Proposal:H.015801.6
Parish:Terrebonne
Routes:LA 182
Description:LA 182: LA 311 - LA 24
Type Construction:MILLING ASPHALT CONCRETE, PAVEMENT PATCHING, ASPHALT CONCRETE OVERLAY, AND RELATED WORK.
Estimated Construction Cost:$1,880,377.40
| Rank | License | Bidder | Construction Bid |
| 1 | 62139 | Huey P. Stockstill, LLC | $1,764,899.27 |
| 2 | 06276 | Barriere Construction Co., LLC | $1,836,426.34 |
Line Number | Item Number | Item Description | Quantity | Unit of Measure | - 1 - Huey P. Stockstill, LLC | - 2 - Barriere Construction Co., LLC | | Unit Price | Total Amount | Unit Price | Total Amount | | 0001 | 202-02-06100 | Removal of Concrete Walks and Drives | 122 | SQYD | 45.00 | 5,490.00 | 35.00 | 4,270.00 | | 0002 | 202-02-06140 | Removal of Curbs (Concrete) | 1,221 | LNFT | 3.50 | 4,273.50 | 22.00 | 26,862.00 | | 0003 | 202-02-38220 | Removal of Sign Supports | 2 | EACH | 65.00 | 130.00 | 50.00 | 100.00 | | 0004 | 202-03-38000 | Relocation of Sign | 2 | EACH | 150.00 | 300.00 | 100.00 | 200.00 | | 0005 | 203-01-00100 | General Excavation | 2.9 | CUYD | 315.00 | 913.50 | 300.00 | 870.00 | | 0006 | 203-07-00100 | Borrow (Vehicular Measurement) | 95 | CUYD | 75.00 | 7,125.00 | 21.00 | 1,995.00 | | 0007 | 502-01-00100 | Asphalt Concrete | 3,302.5 | TON | 112.00 | 369,880.00 | 131.00 | 432,627.50 | | 0008 | 502-01-00200 | Asphalt Concrete, Drives, Turnouts and Miscellaneous | 279 | TON | 255.00 | 71,145.00 | 231.00 | 64,449.00 | | 0009 | 509-01-00100 | Milling Asphalt Pavement | 31,474 | SQYD | 2.05 | 64,521.70 | 3.00 | 94,422.00 | | 0010 | 509-02-00100 | Contractor Retained Reclaimed Asphalt Pavement | -1,749 | CUYD | 0.01 | -17.49 | 20.00 | -34,980.00 | | 0011 | 510-01-00200 | Pavement Patching (12" Minimum Thickness) | 3,520 | SQYD | 130.00 | 457,600.00 | 113.00 | 397,760.00 | | 0012 | 510-03-00100 | Pavement Joint Repair | 5 | TON | 750.00 | 3,750.00 | 3,000.00 | 15,000.00 | | 0013 | 702-03-00001 | Catch Basin (Remove and Replace Frame and Cover) | 1 | EACH | 4,200.00 | 4,200.00 | 6,500.00 | 6,500.00 | | 0014 | 702-04-00001 | Adjusting Miscellaneous Structures (Replace Drainage Grates) | 1 | EACH | 2,350.00 | 2,350.00 | 6,850.00 | 6,850.00 | | 0015 | 702-04-00100 | Adjusting Manholes | 4 | EACH | 2,500.00 | 10,000.00 | 1,175.00 | 4,700.00 | | 0016 | 702-04-00150 | Adjusting Manholes w/Manhole Adjustment Rings | 9 | EACH | 275.00 | 2,475.00 | 275.00 | 2,475.00 | | 0017 | 702-04-00200 | Adjusting Catch Basins | 17 | EACH | 2,350.00 | 39,950.00 | 2,950.00 | 50,150.00 | | 0018 | 702-04-00300 | Adjusting Junction Boxes | 7 | EACH | 2,350.00 | 16,450.00 | 1,500.00 | 10,500.00 | | 0019 | 706-01-00100 | Concrete Walk (4" Thick) | 152.9 | SQYD | 105.00 | 16,054.50 | 285.00 | 43,576.50 | | 0020 | 706-04-00110 | Curb Ramps TYPE 1 | 115.2 | SQYD | 195.00 | 22,464.00 | 335.00 | 38,592.00 | | 0021 | 706-04-00110 | Curb Ramps TYPE 4 | 17.9 | SQYD | 175.00 | 3,132.50 | 335.00 | 5,996.50 | | 0022 | 706-04-00110 | Curb Ramps TYPE 5 | 362.9 | SQYD | 185.00 | 67,136.50 | 335.00 | 121,571.50 | | 0023 | 706-04-00110 | Curb Ramps TYPE 6 | 13.7 | SQYD | 205.00 | 2,808.50 | 335.00 | 4,589.50 | | 0024 | 706-04-00110 | Curb Ramps TYPE 7 | 93.1 | SQYD | 195.00 | 18,154.50 | 335.00 | 31,188.50 | | 0025 | 706-04-00110 | Curb Ramps TYPE 8 | 15.5 | SQYD | 195.00 | 3,022.50 | 335.00 | 5,192.50 | | 0026 | 707-01-00100 | Concrete Curb | 1,052 | LNFT | 30.00 | 31,560.00 | 48.00 | 50,496.00 | | 0027 | 707-03-00100 | Combination Concrete Curb and Gutter | 267 | LNFT | 37.00 | 9,879.00 | 65.00 | 17,355.00 | | 0028 | 713-01-00100 | Temporary Signs and Barricades | 1 | LUMP | 205,000.00 | 205,000.00 | 150,000.00 | 150,000.00 | | 0029 | 713-02-00300 | Temporary Pavement Markings (8" Width) | 2,622 | LNFT | 0.15 | 393.30 | 0.15 | 393.30 | | 0030 | 713-02-00500 | Temporary Pavement Markings (24" Width) | 608 | LNFT | 0.50 | 304.00 | 0.50 | 304.00 | | 0031 | 713-03-01000 | Temporary Pavement Markings (Broken Line) (4" Width) (4' Length) | 2.558 | MILE | 195.00 | 498.81 | 710.00 | 1,816.18 | | 0032 | 713-04-01000 | Temporary Pavement Markings (Solid Line) (4" Width) | 9.779 | MILE | 900.00 | 8,801.10 | 900.00 | 8,801.10 | | 0033 | 713-05-00200 | Temporary Pavement Legends & Symbols (Arrow - Double) | 4 | EACH | 25.00 | 100.00 | 25.00 | 100.00 | | 0034 | 713-05-00220 | Temporary Pavement Legends & Symbols (Arrow - Left Turn) | 4 | EACH | 25.00 | 100.00 | 25.00 | 100.00 | | 0035 | 716-01-00100 | Mulch (Vegetative) | 0.5 | TON | 3,500.00 | 1,750.00 | 5,900.00 | 2,950.00 | | 0036 | 717-01-00100 | Seeding | 16 | LB | 5.00 | 80.00 | 10.19 | 163.04 | | 0037 | 718-01-00100 | Fertilizer | 271 | LB | 0.50 | 135.50 | 0.72 | 195.12 | | 0038 | 727-01-00100 | Mobilization | 1 | LUMP | 176,000.00 | 176,000.00 | 138,000.00 | 138,000.00 | | 0039 | 729-22-00200 | Square Tubing Post with 2-1/4" Omni-Directional Anchor | 2 | EACH | 165.00 | 330.00 | 150.00 | 300.00 | | 0040 | 731-02-00100 | Reflectorized Raised Pavement Markers | 430 | EACH | 5.00 | 2,150.00 | 5.00 | 2,150.00 | | 0041 | 732-01-01040 | Plastic Pavement Striping (8" Width) (Thermoplastic 90 mil) | 135 | LNFT | 3.00 | 405.00 | 3.00 | 405.00 | | 0042 | 732-01-01080 | Plastic Pavement Striping (24" Width) (Thermoplastic 90 mil) | 128 | LNFT | 14.00 | 1,792.00 | 14.00 | 1,792.00 | | 0043 | 732-01-02040 | Plastic Pavement Striping (8" Width) (Thermoplastic 125 mil) | 1,120 | LNFT | 3.00 | 3,360.00 | 3.00 | 3,360.00 | | 0044 | 732-01-02080 | Plastic Pavement Striping (24" Width) (Thermoplastic 125 mil) | 176 | LNFT | 14.00 | 2,464.00 | 14.00 | 2,464.00 | | 0045 | 732-02-02000 | Plastic Pavement Striping (Solid Line) (4" Width) (Thermoplastic 90 mil) | 5.247 | MILE | 4,300.00 | 22,562.10 | 4,300.00 | 22,562.10 | | 0046 | 732-03-02030 | Plastic Pavement Striping (Dotted Line)(8" W)(2' L)(Thermo 90 mil) | 0.021 | MILE | 8,100.00 | 170.10 | 8,500.00 | 178.50 | | 0047 | 732-04-01040 | Plastic Pavement Legends and Symbols (Arrow - Double) | 2 | EACH | 350.00 | 700.00 | 350.00 | 700.00 | | 0048 | 732-04-01080 | Plastic Pavement Legends and Symbols (Arrow - Left Turn) | 2 | EACH | 325.00 | 650.00 | 325.00 | 650.00 | | 0049 | 732-04-08040 | Plastic Pavement Legends and Symbols (Handicap Parking) | 2 | EACH | 450.00 | 900.00 | 450.00 | 900.00 | | 0050 | 740-01-00100 | Construction Layout | 1 | LUMP | 30,000.00 | 30,000.00 | 13,000.00 | 13,000.00 | | 0051 | 741-35-00100 | Adjust Valve or Meter Box | 9 | EACH | 150.00 | 1,350.00 | 645.00 | 5,805.00 | | 0052 | NS-500-00220 | Sawing and Sealing Longitudinal Joints in Asphalt Concrete Overlay | 20,265 | LNFT | 1.50 | 30,397.50 | 1.95 | 39,516.75 | | 0053 | NS-500-00240 | Sawing and Sealing Transverse Joints in Asphalt Concrete Overlay | 6,755 | LNFT | 1.55 | 10,470.25 | 1.95 | 13,172.25 | | 0054 | NS-500-00260 | Sawcuts in Asphalt Concrete Lifts | 27,020 | LNFT | 1.05 | 28,371.00 | 0.80 | 21,616.00 | | 0055 | NS-500-00360 | Saw Cutting Asphalt Concrete Pavement Over Portland Cement Concrete Composite Pavement | 552 | INLF | 1.35 | 745.20 | 2.25 | 1,242.00 | | 0056 | NS-600-00220 | Saw Cutting Portland Cement Concrete Pavement | 214 | INLF | 0.80 | 171.20 | 2.25 | 481.50 | | | | | | | | | | | | | | CONTRACTOR TOTAL | | | | 1,764,899.27 | | 1,836,426.34 |
|