500.00 | 2,915.00 | | 0042 | 740-01-00100 | Construction Layout | 1 | LUMP | 30,000.00 | 30,000.00 | 18,628.70 | 18,628.70 | 25,000.00 | 25,000.00 | 25,000.00 | 25,000.00 | | 0043 | 804-01-00300 | Precast Concrete Piles (16") | 1,520 | LNFT | 150.00 | 228,000.00 | 170.00 | 258,400.00 | 165.00 | 250,800.00 | 300.00 | 456,000.00 | | 0044 | 805-01-00100 | Class A1 Concrete (Slab Span) | 101.92 | CUYD | 1,700.00 | 173,264.00 | 1,700.00 | 173,264.00 | 1,800.00 | 183,456.00 | 1,500.00 | 152,880.00 | | 0045 | 805-01-00300 | Class A1 Concrete (Bent Cap) | 27.14 | CUYD | 4,000.00 | 108,560.00 | 4,900.00 | 132,986.00 | 3,800.00 | 103,132.00 | 2,700.00 | 73,278.00 | | 0046 | 805-15-01400 | Reinforced Concrete Box Culverts (Precast) (8' x 6') | 204 | LNFT | 1,500.00 | 306,000.00 | 1,550.00 | 316,200.00 | 2,300.00 | 469,200.00 | 1,400.00 | 285,600.00 | | 0047 | 805-17-00100 | Reinforced Concrete Box Culvert Headwall (13.2 CUYD Concrete and 989 LB Reinforcing Steel) | 2 | EACH | 60,000.00 | 120,000.00 | 50,000.00 | 100,000.00 | 50,000.00 | 100,000.00 | 45,000.00 | 90,000.00 | | 0048 | 805-18-00100 | Concrete Finish (Class 2 Rubbed Finish) | 956 | SQFT | 4.00 | 3,824.00 | 2.00 | 1,912.00 | 4.00 | 3,824.00 | 1.50 | 1,434.00 | | 0049 | 805-18-00200 | Concrete Finish (Class 3 Special Finish) | 956 | SQFT | 4.00 | 3,824.00 | 3.00 | 2,868.00 | 4.00 | 3,824.00 | 3.00 | 2,868.00 | | 0050 | 806-01-00100 | Deformed Reinforcing Steel | 27,282 | LB | 2.00 | 54,564.00 | 2.00 | 54,564.00 | 2.00 | 54,564.00 | 1.40 | 38,194.80 | | 0051 | 810-01-00100 | Concrete Bridge Railing (Standard) | 80 | LNFT | 145.00 | 11,600.00 | 320.00 | 25,600.00 | 300.00 | 24,000.00 | 250.00 | 20,000.00 | | 0052 | 810-01-00200 | Concrete Bridge Railing (Slotted) | 80 | LNFT | 175.00 | 14,000.00 | 320.00 | 25,600.00 | 300.00 | 24,000.00 | 250.00 | 20,000.00 | | 0053 | 813-01-00100 | Concrete Approach Slabs (Cast-in-Place) | 580 | SQFT | 60.00 | 34,800.00 | 95.00 | 55,100.00 | 110.00 | 63,800.00 | 130.00 | 75,400.00 | | 0054 | 815-03-00300 | Joint Seal (Poured) | 140 | LNFT | 20.00 | 2,800.00 | 31.00 | 4,340.00 | 25.00 | 3,500.00 | 20.00 | 2,800.00 | | | | | | | | | | | | | | | | | | CONTRACTOR TOTAL | | | | 2,013,738.50 | | 2,289,000.00 | | 2,409,022.90 | | 2,594,032.30 |
