Proposal:H.016043.6
Parish:Orleans
Routes:US 90
Description:US 90 (CLAIBORNE) @ AUDUBON BL: INT IMPR
Type Construction:GRADING, CLASS II BASE COURSE, CONCRETE WALKS AND CURBS, LANDSCAPING, ASPHALT CONCRETE PAVEMENT, AND RELATED WORK.
Estimated Construction Cost:$419,189.04
| Rank | License | Bidder | Construction Bid |
| 1 | 49356 | KORT's CONSTRUCTION SERVICES, INC. | $444,994.10 |
| 2 | 48896 | Command Construction Industries LLC | $451,995.50 |
| 3 | 75850 | Otwell Services, LLC | $474,178.50 |
| 4 | 36961 | Cycle Construction Co. L.L.C. | $524,993.20 |
| 5 | 74839 | 21 Construction, L.L.C. | $549,377.00 |
| 6 | 02179 | Boh Bros. Construction Co., LLC. | $549,390.00 |
| 7 | 00046 | Barber Bros. Contracting Co., L.L.C | $615,060.50 |
| 8 | 56388 | Franklin Pavement Management, Inc. | $692,635.88 |
Line Number | Item Number | Item Description | Quantity | Unit of Measure | - 1 - KORT's CONSTRUCTION SERVICES, INC. | - 2 - Command Construction Industries LLC | - 3 - Otwell Services, LLC | - 4 - Cycle Construction Co. L.L.C. | | Unit Price | Total Amount | Unit Price | Total Amount | Unit Price | Total Amount | Unit Price | Total Amount | | 0001 | 202-02-03030 | Removal of Pavement Structure | 559.7 | SQYD | 25.00 | 13,992.50 | 25.00 | 13,992.50 | 25.00 | 13,992.50 | 35.00 | 19,589.50 | | 0002 | 202-02-06080 | Removal of Concrete Combination Curb and Gutter | 582 | LNFT | 8.00 | 4,656.00 | 15.00 | 8,730.00 | 20.00 | 11,640.00 | 12.00 | 6,984.00 | | 0003 | 202-02-06100 | Removal of Concrete Walks and Drives | 116.2 | SQYD | 10.00 | 1,162.00 | 15.00 | 1,743.00 | 30.00 | 3,486.00 | 30.00 | 3,486.00 | | 0004 | 202-02-06102 | Removal of Incidental Concrete Paving | 41 | SQYD | 15.00 | 615.00 | 15.00 | 615.00 | 70.00 | 2,870.00 | 32.00 | 1,312.00 | | 0005 | 202-02-06140 | Removal of Curbs (Concrete) | 430 | LNFT | 5.00 | 2,150.00 | 15.00 | 6,450.00 | 15.00 | 6,450.00 | 10.00 | 4,300.00 | | 0006 | 202-02-38300 | Removal of Sign and U-Channel Post | 6 | EACH | 60.00 | 360.00 | 10.00 | 60.00 | 11.00 | 66.00 | 75.00 | 450.00 | | 0007 | 203-01-00100 | General Excavation | 525 | CUYD | 38.00 | 19,950.00 | 30.00 | 15,750.00 | 45.00 | 23,625.00 | 33.00 | 17,325.00 | | 0008 | 203-07-00100 | Borrow (Vehicular Measurement) | 162.6 | CUYD | 60.00 | 9,756.00 | 30.00 | 4,878.00 | 70.00 | 11,382.00 | 38.00 | 6,178.80 | | 0009 | 302-02-06030 | Class II Base Course (6" Thick) (Asphalt Concrete Base) | 1,393.6 | SQYD | 75.00 | 104,520.00 | 55.00 | 76,648.00 | 58.00 | 80,828.80 | 68.00 | 94,764.80 | | 0010 | 502-01-00100 | Asphalt Concrete | 523.6 | TON | 240.00 | 125,664.00 | 190.00 | 99,484.00 | 175.00 | 91,630.00 | 220.00 | 115,192.00 | | 0011 | 702-04-00100 | Adjusting Manholes | 2 | EACH | 1,200.00 | 2,400.00 | 1,500.00 | 3,000.00 | 750.00 | 1,500.00 | 2,200.00 | 4,400.00 | | 0012 | 706-01-00100 | Concrete Walk (4" Thick) | 47.7 | SQYD | 70.00 | 3,339.00 | 80.00 | 3,816.00 | 74.00 | 3,529.80 | 139.00 | 6,630.30 | | 0013 | 706-03-00300 | Incidental Concrete Paving (6" Thick) | 47.2 | SQYD | 88.00 | 4,153.60 | 85.00 | 4,012.00 | 84.00 | 3,964.80 | 125.00 | 5,900.00 | | 0014 | 706-04-00110 | Curb Ramps Type 2 | 10.4 | SQYD | 145.00 | 1,508.00 | 250.00 | 2,600.00 | 220.00 | 2,288.00 | 250.00 | 2,600.00 | | 0015 | 706-04-00110 | Curb Ramps Type 3 | 16.2 | SQYD | 170.00 | 2,754.00 | 250.00 | 4,050.00 | 220.00 | 3,564.00 | 250.00 | 4,050.00 | | 0016 | 706-04-00110 | Curb Ramps Type 7 | 12.8 | SQYD | 120.00 | 1,536.00 | 250.00 | 3,200.00 | 220.00 | 2,816.00 | 250.00 | 3,200.00 | | 0017 | 707-03-00100 | Combination Concrete Curb and Gutter | 1,111 | LNFT | 38.00 | 42,218.00 | 35.00 | 38,885.00 | 56.00 | 62,216.00 | 52.00 | 57,772.00 | | 0018 | 713-01-00100 | Temporary Signs and Barricades | 1 | LUMP | 25,000.00 | 25,000.00 | 50,000.00 | 50,000.00 | 46,000.00 | 46,000.00 | 19,000.00 | 19,000.00 | | 0019 | 716-01-00100 | Mulch (Vegetative) | 0.2 | TON | 15,000.00 | 3,000.00 | 5,000.00 | 1,000.00 | 2,250.00 | 450.00 | 1,700.00 | 340.00 | | 0020 | 717-01-00100 | Seeding | 2 | LB | 16.00 | 32.00 | 25.00 | 50.00 | 35.00 | 70.00 | 375.00 | 750.00 | | 0021 | 718-01-00100 | Fertilizer | 122 | LB | 1.00 | 122.00 | 1.00 | 122.00 | 1.75 | 213.50 | 3.00 | 366.00 | | 0022 | 719-01-06160 | Plants (Plant) (Container) (30 gallon) Crape Myrtle
Live Oak | 3 | EACH | 1,500.00 | 4,500.00 | 1,000.00 | 3,000.00 | 750.00 | 2,250.00 | 550.00 | 1,650.00 | | 0023 | 727-01-00100 | Mobilization | 1 | LUMP | 30,000.00 | 30,000.00 | 45,000.00 | 45,000.00 | 43,000.00 | 43,000.00 | 81,500.00 | 81,500.00 | | 0024 | 729-01-00100 | Sign (Type A) | 176 | SQFT | 45.00 | 7,920.00 | 15.00 | 2,640.00 | 17.75 | 3,124.00 | 23.00 | 4,048.00 | | 0025 | 729-22-00100 | Square Tubing Post with 2-1/4" Anchor | 13 | EACH | 215.00 | 2,795.00 | 150.00 | 1,950.00 | 176.50 | 2,294.50 | 175.00 | 2,275.00 | | 0026 | 731-02-00100 | Reflectorized Raised Pavement Markers | 164 | EACH | 5.00 | 820.00 | 4.00 | 656.00 | 4.75 | 779.00 | 5.00 | 820.00 | | 0027 | 732-01-01040 | Plastic Pavement Striping (8" Width) (Thermoplastic 90 mil) | 1,022 | LNFT | 4.00 | 4,088.00 | 3.00 | 3,066.00 | 3.50 | 3,577.00 | 3.50 | 3,577.00 | | 0028 | 732-01-02080 | Plastic Pavement Striping (24" Width) (Thermoplastic 125 mil) | 700 | LNFT | 15.00 | 10,500.00 | 12.00 | 8,400.00 | 14.00 | 9,800.00 | 14.00 | 9,800.00 | | 0029 | 732-02-02000 | Plastic Pavement Striping (Solid Line) (4" Width) (Thermoplastic 90 mil) | 0.172 | MILE | 6,000.00 | 1,032.00 | 5,000.00 | 860.00 | 5,600.00 | 963.20 | 6,100.00 | 1,049.20 | | 0030 | 732-04-01080 | Plastic Pavement Legends and Symbols (Arrow - Left Turn) | 4 | EACH | 340.00 | 1,360.00 | 300.00 | 1,200.00 | 310.00 | 1,240.00 | 320.00 | 1,280.00 | | 0031 | 732-05-00100 | Removal of Existing Markings | 0.126 | MILE | 3,500.00 | 441.00 | 3,000.00 | 378.00 | 3,400.00 | 428.40 | 3,600.00 | 453.60 | | 0032 | 740-01-00100 | Construction Layout | 1 | LUMP | 6,500.00 | 6,500.00 | 25,000.00 | 25,000.00 | 15,000.00 | 15,000.00 | 21,000.00 | 21,000.00 | | 0033 | NS-201-00001 | Tree and Stump Removal (<= 36" Diameter) | 3 | EACH | 900.00 | 2,700.00 | 6,000.00 | 18,000.00 | 5,000.00 | 15,000.00 | 6,500.00 | 19,500.00 | | 0034 | NS-500-00360 | Saw Cutting Asphalt Concrete Pavement Over Portland Cement Concrete Composite Pavement | 2,760 | INLF | 1.25 | 3,450.00 | 1.00 | 2,760.00 | 1.50 | 4,140.00 | 1.25 | 3,450.00 | | | | | | | | | | | | | | | | | | CONTRACTOR TOTAL | | | | 444,994.10 | | 451,995.50 | | 474,178.50 | | 524,993.20 |
