Search


Bid Tabulations for the Letting of 12/10/2025 LA DOTD Headquarters

Proposal:H.014411.6
Parish:Caddo
Description:LINWOOD AVENUE RECONSTRUCTION PHASE IV - A
Type Construction:DRAINAGE STRUCTURES, SUBGRADE TREATMENT, CLASS II BASE COURSE, ASPHALT CONCRETE OVERLAY, PORTLAND CEMENT CONCRETE PAVEMENT, SIDEWALKS; ADDITIVE ALTERNATE 1 - DRAINAGE STRUCTURES, SUBGRADE TREATMENT, CLASS II BASE COURSE, ASPHALT CONCRETE OVERLAY, PORTLAND CEMENT CONCRETE PAVEMENT, SIDEWALKS, AND RELATED WORK.
Estimated Construction Cost:$6,852,071.69
Rank License BidderConstruction Bid
130774Progressive Construction Co., LLC$6,424,288.57
239462JB JAMES CONSTRUCTION LLC$7,878,202.50
352306SIEMA CONSTRUCTION, LLC$8,547,627.00


Line
Number
Item NumberItem DescriptionQuantityUnit of
Measure
- 1 -
Progressive Construction Co., LLC
- 2 -
JB JAMES CONSTRUCTION LLC
- 3 -
SIEMA CONSTRUCTION, LLC
Unit PriceTotal
Amount
Unit PriceTotal
Amount
Unit PriceTotal
Amount
0001201-01-00100Clearing and Grubbing 0.9   LUMP30,000.0030,000.00250,000.00250,000.00200,000.00200,000.00
0002202-02-03030Removal of Pavement Structure 20,596.4   SQYD12.50257,455.0030.00617,892.0020.00411,928.00
0003202-02-06100Removal of Concrete Walks and Drives 3,748     SQYD15.0056,220.0020.0074,960.0018.7570,275.00
0004202-02-32140Removal of Pipe (Storm Drain) 15" RCP20     LNFT65.001,300.00340.006,800.0045.00900.00
0005203-05-00100Excavation and Embankment 1     LUMP90,000.0090,000.00227,000.00227,000.00102,000.00102,000.00
0006204-02-00100Temporary Hay Bales 152     EACH35.005,320.0035.005,320.0040.006,080.00
0007204-06-00100Temporary Silt Fencing 12,478     LNFT4.0049,912.003.0037,434.002.2528,075.50
0008302-02-08000Class II Base Course (8" Thick) 21,493     SQYD32.00687,776.0042.00902,706.0039.50848,973.50
0009305-01-04020Subgrade Layer (12" Thick) (Treated) 21,494     SQYD20.00429,880.0023.00494,362.0014.00300,916.00
0010402-01-00101Traffic Maintenance Surfacing (Aggregate) (Vehicular Measurement) 700     CUYD150.00105,000.00175.00122,500.00155.00108,500.00
0011402-02-00101Traffic Maintenance Surfacing (Hard) 100     SQYD125.0012,500.0090.009,000.00210.0021,000.00
0012502-01-00100Asphalt Concrete 114.3   TON575.0065,722.50425.0048,577.50450.0051,435.00
0013601-01-00100Portland Cement Concrete Pavement (8" Thick) 20,339.7   SQYD99.002,013,630.3095.001,932,271.50140.002,847,558.00
0014701-03-01002Storm Drain Pipe (15" RCP/RPVCP) 20     LNFT177.003,540.00450.009,000.00135.002,700.00
0015701-15-00100Concrete Collar 2     EACH2,000.004,000.002,000.004,000.001,125.002,250.00
0016702-04-00200Adjusting Catch Basins 15     EACH5,000.0075,000.005,000.0075,000.005,500.0082,500.00
0017703-01-00100Shoulder Underdrain Systems 6,239     LNFT18.00112,302.0020.00124,780.0031.00193,409.00
