Proposal:H.016397.6
Parish:St. James
Routes:LA 3125, LA 3274
Description:LA 3125 @ LA 3274 ROUNDABOUT CLEAR&GRUB
Type Construction:CLEARING AND GRUBBING, CHAIN LINK FENCE, AND RELATED WORK.
Estimated Construction Cost:$116,564.00
| Rank | License | Bidder | Construction Bid |
| 1 | 34263 | LA Contracting Enterprise, L.L.C. | $80,000.00 |
| 2 | 67594 | Traffic Commander, LLC | $93,106.00 |
| 3 | 74077 | TLP Construction Co. LLC | $198,701.00 |
Line Number | Item Number | Item Description | Quantity | Unit of Measure | - 1 - LA Contracting Enterprise, L.L.C. | - 2 - Traffic Commander, LLC | - 3 - TLP Construction Co. LLC | | Unit Price | Total Amount | Unit Price | Total Amount | Unit Price | Total Amount | | 0001 | 201-01-00100 | Clearing and Grubbing | 1 | LUMP | 21,033.00 | 21,033.00 | 2,500.00 | 2,500.00 | 91,500.00 | 91,500.00 | | 0002 | 202-01-00100 | Removal of Structures and Obstructions | 1 | LUMP | 4,200.00 | 4,200.00 | 9,500.00 | 9,500.00 | 15,000.00 | 15,000.00 | | 0003 | 202-02-02000 | Removal of Asphalt Drives | 40 | SQYD | 27.00 | 1,080.00 | 100.00 | 4,000.00 | 50.00 | 2,000.00 | | 0004 | 204-02-00100 | Temporary Hay Bales | 17 | EACH | 36.00 | 612.00 | 5.00 | 85.00 | 50.00 | 850.00 | | 0005 | 204-06-00100 | Temporary Silt Fencing | 412 | LNFT | 3.50 | 1,442.00 | 1.00 | 412.00 | 10.00 | 4,120.00 | | 0006 | 401-02-00100 | Aggregate Surface Course (Adjusted Vehicular Measurement) | 5 | CUYD | 583.00 | 2,915.00 | 550.00 | 2,750.00 | 500.00 | 2,500.00 | | 0007 | 502-01-00200 | Asphalt Concrete, Drives, Turnouts and Miscellaneous | 6.7 | TON | 600.00 | 4,020.00 | 2,250.00 | 15,075.00 | 750.00 | 5,025.00 | | 0008 | 705-04-00100 | Single Swinging Driveway Gates | 1 | EACH | 1,900.00 | 1,900.00 | 5,000.00 | 5,000.00 | 3,250.00 | 3,250.00 | | 0009 | 705-06-00400 | Chain Link Fence (7 Foot Height) | 278 | LNFT | 60.00 | 16,680.00 | 38.50 | 10,703.00 | 75.00 | 20,850.00 | | 0010 | 713-01-00100 | Temporary Signs and Barricades | 1 | LUMP | 12,000.00 | 12,000.00 | 15,000.00 | 15,000.00 | 15,000.00 | 15,000.00 | | 0011 | 727-01-00100 | Mobilization | 1 | LUMP | 7,500.00 | 7,500.00 | 12,500.00 | 12,500.00 | 20,000.00 | 20,000.00 | | 0012 | 739-01-00100 | Hydro-Seeding | 0.55 | ACRE | 4,000.00 | 2,200.00 | 500.00 | 275.00 | 6,000.00 | 3,300.00 | | 0013 | 740-01-00100 | Construction Layout | 1 | LUMP | 3,500.00 | 3,500.00 | 15,000.00 | 15,000.00 | 15,000.00 | 15,000.00 | | 0014 | NS-500-00340 | Saw Cutting Asphalt Concrete Pavement | 306 | INLF | 3.00 | 918.00 | 1.00 | 306.00 | 1.00 | 306.00 | | | | | | | | | | | | | | | | CONTRACTOR TOTAL | | | | 80,000.00 | | 93,106.00 | | 198,701.00 |
|