Proposal:H.015333.6
Parish:Tangipahoa
Description:EASLEY ROAD OVER SWEETWATER CREEK
Type Construction:CLEARING AND GRUBBING, REMOVAL OF BRIDGE, GRADING, DRAINAGE STRUCTURES, CLASS II BASE COURSE, LIME TREATMENT, ASPHALT CONCRETE PAVEMENT, CONCRETE SLAB SPAN BRIDGE, PRECAST CONCRETE PILES, AND RELATED WORK.
Estimated Construction Cost:$1,223,222.46
| Rank | License | Bidder | Construction Bid |
| 1 | 39613 | Baker Pile Driving and Site Work, LLC | $1,199,099.46 |
| 2 | 28190 | Buck Town Contractors & Co. | $1,260,369.00 |
| 3 | 01516 | Elevate Heavy Civil Construction, LLC | $1,372,993.70 |
| 4 | 00009 | Coastal Contractors, LLC | $1,374,540.95 |
| 5 | 12487 | Diamond B Construction Co., L.L.C. | $1,418,823.00 |
| 6 | 67770 | Reliant Industrial Solutions L.L.C. | $1,489,934.96 |
| 7 | 56994 | Matt L. Guinn Construction, LLC | $1,528,844.50 |
| 8 | 00044 | Guinn Construction, LLC | $1,544,019.30 |
| 9 | 39462 | JB JAMES CONSTRUCTION LLC | $1,652,733.95 |
Line Number | Item Number | Item Description | Quantity | Unit of Measure | - 1 - Baker Pile Driving and Site Work, LLC | - 2 - Buck Town Contractors & Co. | - 3 - Elevate Heavy Civil Construction, LLC | - 4 - Coastal Contractors, LLC | | Unit Price | Total Amount | Unit Price | Total Amount | Unit Price | Total Amount | Unit Price | Total Amount | | 0001 | 201-01-00100 | Clearing and Grubbing | 0.77 | LUMP | 14,742.00 | 14,742.00 | 7,800.00 | 7,800.00 | 82,500.00 | 82,500.00 | 50,000.00 | 50,000.00 | | 0002 | 202-02-03030 | Removal of Pavement Structure | 990.3 | SQYD | 15.80 | 15,646.74 | 27.00 | 26,738.10 | 20.00 | 19,806.00 | 23.00 | 22,776.90 | | 0003 | 202-02-04501 | Removal of Bridge (Str. No. 625330394902611; STA. 106+07.79; 20' 47' TTTRES) | 940 | LUMP | 22,883.57 | 22,883.57 | 50,110.30 | 50,110.30 | 60,400.00 | 60,400.00 | 100,000.00 | 100,000.00 | | 0004 | 202-02-12000 | Removal of Fence | 276 | LNFT | 6.32 | 1,744.32 | 7.00 | 1,932.00 | 7.00 | 1,932.00 | 4.00 | 1,104.00 | | 0005 | 202-02-32120 | Removal of Pipe (Side Drain) (Side Drain) (15'' Metal) | 18 | LNFT | 25.27 | 454.86 | 50.00 | 900.00 | 76.00 | 1,368.00 | 36.00 | 648.00 | | 0006 | 203-02-00100 | Drainage Excavation | 703 | CUYD | 21.09 | 14,826.27 | 25.00 | 17,575.00 | 24.00 | 16,872.00 | 47.00 | 33,041.00 | | 0007 | 203-05-00100 | Excavation and Embankment | 1 | LUMP | 37,379.19 | 37,379.19 | 25,300.00 | 25,300.00 | 49,000.00 | 49,000.00 | 38,000.00 | 38,000.00 | | 0008 | 204-05-00100 | Temporary Sediment Check Dams (Hay) | 8 | EACH | 257.57 | 2,060.56 | 70.00 | 560.00 | 150.00 | 1,200.00 | 179.00 | 1,432.00 | | 0009 | 204-06-00100 | Temporary Silt Fencing | 1,152 | LNFT | 3.08 | 3,548.16 | 2.00 | 2,304.00 | 3.00 | 3,456.00 | 4.00 | 4,608.00 | | 0010 | 302-02-08080 | Class II Base Course (8" Thick) (Asphalt Concrete Base) | 1,202.6 | SQYD | 69.00 | 82,979.40 | 75.00 | 90,195.00 | 85.00 | 102,221.00 | 80.00 | 96,208.00 | | 0011 | 304-01-00100 | Lime | 17.05 | TON | 465.00 | 7,928.25 | 380.00 | 6,479.00 | 444.00 | 7,570.20 | 325.00 | 5,541.25 | | 0012 | 304-05-00100 | Lime Treatment (Type E) | 1,203 | SQYD | 16.42 | 19,753.26 | 10.00 | 12,030.00 | 14.00 | 16,842.00 | 12.00 | 14,436.00 | | 0013 | 401-02-00100 | Aggregate Surface Course (Adjusted Vehicular Measurement) | 3 | CUYD | 173.47 | 520.41 | 350.00 | 1,050.00 | 249.00 | 747.00 | 150.00 | 450.00 | | 0014 | 402-01-00101 | Traffic Maintenance Surfacing (Aggregate) (Vehicular Measurement) | 5 | CUYD | 160.94 | 804.70 | 150.00 | 750.00 | 222.00 | 1,110.00 | 150.00 | 750.00 | | 0015 | 502-01-00100 | Asphalt Concrete | 248.4 | TON | 194.00 | 48,189.60 | 220.00 | 54,648.00 | 197.00 | 48,934.80 | 240.00 | 59,616.00 | | 0016 | 502-01-00200 | Asphalt Concrete, Drives, Turnouts and Miscellaneous | 42.4 | TON | 471.00 | 19,970.40 | 520.00 | 22,048.00 | 345.00 | 14,628.00 | 425.00 | 18,020.00 | | 0017 | 701-06-00020 | Side Drain Pipe Arch (18" Equiv. RCPA) | 108 | LNFT | 109.10 | 11,782.80 | 170.00 | 18,360.00 | 149.00 | 16,092.00 | 180.00 | 19,440.00 | | 0018 | 702-03-00100 | Catch Basins (CB-01) | 1 | EACH | 4,963.48 | 4,963.48 | 4,500.00 | 4,500.00 | 6,634.00 | 6,634.00 | 6,600.00 | 6,600.00 | | 0019 | 704-03-00200 | Blocked Out Guard Rail - 31", (6'-3" Post Spacing) | 50 | LNFT | 30.68 | 1,534.00 | 26.00 | 1,300.00 | 31.00 | 1,550.00 | 24.00 | 1,200.00 | | 0020 | 704-07-00200 | Guard Rail Transitions (Double Thrie Beam) | 100 | LNFT | 98.53 | 9,853.00 | 110.00 | 11,000.00 | 118.00 | 11,800.00 | 100.00 | 10,000.00 | | 0021 | 704-10-00205 | Guard Rail End Treatment, MASH, (TL-3 Tangent) | 4 | EACH | 3,252.94 | 13,011.76 | 3,600.00 | 14,400.00 | 3,425.00 | 13,700.00 | 3,250.00 | 13,000.00 | | 0022 | 705-01-00100 | Barbed Wire Fence | 521 | LNFT | 19.01 | 9,904.21 | 16.00 | 8,336.00 | 14.00 | 7,294.00 | 15.00 | 7,815.00 | | 0023 | 705-04-00100 | Single Swinging Driveway Gates | 1 | EACH | 1,955.24 | 1,955.24 | 5,000.00 | 5,000.00 | 1,500.00 | 1,500.00 | 2,500.00 | 2,500.00 | | 0024 | 708-01-00100 | Right-of-Way Monument | 12 | EACH | 663.11 | 7,957.32 | 300.00 | 3,600.00 | 600.00 | 7,200.00 | 700.00 | 8,400.00 | | 0025 | 708-02-00100 | Right-of-Way Monument Witness Post | 12 | EACH | 241.91 | 2,902.92 | 200.00 | 2,400.00 | 200.00 | 2,400.00 | 225.00 | 2,700.00 | | 0026 | 711-01-04000 | Riprap (55 lb, 