0018706-01-00100Concrete Walk (4" Thick) 2,497     SQYD90.00224,730.0074.00184,778.00111.00277,167.00
0019706-02-00200Concrete Drive (6" Thick) 1,359.8   SQYD100.00135,980.0090.00122,382.00125.00169,975.00
0020706-04-00110Curb Ramps Type 450.2   SQYD200.0010,040.00380.0019,076.00475.0023,845.00
0021706-04-00110Curb Ramps Type 679.1   SQYD200.0015,820.00360.0028,476.00475.0037,572.50
0022706-04-00110Curb Ramps Type 723.1   SQYD200.004,620.00230.005,313.00335.007,738.50
0023707-01-00100Concrete Curb 6,435.3   LNFT12.0077,223.606.0038,611.8014.0090,094.20
0024713-01-00100Temporary Signs and Barricades 1     LUMP130,000.00130,000.00175,000.00175,000.00255,000.00255,000.00
0025713-04-01020Temporary Pavement Markings (Solid Line) (4"Width) (Type 1 Removable) 2.73  MILE10,450.0028,528.509,500.0025,935.0011,250.0030,712.50
0026726-01-00100Bedding Material 1.8   CUYD170.00306.00800.001,440.00113.00203.40
0027727-01-00100Mobilization 1     LUMP550,000.00550,000.00640,000.00640,000.00700,000.00700,000.00
0028731-02-00100Reflectorized Raised Pavement Markers 1,133     EACH8.809,970.408.009,064.009.0010,197.00
0029732-01-01040Plastic Pavement Striping (8" Width) (Thermoplastic 90 mil) 144     LNFT5.50792.005.00720.005.65813.60
0030732-01-02080Plastic Pavement Striping (24" Width) (Thermoplastic 125 mil) 697     LNFT24.2016,867.4022.0015,334.0024.7517,250.75
0031732-02-02000Plastic Pavement Striping (Solid Line) (4" Width) (Thermoplastic 90 mil) 1.779 MILE9,900.0017,612.106,500.0011,563.5010,140.0018,039.06
0032732-03-02000Plastic Pavement Striping (Broken Line) (4" Width) (Thermoplastic 90 mil) 0.951 MILE8,250.007,845.7510,000.009,510.008,435.008,021.69
0033732-03-02010Plastic Pavement Striping (Dotted Line)(4" W)(2' L)(Thermo 90 mil) 0.011 MILE9,350.00102.8516,000.00176.008,700.0095.70
0034732-03-02030Plastic Pavement Striping (Dotted Line)(8" W)(2' L)(Thermo 90 mil) 0.022 MILE17,985.00395.6724,000.00528.0016,735.00368.17
0035732-04-01080Plastic Pavement Legends and Symbols (Arrow - Left Turn) 3     EACH715.002,145.00650.001,950.00730.002,190.00
0036739-01-00100Hydro-Seeding 1.25  ACRE4,890.006,112.503,000.003,750.003,150.003,937.50
0037740-01-00100Construction Layout 1     LUMP30,000.0030,000.00150,000.00150,000.00105,404.00105,404.00
0038741-28-02020Service Connection (1" PE) 900     LNFT14.0012,600.0075.0067,500.0061.0054,900.00
0039741-28-02040Service Connection (2" PE) 150     LNFT50.007,500.00100.0015,000.0071.0010,650.00
0040NS-300-00060Geogrid 21,493     SQYD2.0042,986.002.0042,986.001.7537,612.75
0041NS-500-00340Saw Cutting Asphalt Concrete Pavement 2,940     INLF1.253,675.001.002,940.001.103,234.00
0042NS-600-00220Saw Cutting Portland Cement Concrete Pavement 2,988     INLF1.504,482.001.002,988.002.005,976.00
  SUBTOTAL GENERAL   5,339,893 6,516,624 7,149,498
           