Line Number | Item Number | Item Description | Quantity | Unit of Measure | - 5 - 21 Construction, L.L.C. | - 6 - Boh Bros. Construction Co., LLC. | - 7 - Barber Bros. Contracting Co., L.L.C | - 8 - Franklin Pavement Management, Inc. | | Unit Price | Total Amount | Unit Price | Total Amount | Unit Price | Total Amount | Unit Price | Total Amount | | 0001 | 202-02-03030 | Removal of Pavement Structure | 559.7 | SQYD | 30.00 | 16,791.00 | 10.00 | 5,597.00 | 35.00 | 19,589.50 | 38.00 | 21,268.60 | | 0002 | 202-02-06080 | Removal of Concrete Combination Curb and Gutter | 582 | LNFT | 35.00 | 20,370.00 | 10.00 | 5,820.00 | 25.00 | 14,550.00 | 35.00 | 20,370.00 | | 0003 | 202-02-06100 | Removal of Concrete Walks and Drives | 116.2 | SQYD | 30.00 | 3,486.00 | 10.00 | 1,162.00 | 40.00 | 4,648.00 | 52.00 | 6,042.40 | | 0004 | 202-02-06102 | Removal of Incidental Concrete Paving | 41 | SQYD | 30.00 | 1,230.00 | 20.00 | 820.00 | 40.00 | 1,640.00 | 46.00 | 1,886.00 | | 0005 | 202-02-06140 | Removal of Curbs (Concrete) | 430 | LNFT | 35.00 | 15,050.00 | 10.00 | 4,300.00 | 15.00 | 6,450.00 | 18.00 | 7,740.00 | | 0006 | 202-02-38300 | Removal of Sign and U-Channel Post | 6 | EACH | 150.00 | 900.00 | 125.00 | 750.00 | 60.00 | 360.00 | 19.00 | 114.00 | | 0007 | 203-01-00100 | General Excavation | 525 | CUYD | 50.00 | 26,250.00 | 40.00 | 21,000.00 | 60.00 | 31,500.00 | 134.00 | 70,350.00 | | 0008 | 203-07-00100 | Borrow (Vehicular Measurement) | 162.6 | CUYD | 48.00 | 7,804.80 | 75.00 | 12,195.00 | 125.00 | 20,325.00 | 115.00 | 18,699.00 | | 0009 | 302-02-06030 | Class II Base Course (6" Thick) (Asphalt Concrete Base) | 1,393.6 | SQYD | 59.00 | 82,222.40 | 90.00 | 125,424.00 | 80.00 | 111,488.00 | 131.00 | 182,561.60 | | 0010 | 502-01-00100 | Asphalt Concrete | 523.6 | TON | 215.00 | 112,574.00 | 295.00 | 154,462.00 | 245.00 | 128,282.00 | 179.00 | 93,724.40 | | 0011 | 702-04-00100 | Adjusting Manholes | 2 | EACH | 950.00 | 1,900.00 | 950.00 | 1,900.00 | 5,000.00 | 10,000.00 | 2,020.00 | 4,040.00 | | 0012 | 706-01-00100 | Concrete Walk (4" Thick) | 47.7 | SQYD | 140.00 | 6,678.00 | 100.00 | 4,770.00 | 150.00 | 7,155.00 | 108.00 | 5,151.60 | | 0013 | 706-03-00300 | Incidental Concrete Paving (6" Thick) | 47.2 | SQYD | 60.00 | 2,832.00 | 100.00 | 4,720.00 | 150.00 | 7,080.00 | 114.00 | 5,380.80 | | 0014 | 706-04-00110 | Curb Ramps Type 2 | 10.4 | SQYD | 300.00 | 3,120.00 | 275.00 | 2,860.00 | 275.00 | 2,860.00 | 258.00 | 2,683.20 | | 0015 | 706-04-00110 | Curb Ramps Type 3 | 16.2 | SQYD | 300.00 | 4,860.00 | 345.00 | 5,589.00 | 275.00 | 4,455.00 | 258.00 | 4,179.60 | | 0016 | 706-04-00110 | Curb Ramps Type 7 | 12.8 | SQYD | 300.00 | 3,840.00 | 225.00 | 2,880.00 | 275.00 | 3,520.00 | 258.00 | 3,302.40 | | 0017 | 707-03-00100 | Combination Concrete Curb and Gutter | 1,111 | LNFT | 82.00 | 91,102.00 | 45.00 | 49,995.00 | 50.00 | 55,550.00 | 74.00 | 82,214.00 | | 0018 | 713-01-00100 | Temporary Signs and Barricades | 1 | LUMP | 25,000.00 | 25,000.00 | 34,000.00 | 34,000.00 | 55,000.00 | 55,000.00 | 50,000.00 | 50,000.00 | | 0019 | 716-01-00100 | Mulch (Vegetative) | 0.2 | TON | 13,750.00 | 2,750.00 | 14,400.00 | 2,880.00 | 13,000.00 | 2,600.00 | 8,430.00 | 1,686.00 | | 0020 | 717-01-00100 | Seeding | 2 | LB | 15.00 | 30.00 | 15.00 | 30.00 | 15.00 | 30.00 | 56.00 | 112.00 | | 0021 | 718-01-00100 | Fertilizer | 122 | LB | 1.00 | 122.00 | 1.00 | 122.00 | 1.00 | 122.00 | 6.00 | 732.00 | | 0022 | 719-01-06160 | Plants (Plant) (Container) (30 gallon) Crape Myrtle
Live Oak | 3 | EACH | 1,100.00 | 3,300.00 | 1,155.00 | 3,465.00 | 1,000.00 | 3,000.00 | 682.00 | 2,046.00 | | 0023 | 727-01-00100 | Mobilization | 1 | LUMP | 50,000.00 | 50,000.00 | 45,000.00 | 45,000.00 | 60,000.00 | 60,000.00 | 30,000.00 | 30,000.00 | | 0024 | 729-01-00100 | Sign (Type A) | 176 | SQFT | 28.00 | 4,928.00 | 35.00 | 6,160.00 | 30.00 | 5,280.00 | 40.00 | 7,040.00 | | 0025 | 729-22-00100 | Square Tubing Post with 2-1/4" Anchor | 13 | EACH | 250.00 | 3,250.00 | 225.00 | 2,925.00 | 275.00 | 3,575.00 | 269.00 | 3,497.00 | | 0026 | 731-02-00100 | Reflectorized Raised Pavement Markers | 164 | EACH | 4.50 | 738.00 | 5.00 | 820.00 | 5.00 | 820.00 | 12.00 | 1,968.00 | | 0027 | 732-01-01040 | Plastic Pavement Striping (8" Width) (Thermoplastic 90 mil) | 1,022 | LNFT | 3.50 | 3,577.00 | 4.00 | 4,088.00 | 4.00 | 4,088.00 | 6.00 | 6,132.00 | | 0028 | 732-01-02080 | Plastic Pavement Striping (24" Width) (Thermoplastic 125 mil) | 700 | LNFT | 13.50 | 9,450.00 | 14.00 | 9,800.00 | 15.00 | 10,500.00 | 24.00 | 16,800.00 | | 0029 | 732-02-02000 | Plastic Pavement Striping (Solid Line) (4" Width) (Thermoplastic 90 mil) | 0.172 | MILE | 5,500.00 | 946.00 | 5,800.00 | 997.60 | 6,000.00 | 1,032.00 | 6,452.00 | 1,109.74 | | 0030 | 732-04-01080 | Plastic Pavement Legends and Symbols (Arrow - Left Turn) | 4 | EACH | 300.00 | 1,200.00 | 320.00 | 1,280.00 | 335.00 | 1,340.00 | 383.00 | 1,532.00 | | 0031 | 732-05-00100 | Removal of Existing Markings | 0.126 | MILE | 3,300.00 | 415.80 | 3,400.00 | 428.40 | 3,500.00 | 441.00 | 13,517.00 | 1,703.14 | | 0032 | 740-01-00100 | Construction Layout | 1 | LUMP | 15,000.00 | 15,000.00 | 10,500.00 | 10,500.00 | 10,000.00 | 10,000.00 | 30,000.00 | 30,000.00 | | 0033 | NS-201-00001 | Tree and Stump Removal (<= 36" Diameter) | 3 | EACH | 6,000.00 | 18,000.00 | 6,400.00 | 19,200.00 | 6,500.00 | 19,500.00 | 1,348.00 | 4,044.00 | | 0034 | NS-500-00360 | Saw Cutting Asphalt Concrete Pavement Over Portland Cement Concrete Composite Pavement | 2,760 | INLF | 3.50 | 9,660.00 | 1.25 | 3,450.00 | 3.00 | 8,280.00 | 1.64 | 4,526.40 | | | | | | | | | | | | | | | | | | CONTRACTOR TOTAL | | | | 549,377.00 | | 549,390.00 | | 615,060.50 | | 692,635.88 |
|