18" Thick) | 313 | SQYD | 135.23 | 42,326.99 | 130.00 | 40,690.00 | 112.00 | 35,056.00 | 120.00 | 37,560.00 | | 0027 | 711-04-00100 | Geotextile Fabric | 313 | SQYD | 5.41 | 1,693.33 | 2.00 | 626.00 | 5.00 | 1,565.00 | 5.00 | 1,565.00 | | 0028 | 713-01-00100 | Temporary Signs and Barricades | 1 | LUMP | 21,829.33 | 21,829.33 | 18,000.00 | 18,000.00 | 41,000.00 | 41,000.00 | 35,000.00 | 35,000.00 | | 0029 | 716-01-00100 | Mulch (Vegetative) | 0.1 | TON | 11,655.00 | 1,165.50 | 5,200.00 | 520.00 | 4,300.00 | 430.00 | 4,500.00 | 450.00 | | 0030 | 720-01-01000 | Erosion Control System (Slope Protection) (Type A) | 359 | SQYD | 6.31 | 2,265.29 | 2.00 | 718.00 | 2.00 | 718.00 | 2.00 | 718.00 | | 0031 | 726-01-00100 | Bedding Material | 10.9 | CUYD | 219.00 | 2,387.10 | 350.00 | 3,815.00 | 166.00 | 1,809.40 | 187.00 | 2,038.30 | | 0032 | 727-01-00100 | Mobilization | 1 | LUMP | 130,012.96 | 130,012.96 | 120,000.00 | 120,000.00 | 137,500.00 | 137,500.00 | 130,000.00 | 130,000.00 | | 0033 | 729-16-00300 | Object Marker Assembly (Type 3) | 4 | EACH | 199.24 | 796.96 | 120.00 | 480.00 | 85.00 | 340.00 | 105.00 | 420.00 | | 0034 | 732-03-02000 | Plastic Pavement Striping (Broken Line) (4" Width) (Thermoplastic 90 mil) | 0.102 | MILE | 45,400.00 | 4,630.80 | 25,000.00 | 2,550.00 | 20,000.00 | 2,040.00 | 22,000.00 | 2,244.00 | | 0035 | 739-01-00100 | Hydro-Seeding | 0.47 | ACRE | 8,697.00 | 4,087.59 | 8,600.00 | 4,042.00 | 6,400.00 | 3,008.00 | 6,500.00 | 3,055.00 | | 0036 | 740-01-00100 | Construction Layout | 1 | LUMP | 31,360.45 | 31,360.45 | 17,000.00 | 17,000.00 | 26,000.00 | 26,000.00 | 18,000.00 | 18,000.00 | | 0037 | 804-01-00300 | Precast Concrete Piles (16") | 1,200 | LNFT | 164.30 | 197,160.00 | 220.00 | 264,000.00 | 171.00 | 205,200.00 | 154.00 | 184,800.00 | | 0038 | 805-01-00100 | Class A1 Concrete (Slab Span) | 88.32 | CUYD | 2,005.00 | 177,081.60 | 1,830.00 | 161,625.60 | 1,640.00 | 144,844.80 | 2,750.00 | 242,880.00 | | 0039 | 805-01-00300 | Class A1 Concrete (Bent Cap) | 23.69 | CUYD | 2,778.00 | 65,810.82 | 2,700.00 | 63,963.00 | 4,050.00 | 95,944.50 | 2,850.00 | 67,516.50 | | 0040 | 805-18-00100 | Concrete Finish (Class 2 Rubbed Finish) | 947 | SQFT | 4.61 | 4,365.67 | 2.00 | 1,894.00 | 3.00 | 2,841.00 | 2.50 | 2,367.50 | | 0041 | 805-18-00200 | Concrete Finish (Class 3 Special Finish) | 947 | SQFT | 4.49 | 4,252.03 | 2.00 | 1,894.00 | 4.00 | 3,788.00 | 3.50 | 3,314.50 | | 0042 | 806-01-00100 | Deformed Reinforcing Steel | 23,740 | LB | 1.38 | 32,761.20 | 1.40 | 33,236.00 | 2.00 | 47,480.00 | 1.40 | 33,236.00 | | 0043 | 810-01-00100 | Concrete Bridge Railing (Standard) | 80 | LNFT | 