 Additive Section 1Additive Alternate 1        
           
0043201-01-00100Clearing and Grubbing 1     LUMP6,000.006,000.0047,000.0047,000.001,500.001,500.00
0044202-02-03030Removal of Pavement Structure 4,245.6   SQYD12.5053,070.0030.00127,368.0020.0084,912.00
0045202-02-06100Removal of Concrete Walks and Drives 667     SQYD15.0010,005.0020.0013,340.0018.7512,506.25
0046203-05-00100Excavation and Embankment 1     LUMP18,000.0018,000.0080,000.0080,000.0021,500.0021,500.00
0047204-02-00100Temporary Hay Bales 10     EACH35.00350.0035.00350.0040.00400.00
0048204-06-00100Temporary Silt Fencing 2,638     LNFT4.0010,552.003.007,914.002.255,935.50
0049302-02-08000Class II Base Course (8" Thick) 4,442.3   SQYD32.00142,153.6042.00186,576.6040.00177,692.00
0050305-01-04020Subgrade Layer (12" Thick) (Treated) 4,443     SQYD20.0088,860.0023.00102,189.0014.0062,202.00
0051402-01-00101Traffic Maintenance Surfacing (Aggregate) (Vehicular Measurement) 75     CUYD150.0011,250.00175.0013,125.00150.0011,250.00
0052402-02-00101Traffic Maintenance Surfacing (Hard) 10     SQYD125.001,250.0090.00900.00210.002,100.00
0053502-01-00100Asphalt Concrete 48.5   TON575.0027,887.50425.0020,612.50500.0024,250.00
0054601-01-00100Portland Cement Concrete Pavement (8" Thick) 4,134.6   SQYD99.00409,325.4095.00392,787.00125.00516,825.00
0055702-04-00200Adjusting Catch Basins 1     EACH5,000.005,000.005,000.005,000.006,000.006,000.00
0056703-01-00100Shoulder Underdrain Systems 1,319     LNFT18.0023,742.0020.0026,380.0042.0055,398.00
0057706-01-00100Concrete Walk (4" Thick) 658     SQYD90.0059,220.0074.0048,692.00110.0072,380.00
0058706-02-00200Concrete Drive (6" Thick) 174.9   SQYD100.0017,490.0090.0015,741.00125.0021,862.50
0059706-04-00110Curb Ramps Type 414     SQYD200.002,800.00380.005,320.00476.006,664.00
0060706-04-00110Curb Ramps Type 621     SQYD200.004,200.00360.007,560.00425.008,925.00
0061706-04-00110Curb Ramps Type 721     SQYD200.004,200.00230.004,830.00350.007,350.00
0062707-01-00100Concrete Curb 1,336.1   LNFT12.0016,033.206.008,016.6014.5019,373.45
0063707-03-00100Combination Concrete Curb and Gutter 11     LNFT75.00825.00140.001,540.00145.001,595.00
0064713-01-00100Temporary Signs and Barricades 1     LUMP26,000.0026,000.0052,000.0052,000.0075,000.3375,000.33
0065713-04-01020Temporary Pavement Markings (Solid Line) (4"Width) (Type 1 Removable) 0.565 MILE10,450.005,904.252,500.001,412.5011,350.006,412.75
0066727-01-00100Mobilization 1     LUMP110,000.00110,000.00135,000.00135,000.00140,000.00140,000.00
0067731-02-00100Reflectorized Raised Pavement Markers 66     EACH8.80580.809.00594.0010.50693.00
0068732-01-02080Plastic Pavement Striping (24" Width) (Thermoplastic 125 mil) 162     LNFT24.203,920.4022.003,564.0024.754,009.50
0069732-02-02000Plastic Pavement Striping (Solid Line) (4" Width) (Thermoplastic 90 mil) 0.372 MILE9,900.003,682.806,500.002,418.0010,100.003,757.20
0070732-03-02000Plastic Pavement Striping (Broken Line) (4" Width) (Thermoplastic 90 mil) 0.193 MILE8,250.001,592.2510,000.001,930.008,315.001,604.80
0071739-01-00100Hydro-Seeding 0.22  ACRE4,890.001,075.8016,000.003,520.0018,015.003,963.30
0072740-01-00100Construction Layout 1     LUMP6,000.006,000.0024,000.0024,000.0022,350.0022,350.00
0073741-28-02020Service Connection (1" PE) 150     LNFT14.002,100.0075.0011,250.0061.009,150.00
0074NS-300-00060Geogrid 4,442     SQYD2.008,884.002.008,884.001.757,773.50
0075NS-500-00340Saw Cutting Asphalt Concrete Pavement 816     INLF1.251,020.001.00816.001.10897.60
0076NS-600-00220Saw Cutting Portland Cement Concrete Pavement 948     INLF1.501,422.001.00948.002.001,896.00
  SUBTOTAL ADDITIVE SECTION 1   1,084,396.00 1,361,578.20 1,398,128.68
           
  CONTRACTOR TOTAL   6,424,288.57 7,878,202.50 8,547,627.00