Line Number | Item Number | Item Description | Quantity | Unit of Measure | - 5 - Guinn Construction, LLC | - 6 - Coastal Contractors, LLC | - 7 - Command Construction Industries LLC | | Unit Price | Total Amount | Unit Price | Total Amount | Unit Price | Total Amount | | 0001 | 201-01-00100 | Clearing and Grubbing | 0.53 | LUMP | 80,000.00 | 80,000.00 | 125,000.00 | 125,000.00 | 25,000.00 | 25,000.00 | | 0002 | 202-01-00100 | Removal of Structures and Obstructions | 1 | LUMP | 10,000.00 | 10,000.00 | 23,000.00 | 23,000.00 | 25,000.00 | 25,000.00 | | 0003 | 202-02-00010 | Removal of Removal of Mailboxes | 4 | EACH | 100.00 | 400.00 | 100.00 | 400.00 | 50.00 | 200.00 | | 0004 | 202-02-03030 | Removal of Pavement Structure | 1,053.3 | SQYD | 15.00 | 15,799.50 | 23.00 | 24,225.90 | 25.00 | 26,332.50 | | 0005 | 202-02-04501 | Removal of Bridge Removal of Bridge Str. No. 611730398905921 (27.6' Wide x 57.1' Long) Concrete Bridge | 1,576 | LUMP | 40,000.00 | 40,000.00 | 80,000.00 | 80,000.00 | 100,000.00 | 100,000.00 | | 0006 | 202-02-04501 | Removal of Bridge Removal of Bridge Str. No. 611730407905901 (31.2' Wide x 57.1' Long) Concrete Bridge | 1,782 | LUMP | 40,000.00 | 40,000.00 | 80,000.00 | 80,000.00 | 100,000.00 | 100,000.00 | | 0007 | 202-02-32120 | Removal of Pipe (Side Drain) (24" CMP, 18" RCP, 24" RCP) | 149 | LNFT | 10.00 | 1,490.00 | 26.00 | 3,874.00 | 25.00 | 3,725.00 | | 0008 | 203-02-00100 | Drainage Excavation | 180 | CUYD | 30.00 | 5,400.00 | 57.88 | 10,418.40 | 50.00 | 9,000.00 | | 0009 | 203-05-00100 | Excavation and Embankment | 1 | LUMP | 130,000.00 | 130,000.00 | 179,000.00 | 179,000.00 | 100,000.00 | 100,000.00 | | 0010 | 204-05-00100 | Temporary Sediment Check Dams (Hay) | 8 | EACH | 500.00 | 4,000.00 | 182.00 | 1,456.00 | 250.00 | 2,000.00 | | 0011 | 204-06-00100 | Temporary Silt Fencing | 1,319 | LNFT | 3.00 | 3,957.00 | 3.00 | 3,957.00 | 5.00 | 6,595.00 | | 0012 | 302-02-08570 | Class II Base Course (8-1/2" Thick) (Crushed Stone or Recycled Portland Cement Concrete) | 1,430.1 | SQYD | 65.00 | 92,956.50 | 65.00 | 92,956.50 | 45.00 | 64,354.50 | | 0013 | 302-03-00100 | Base Drain Outlet | 6 | EACH | 2,000.00 | 12,000.00 | 1,100.00 | 6,600.00 | 1,000.00 | 6,000.00 | | 0014 | 304-01-00100 | Lime | 18.94 | TON | 750.00 | 14,205.00 | 500.00 | 9,470.00 | 450.00 | 8,523.00 | | 0015 | 304-05-00100 | Lime Treatment (Type E) | 1,431 | SQYD | 25.00 | 35,775.00 | 16.00 | 22,896.00 | 12.00 | 17,172.00 | | 0016 | 401-02-00100 | Aggregate Surface Course (Adjusted Vehicular Measurement) | 211 | CUYD | 250.00 | 52,750.00 | 145.00 | 30,595.00 | 125.00 | 26,375.00 | | 0017 | 402-01-00101 | Traffic Maintenance Surfacing (Aggregate) (Vehicular Measurement) | 100 | CUYD | 100.00 | 10,000.00 | 145.00 | 14,500.00 | 1.00 | 100.00 | | 0018 | 502-01-00100 | Asphalt Concrete | 295.6 | TON | 350.00 | 103,460.00 | 225.00 | 66,510.00 | 250.00 | 73,900.00 | | 0019 | 502-01-00200 | Asphalt Concrete, Drives, Turnouts and Miscellaneous | 32.1 | TON | 425.00 | 13,642.50 | 400.00 | 12,840.00 | 450.00 | 14,445.00 | | 0020 | 511-01-00100 | Saw Cutting Asphalt Concrete Pavement | 248 | INLF | 10.00 | 2,480.00 | 5.00 | 1,240.00 | 3.00 | 744.00 | | 0021 | 701-05-01066 | Side Drain Pipe (24" RCP) | 462 | LNFT | 170.00 | 78,540.00 | 149.00 | 68,838.00 | 230.00 | 106,260.00 | | 0022 | 701-05-01087 | Side Drain Pipe (30" RCP/RPVCP) | 128 | LNFT | 225.00 | 28,800.00 | 182.00 | 23,296.00 | 260.00 | 33,280.00 | | 0023 | 701-05-01102 | Side Drain Pipe (36" RCP/RPVCP/CMP) | 131 | LNFT | 300.00 | 39,300.00 | 201.00 | 26,331.00 | 300.00 | 39,300.00 | | 0024 | 702-03-00100 | Catch Basins (CB-01) | 1 | EACH | 7,500.00 | 7,500.00 | 7,500.00 | 7,500.00 | 10,000.00 | 10,000.00 | | 0025 | 702-08-00100 | Side Drain Safety End (Type 1) | 6 | EACH | 5,500.00 | 33,000.00 | 4,800.00 | 28,800.00 | 6,000.00 | 36,000.00 | | 0026 | 702-08-00200 | Side Drain Safety End (Type 2) | 2 | EACH | 12,000.00 | 24,000.00 | 11,000.00 | 22,000.00 | 10,000.00 | 20,000.00 | | 0027 | 704-03-00200 | Blocked Out Guard Rail - 31", (6'-3" Post Spacing) | 12.5 | LNFT | 50.00 | 625.00 | 22.00 | 275.00 | 25.00 | 312.50 | | 0028 | 704-07-00200 | Guard Rail Transitions (Double Thrie Beam) | 100 | LNFT | 150.00 | 15,000.00 | 88.00 | 8,800.00 | 100.00 | 10,000.00 | | 0029 | 704-10-00204 | Guard Rail End Treatment, MASH, (TL-2 Tangent) | 1 | EACH | 5,500.00 | 5,500.00 | 3,250.00 | 3,250.00 | 2,500.00 | 2,500.00 | | 0030 | 704-10-00205 | Guard Rail End Treatment, MASH, (TL-3 Tangent) | 3 | EACH | 6,500.00 | 19,500.00 | 2,500.00 | 7,500.00 | 3,500.00 | 10,500.00 | | 0031 | 711-02-00400 | Riprap (55 lb) | 400 | CUYD | 155.00 | 62,000.00 | 125.00 | 50,000.00 | 200.00 | 80,000.00 | | 0032 | 711-04-00100 | Geotextile Fabric | 798 | SQYD | 5.00 | 3,990.00 | 6.00 | 4,788.00 | 5.00 | 3,990.00 | | 0033 | 713-01-00100 | Temporary Signs and Barricades | 1 | LUMP | 45,000.00 | 45,000.00 | 59,000.00 | 59,000.00 | 50,000.00 | 50,000.00 | | 0034 | 726-01-00100 | Bedding Material | 120.9 | CUYD | 200.00 | 24,180.00 | 165.00 | 19,948.50 | 100.00 | 12,090.00 | | 0035 | 727-01-00100 | Mobilization | 1 | LUMP | 300,000.00 | 300,000.00 | 260,000.00 | 260,000.00 | 300,000.00 | 300,000.00 | | 0036 | 729-16-00300 | Object Marker Assembly (Type 3) | 8 | EACH | 200.00 | 1,600.00 | 275.00 | 2,200.00 | 300.00 | 2,400.00 | | 0037 | 731-02-00100 | Reflectorized Raised Pavement