357.55 | 28,604.00 | 290.00 | 23,200.00 | 246.00 | 19,680.00 | 225.00 | 18,000.00 | | 0044 | 810-01-00200 | Concrete Bridge Railing (Slotted) | 80 | LNFT | 209.52 | 16,761.60 | 290.00 | 23,200.00 | 246.00 | 19,680.00 | 225.00 | 18,000.00 | | 0045 | 813-01-00100 | Concrete Approach Slabs (Cast-in-Place) | 500 | SQFT | 138.20 | 69,100.00 | 162.00 | 81,000.00 | 166.00 | 83,000.00 | 100.00 | 50,000.00 | | 0046 | 815-03-00300 | Joint Seal (Poured) | 120 | LNFT | 19.92 | 2,390.40 | 42.00 | 5,040.00 | 30.00 | 3,600.00 | 35.00 | 4,200.00 | | 0047 | NS-500-00340 | Saw Cutting Asphalt Concrete Pavement | 178 | INLF | 5.39 | 959.42 | 20.00 | 3,560.00 | 4.00 | 712.00 | 5.00 | 890.00 | | | | | | | | | | | | | | | | | | CONTRACTOR TOTAL | | | | 1,199,099.46 | | 1,260,369.00 | | 1,372,993.70 | | 1,374,540.95 |
Line Number | Item Number | Item Description | Quantity | Unit of Measure | - 5 - Diamond B Construction Co., L.L.C. | - 6 - Reliant Industrial Solutions L.L.C. | - 7 - Matt L. Guinn Construction, LLC | - 8 - Guinn Construction, LLC | | Unit Price | Total Amount | Unit Price | Total Amount | Unit Price | Total Amount | Unit Price | Total Amount | | 0001 | 201-01-00100 | Clearing and Grubbing | 0.77 | LUMP | 34,000.00 | 34,000.00 | 50,000.00 | 50,000.00 | 50,000.00 | 50,000.00 | 60,000.00 | 60,000.00 | | 0002 | 202-02-03030 | Removal of Pavement Structure | 990.3 | SQYD | 15.00 | 14,854.50 | 19.00 | 18,815.70 | 20.00 | 19,806.00 | 15.00 | 14,854.50 | | 0003 | 202-02-04501 | Removal of Bridge (Str. No. 625330394902611; STA. 106+07.79; 20' 47' TTTRES) | 940 | LUMP | 45,000.00 | 45,000.00 | 30,000.00 | 30,000.00 | 75,000.00 | 75,000.00 | 20,000.00 | 20,000.00 | | 0004 | 202-02-12000 | Removal of Fence | 276 | LNFT | 13.00 | 3,588.00 | 5.65 | 1,559.40 | 7.00 | 1,932.00 | 10.00 | 2,760.00 | | 0005 | 202-02-32120 | Removal of Pipe (Side Drain) (Side Drain) (15'' Metal) | 18 | LNFT | 80.00 | 1,440.00 | 32.00 | 576.00 | 40.00 | 720.00 | 50.00 | 900.00 | | 0006 | 203-02-00100 | Drainage Excavation | 703 | CUYD | 25.00 | 17,575.00 | 48.00 | 33,744.00 | 40.00 | 28,120.00 | 30.00 | 21,090.00 | | 0007 | 203-05-00100 | Excavation and Embankment | 1 | LUMP | 45,000.00 | 45,000.00 | 55,000.00 | 55,000.00 | 25,000.00 | 25,000.00 | 50,000.00 | 50,000.00 | | 0008 | 204-05-00100 | Temporary Sediment Check Dams (Hay) | 8 | EACH | 200.00 | 1,600.00 | 220.00 | 1,760.00 | 1,000.00 | 8,000.00 | 500.00 | 4,000.00 | | 0009 | 204-06-00100 | Temporary Silt Fencing | 1,152 | LNFT | 2.00 | 2,304.00 | 2.20 | 2,534.40 | 8.00 | 9,216.00 | 5.00 | 5,760.00 | | 0010 | 302-02-08080 | Class II Base Course (8" Thick) (Asphalt Concrete Base) | 1,202.6 | SQYD | 80.00 | 96,208.00 | 83.60 | 100,537.36 | 145.00 | 174,377.00 | 128.00 | 153,932.80 | | 0011 | 304-01-00100 | Lime | 17.05 | TON | 410.00 | 6,990.50 | 330.00 | 5,626.50 | 200.00 | 3,410.00 | 500.00 | 8,525.00 | | 0012 | 304-05-00100 | Lime Treatment (Type E) | 1,203 | SQYD | 13.00 | 15,639.00 | 30.80 | 37,052.40 | 10.00 | 12,030.00 | 20.00 | 24,060.00 | | 0013 | 401-02-00100 | Aggregate Surface Course (Adjusted Vehicular Measurement) | 3 | CUYD | 300.00 | 900.00 | 260.00 | 780.00 | 350.00 | 1,050.00 | 1,000.00 | 3,000.00 | | 0014 | 402-01-00101 | Traffic Maintenance Surfacing (Aggregate) (Vehicular Measurement) | 5 | CUYD | 210.00 | 1,050.00 | 230.00 | 1,150.00 | 350.00 | 1,750.00 | 100.00 | 500.00 | | 0015 | 502-01-00100 | Asphalt Concrete | 248.4 | TON | 225.00 | 55,890.00 | 242.00 | 60,112.80 | 360.00 | 89,424.00 | 350.00 | 86,940.00 | | 0016 | 502-01-00200 | Asphalt Concrete, Drives, Turnouts and Miscellaneous | 42.4 | TON | 400.00 | 16,960.00 | 351.50 | 14,903.60 | 400.00 | 16,960.00 | 400.00 | 16,960.00 | | 0017 | 701-06-00020 | Side Drain Pipe Arch (18" Equiv. RCPA) | 108 | LNFT | 150.00 | 16,200.00 | 140.00 | 15,120.00 | 140.00 | 15,120.00 | 200.00 | 21,600.00 | | 0018 | 702-03-00100 | Catch Basins (CB-01) | 1 | EACH | 13,000.00 | 13,000.00 | 12,500.00 | 12,500.00 | 6,600.00 | 6,600.00 | 5,000.00 | 5,000.00 | | 0019 | 704-03-00200 | Blocked Out Guard Rail - 31", (6'-3" Post Spacing) | 50 | LNFT | 36.00 | 1,800.00 | 24.20 | 1,210.00 | 50.00 | 2,500.00 | 50.00 | 2,500.00 | | 0020 | 704-07-00200 | Guard Rail Transitions (Double Thrie Beam) | 100 | LNFT | 136.00 | 13,600.00 | 100.00 | 10,000.00 | 165.00 | 16,500.00 | 150.00 | 15,000.00 | | 0021 | 704-10-00205 | Guard Rail End Treatment, MASH, (TL-3 Tangent) | 4 | EACH | 4,100.00 | 16,400.00 | 3,275.00 | 13,100.00 | 4,500.00 | 18,000.00 | 5,500.00 | 22,000.00 | | 0022 | 705-01-00100 | Barbed Wire Fence | 521 | LNFT | 16.00 | 8,336.00 | 17.50 | 9,117.50 | 25.00 | 13,025.00 | 25.00 | 13,025.00 | | 0023 | 705-04-00100 | Single Swinging Driveway Gates | 1 | EACH | 1,500.00 | 1,500.00 | 1,650.00 | 1,650.00 | 2,000.00 | 2,000.00 | 2,500.00 | 2,500.00 | | 0024 | 708-01-00100 | Right-of-Way Monument | 12 | EACH | 600.00 | 7,200.00 | 365.00 | 4,380.00 | 900.00 | 10,800.00 | 1,000.00 | 12,000.00 | | 0025 | 708-02-00100 | Right-of-Way Monument Witness Post | 12 | EACH | 200.00 | 2,400.00 | 164.50 | 1,974.00 | 375.00 | 4,500.00 | 300.00 | 3,600.00 | | 0026 | 711-01-04000 | Riprap (55 lb, 18" Thick) | 313 | SQYD | 110.00 | 34,430.00 | 150.85 | 47,216.05 | 135.00 | 42,255.00 | 125.00 | 39,125.00 | | 0027 | 711-04-00100 | Geotextile Fabric | 313 | SQYD | 1.00 | 313.00 | 3.55 | 1,111.15 | 5.00 | 1,565.00 | 5.00 | 1,565.00 | | 0028 | 713-01-00100 | Temporary Signs and Barricades | 1 | LUMP | 135,000.00 | 135,000.00 | 40,000.00 | 40,000.00 | 25,000.00 | 25,000.00 | 20,000.00 | 20,000.00 | | 0029 | 716-01-00100 | Mulch (Vegetative) | 0.1 | TON | 7,500.00 | 750.00 | 8,250.00 | 825.00 | 2,500.00 | 250.00 | 15,000.00 | 1,500.00 | | 0030 | 720-01-01000 | Erosion Control System (Slope Protection) (Type A) | 359 | SQYD | 5.00 | 1,795.00 | 5.50 | 1,974.50 | 10.00 | 3,590.00 | 10.00 | 3,590.00 | | 0031 | 726-01-00100 | Bedding Material | 10.9 | CUYD | 200.00 | 2,180.00 | 197.50 | 2,152.75 | 70.00 | 763.00 | 250.00 | 2,725.00 | | 0032 | 727-01-00100 | Mobilization | 1 | LUMP | 140,000.00 | 140,000.00 | 148,000.00 | 148,000.00 | 141,350.00 | 141,350.00 | 160,000.00 | 160,000.00 | | 0033 | 729-16-00300 | Object Marker Assembly (Type 3) | 4 | EACH | 136.00 | 544.00 | 110.00 | 440.00 | 250.00 | 1,000.00 | 200.00 | 800.00 | | 0034 | 732-03-02000 | Plastic Pavement Striping (Broken Line) (4" Width) (Thermoplastic 90 mil) | 0.102 | MILE | 20,000.00 | 2,040.00 | 22,000.00 | 2,244.00 | 20,000.00 | 2,040.00 | 35,000.00 | 3,570.00 | | 0035 | 739-01-00100 | Hydro-Seeding | 0.47 | ACRE | 7,500.00 | 3,525.00 | 8,200.00 | 3,854.00 | 15,000.00 | 7,050.00 | 10,000.00 | 4,700.00 | | 0036 | 740-01-00100 | Construction Layout | 1 | LUMP | 95,000.00 | 95,000.00 | 25,500.00 | 25,500.00 | 30,000.00 | 30,000.00 | 20,000.00 | 20,000.00 | | 0037 | 804-01-00300 | Precast Concrete Piles (16") | 1,200 | LNFT | 175.00 | 210,000.00 | 170.00 | 204,000.00 | 145.00 | 174,000.00 | 175.00 | 210,000.00 | | 0038 | 805-01-00100 | Class A1 Concrete (Slab Span) | 88.32 | CUYD | 1,600.00 | 141,312.00 | 2,940.00 | 259,660.80 | 2,500.00 | 220,800.00 | 2,850.00 | 251,712.00 | | 0039 | 805-01-00300 | Class A1 Concrete (Bent Cap) | 23.69 | CUYD | 3,100.00 | 73,439.00 | 5,275.00 | 124,964.75 | 2,750.00 | 65,147.50 | 3,500.00 | 82,915.00 | | 0040 | 805-18-00100 | Concrete Finish (Class 2 Rubbed Finish) | 947 | SQFT | 4.00 | 3,788.00 | 1.80 | 1,704.60 | 5.00 | 4,735.00 | 3.00 | 2,841.00 | | 0041 | 805-18-00200 | Concrete Finish (Class 3 Special Finish) | 947 | SQFT | 6.00 | 5,682.00 | 5.50 | 5,208.50 | 5.00 | 4,735.00 | 3.00 | 2,841.00 | | 0042 | 806-01-00100 | Deformed Reinforcing Steel | 23,740 | LB | 1.50 | 35,610.00 | 1.70 | 40,358.00 | 2.10 | 49,854.00 | 2.00 | 47,480.00 | | 0043 | 810-01-00100 | Concrete Bridge Railing (Standard) | 80 | LNFT | 165.00 | 13,200.00 | 270.00 | 21,600.00 | 330.00 | 26,400.00 | 300.00 | 24,000.00 | | 0044 | 810-01-00200 | Concrete