Markers | 27 | EACH | 50.00 | 1,350.00 | 11.00 | 297.00 | 10.00 | 270.00 | | 0038 | 732-02-02000 | Plastic Pavement Striping (Solid Line) (4" Width) (Thermoplastic 90 mil) | 0.402 | MILE | 25,000.00 | 10,050.00 | 8,000.00 | 3,216.00 | 7,500.00 | 3,015.00 | | 0039 | 735-01-00100 | Mailboxes | 4 | EACH | 150.00 | 600.00 | 105.00 | 420.00 | 100.00 | 400.00 | | 0040 | 735-02-00100 | Mailbox Supports (Single) | 4 | EACH | 250.00 | 1,000.00 | 105.00 | 420.00 | 100.00 | 400.00 | | 0041 | 739-01-00100 | Hydro-Seeding | 0.53 | ACRE | 15,000.00 | 7,950.00 | 4,250.00 | 2,252.50 | 4,000.00 | 2,120.00 | | 0042 | 740-01-00100 | Construction Layout | 1 | LUMP | 40,000.00 | 40,000.00 | 72,000.00 | 72,000.00 | 50,000.00 | 50,000.00 | | 0043 | 804-01-00300 | Precast Concrete Piles (16") | 1,520 | LNFT | 160.00 | 243,200.00 | 170.00 | 258,400.00 | 175.00 | 266,000.00 | | 0044 | 805-01-00100 | Class A1 Concrete (Slab Span) | 101.92 | CUYD | 2,250.00 | 229,320.00 | 2,700.00 | 275,184.00 | 2,500.00 | 254,800.00 | | 0045 | 805-01-00300 | Class A1 Concrete (Bent Cap) | 27.14 | CUYD | 2,850.00 | 77,349.00 | 3,200.00 | 86,848.00 | 4,000.00 | 108,560.00 | | 0046 | 805-15-01400 | Reinforced Concrete Box Culverts (Precast) (8' x 6') | 204 | LNFT | 1,950.00 | 397,800.00 | 1,650.00 | 336,600.00 | 2,250.00 | 459,000.00 | | 0047 | 805-17-00100 | Reinforced Concrete Box Culvert Headwall (13.2 CUYD Concrete and 989 LB Reinforcing Steel) | 2 | EACH | 75,000.00 | 150,000.00 | 60,000.00 | 120,000.00 | 50,000.00 | 100,000.00 | | 0048 | 805-18-00100 | Concrete Finish (Class 2 Rubbed Finish) | 956 | SQFT | 2.00 | 1,912.00 | 4.00 | 3,824.00 | 5.00 | 4,780.00 | | 0049 | 805-18-00200 | Concrete Finish (Class 3 Special Finish) | 956 | SQFT | 2.00 | 1,912.00 | 5.00 | 4,780.00 | 5.00 | 4,780.00 | | 0050 | 806-01-00100 | Deformed Reinforcing Steel | 27,282 | LB | 1.75 | 47,743.50 | 1.40 | 38,194.80 | 3.00 | 81,846.00 | | 0051 | 810-01-00100 | Concrete Bridge Railing (Standard) | 80 | LNFT | 300.00 | 24,000.00 | 225.00 | 18,000.00 | 380.00 | 30,400.00 | | 0052 | 810-01-00200 | Concrete Bridge Railing (Slotted) | 80 | LNFT | 300.00 | 24,000.00 | 225.00 | 18,000.00 | 380.00 | 30,400.00 | | 0053 | 813-01-00100 | Concrete Approach Slabs (Cast-in-Place) | 580 | SQFT | 125.00 | 72,500.00 | 120.00 | 69,600.00 | 180.00 | 104,400.00 | | 0054 | 815-03-00300 | Joint Seal (Poured) | 140 | LNFT | 20.00 | 2,800.00 | 40.00 | 5,600.00 | 50.00 | 7,000.00 | | | | | | | | | | | | | | | | CONTRACTOR TOTAL | | | | 2,690,337.00 | | 2,695,101.60 | | 2,834,269.50 |
|