Bridge Railing (Slotted) | 80 | LNFT | 215.00 | 17,200.00 | 270.00 | 21,600.00 | 350.00 | 28,000.00 | 315.00 | 25,200.00 | | 0045 | 813-01-00100 | Concrete Approach Slabs (Cast-in-Place) | 500 | SQFT | 120.00 | 60,000.00 | 100.00 | 50,000.00 | 180.00 | 90,000.00 | 125.00 | 62,500.00 | | 0046 | 815-03-00300 | Joint Seal (Poured) | 120 | LNFT | 15.00 | 1,800.00 | 25.00 | 3,000.00 | 15.00 | 1,800.00 | 30.00 | 3,600.00 | | 0047 | NS-500-00340 | Saw Cutting Asphalt Concrete Pavement | 178 | INLF | 10.00 | 1,780.00 | 7.40 | 1,317.20 | 15.00 | 2,670.00 | 16.00 | 2,848.00 | | | | | | | | | | | | | | | | | | CONTRACTOR TOTAL | | | | 1,418,823.00 | | 1,489,934.96 | | 1,528,844.50 | | 1,544,019.30 |
Line Number | Item Number | Item Description | Quantity | Unit of Measure | - 9 - JB JAMES CONSTRUCTION LLC | | Unit Price | Total Amount | | 0001 | 201-01-00100 | Clearing and Grubbing | 0.77 | LUMP | 125,000.00 | 125,000.00 | | 0002 | 202-02-03030 | Removal of Pavement Structure | 990.3 | SQYD | 13.00 | 12,873.90 | | 0003 | 202-02-04501 | Removal of Bridge (Str. No. 625330394902611; STA. 106+07.79; 20' 47' TTTRES) | 940 | LUMP | 62,000.00 | 62,000.00 | | 0004 | 202-02-12000 | Removal of Fence | 276 | LNFT | 2.99 | 825.24 | | 0005 | 202-02-32120 | Removal of Pipe (Side Drain) (Side Drain) (15'' Metal) | 18 | LNFT | 60.00 | 1,080.00 | | 0006 | 203-02-00100 | Drainage Excavation | 703 | CUYD | 30.00 | 21,090.00 | | 0007 | 203-05-00100 | Excavation and Embankment | 1 | LUMP | 55,000.00 | 55,000.00 | | 0008 | 204-05-00100 | Temporary Sediment Check Dams (Hay) | 8 | EACH | 150.00 | 1,200.00 | | 0009 | 204-06-00100 | Temporary Silt Fencing | 1,152 | LNFT | 7.00 | 8,064.00 | | 0010 | 302-02-08080 | Class II Base Course (8" Thick) (Asphalt Concrete Base) | 1,202.6 | SQYD | 77.00 | 92,600.20 | | 0011 | 304-01-00100 | Lime | 17.05 | TON | 300.00 | 5,115.00 | | 0012 | 304-05-00100 | Lime Treatment (Type E) | 1,203 | SQYD | 8.00 | 9,624.00 | | 0013 | 401-02-00100 | Aggregate Surface Course (Adjusted Vehicular Measurement) | 3 | CUYD | 600.00 | 1,800.00 | | 0014 | 402-01-00101 | Traffic Maintenance Surfacing (Aggregate) (Vehicular Measurement) | 5 | CUYD | 300.00 | 1,500.00 | | 0015 | 502-01-00100 | Asphalt Concrete | 248.4 | TON | 260.00 | 64,584.00 | | 0016 | 502-01-00200 | Asphalt Concrete, Drives, Turnouts and Miscellaneous | 42.4 | TON | 410.00 | 17,384.00 | | 0017 | 701-06-00020 | Side Drain Pipe Arch (18" Equiv. RCPA) | 108 | LNFT | 220.00 | 23,760.00 | | 0018 | 702-03-00100 | Catch Basins (CB-01) | 1 | EACH | 6,500.00 | 6,500.00 | | 0019 | 704-03-00200 | Blocked Out Guard Rail - 31", (6'-3" Post Spacing) | 50 | LNFT | 30.00 | 1,500.00 | | 0020 | 704-07-00200 | Guard Rail Transitions (Double Thrie Beam) | 100 | LNFT | 120.00 | 12,000.00 | | 0021 | 704-10-00205 | Guard Rail End Treatment, MASH, (TL-3 Tangent) | 4 | EACH | 3,500.00 | 14,000.00 | | 0022 | 705-01-00100 | Barbed Wire Fence | 521 | LNFT | 13.13 | 6,840.73 | | 0023 | 705-04-00100 | Single Swinging Driveway Gates | 1 | EACH | 1,500.00 | 1,500.00 | | 0024 | 708-01-00100 | Right-of-Way Monument | 12 | EACH | 600.00 | 7,200.00 | | 0025 | 708-02-00100 | Right-of-Way Monument Witness Post | 12 | EACH | 200.00 | 2,400.00 | | 0026 | 711-01-04000 | Riprap (55 lb, 18" Thick) | 313 | SQYD | 115.00 | 35,995.00 | | 0027 | 711-04-00100 | Geotextile Fabric | 313 | SQYD | 6.00 | 1,878.00 | | 0028 | 713-01-00100 | Temporary Signs and Barricades | 1 | LUMP | 70,000.00 | 70,000.00 | | 0029 | 716-01-00100 | Mulch (Vegetative) | 0.1 | TON | 4,290.20 | 429.02 | | 0030 | 720-01-01000 | Erosion Control System (Slope Protection) (Type A) | 359 | SQYD | 1.74 | 624.66 | | 0031 | 726-01-00100 | Bedding Material | 10.9 | CUYD | 200.00 | 2,180.00 | | 0032 | 727-01-00100 | Mobilization | 1 | LUMP | 165,000.00 | 165,000.00 | | 0033 | 729-16-00300 | Object Marker Assembly (Type 3) | 4 | EACH | 80.00 | 320.00 | | 0034 | 732-03-02000 | Plastic Pavement Striping (Broken Line) (4" Width) (Thermoplastic 90 mil) | 0.102 | MILE | 22,000.00 | 2,244.00 | | 0035 | 739-01-00100 | Hydro-Seeding | 0.47 | ACRE | 8,000.00 | 3,760.00 | | 0036 | 740-01-00100 | Construction Layout | 1 | LUMP | 70,000.00 | 70,000.00 | | 0037 | 804-01-00300 | Precast Concrete Piles (16") | 1,200 | LNFT | 240.00 | 288,000.00 | | 0038 | 805-01-00100 | Class A1 Concrete (Slab Span) | 88.32 | CUYD | 2,300.00 | 203,136.00 | | 0039 | 805-01-00300 | Class A1 Concrete (Bent Cap) | 23.69 | CUYD | 3,600.00 | 85,284.00 | | 0040 | 805-18-00100 | Concrete Finish (Class 2 Rubbed Finish) | 947 | SQFT | 1.60 | 1,515.20 | | 0041 | 805-18-00200 | Concrete Finish (Class 3 Special Finish) | 947 | SQFT | 5.00 | 4,735.00 | | 0042 | 806-01-00100 | Deformed Reinforcing Steel | 23,740 | LB | 2.00 | 47,480.00 | | 0043 | 810-01-00100 | Concrete Bridge Railing (Standard) | 80 | LNFT | 260.00 | 20,800.00 | | 0044 | 810-01-00200 | Concrete Bridge Railing (Slotted) | 80 | LNFT | 230.00 | 18,400.00 | | 0045 | 813-01-00100 | Concrete Approach Slabs (Cast-in-Place) | 500 | SQFT | 140.00 | 70,000.00 | | 0046 | 815-03-00300 | Joint Seal (Poured) | 120 | LNFT | 40.00 | 4,800.00 | | 0047 | NS-500-00340 | Saw Cutting Asphalt Concrete Pavement | 178 | INLF | 4.00 | 712.00 | | | | | | | | | | | | CONTRACTOR TOTAL | | | | 1,652,733.95 |
|