Proposal:H.014830.6
Parish:Iberia
Routes:LA 14, LA 674
Description:LA 14 @ LA 674 INTERSECTION IMPROVEMENTS
Type Construction:MILLING ASPHALT PAVEMENT, PAVEMENT PATCHING, CLASS II BASE COURSE, LIME TREATMENT, ASPHALT CONCRETE OVERLAY, AND RELATED WORK.
Estimated Construction Cost:$1,425,758.80
| Rank | License | Bidder | Construction Bid |
| 1 | 52306 | SIEMA CONSTRUCTION, LLC | $1,736,811.79 |
| 2 | 30774 | Progressive Construction Co., LLC | $1,828,814.05 |
| 3 | 33663 | Glenn Lege Construction LLC | $2,276,050.49 |
Line Number | Item Number | Item Description | Quantity | Unit of Measure | - 1 - SIEMA CONSTRUCTION, LLC | - 2 - Progressive Construction Co., LLC | - 3 - Glenn Lege Construction LLC | | Unit Price | Total Amount | Unit Price | Total Amount | Unit Price | Total Amount | | 0001 | 202-01-00100 | Removal of Structures and Obstructions | 1 | LUMP | 45,000.00 | 45,000.00 | 46,287.00 | 46,287.00 | 19,038.50 | 19,038.50 | | 0002 | 202-02-00010 | Removal of Existing Billboard and Posts (Sta. 101+90, 41' RT.) | 1 | EACH | 2,600.00 | 2,600.00 | 1,425.00 | 1,425.00 | 2,297.75 | 2,297.75 | | 0003 | 202-02-06080 | Removal of Concrete Combination Curb and Gutter | 968 | LNFT | 6.35 | 6,146.80 | 16.00 | 15,488.00 | 12.24 | 11,848.32 | | 0004 | 202-02-06100 | Removal of Concrete Walks and Drives | 150 | SQYD | 24.00 | 3,600.00 | 26.00 | 3,900.00 | 29.54 | 4,431.00 | | 0005 | 202-03-38000 | Relocation of Sign (Sta. 100+42, 36' RT.) | 1 | EACH | 405.00 | 405.00 | 584.00 | 584.00 | 407.03 | 407.03 | | 0006 | 202-03-38000 | Relocation of Sign (Sta. 104+55, 34' RT.) | 1 | EACH | 405.00 | 405.00 | 584.00 | 584.00 | 407.03 | 407.03 | | 0007 | 202-03-38000 | Relocation of Sign (State Highway Assembly, Sta. 101+86, 33' RT.) | 1 | EACH | 405.00 | 405.00 | 855.00 | 855.00 | 439.86 | 439.86 | | 0008 | 203-05-00100 | Excavation and Embankment | 1 | LUMP | 25,000.00 | 25,000.00 | 13,925.00 | 13,925.00 | 14,311.70 | 14,311.70 | | 0009 | 204-02-00100 | Temporary Hay Bales | 24 | EACH | 40.00 | 960.00 | 48.00 | 1,152.00 | 29.04 | 696.96 | | 0010 | 204-04-00100 | Temporary Sediment Basins | 3 | EACH | 570.00 | 1,710.00 | 965.00 | 2,895.00 | 174.23 | 522.69 | | 0011 | 204-06-00100 | Temporary Silt Fencing | 1,253 | LNFT | 2.00 | 2,506.00 | 7.00 | 8,771.00 | 2.91 | 3,646.23 | | 0012 | 302-02-08530 | Class II Base Course (8-1/2" Thick) (Asphalt Concrete Base on Embankment Layer) | 450 | SQYD | 116.00 | 52,200.00 | 109.00 | 49,050.00 | 359.53 | 161,788.50 | | 0013 | 303-02-00100 | Removal of Existing Patches | 70 | SQYD | 33.50 | 2,345.00 | 87.00 | 6,090.00 | 87.23 | 6,106.10 | | 0014 | 304-01-00100 | Lime | 8.15 | TON | 405.00 | 3,300.75 | 804.00 | 6,552.60 | 337.05 | 2,746.96 | | 0015 | 304-05-00100 | Lime Treatment (Type E) | 575 | SQYD | 20.00 | 11,500.00 | 33.00 | 18,975.00 | 15.99 | 9,194.25 | | 0016 | 402-01-00101 | Traffic Maintenance Surfacing (Aggregate) (Vehicular Measurement) | 160 | CUYD | 118.00 | 18,880.00 | 148.00 | 23,680.00 | 98.88 | 15,820.80 | | 0017 | 502-01-00100 | Asphalt Concrete | 2,137.5 | TON | 230.00 | 491,625.00 | 210.00 | 448,875.00 | 197.61 | 422,391.38 | | 0018 | 502-01-00200 | Asphalt Concrete, Drives, Turnouts and Miscellaneous | 38.2 | TON | 300.00 | 11,460.00 | 313.00 | 11,956.60 | 372.57 | 14,232.17 | | 0019 | 509-01-00100 | Milling Asphalt Pavement | 6,815 | SQYD | 9.15 | 62,357.25 | 5.00 | 34,075.00 | 23.33 | 158,993.95 | | 0020 | 509-02-00100 | Contractor Retained Reclaimed Asphalt Pavement | -510 | CUYD | 0.01 | -5.10 | 0.01 | -5.10 | 0.01 | -5.10 | | 0021 | 510-01-00200 | Pavement Patching (12" Minimum Thickness) | 1,890 | SQYD | 170.00 | 321,300.00 | 184.00 | 347,760.00 | 167.80 | 317,142.00 | | 0022 | 602-02-00200 | Cleaning and Resealing Existing Longitudinal Pavement Joints | 2,548 | LNFT | 4.50 | 11,466.00 | 8.00 | 20,384.00 | 4.49 | 11,440.52 | | 0023 | 602-02-00300 | Cleaning and Resealing Existing Transverse Pavements Joints | 1,219 | LNFT | 4.50 | 5,485.50 | 9.00 | 10,971.00 | 4.58 | 5,583.02 | | 0024 | 602-03-00100 | Cleaning and Sealing Random Cracks | 300 | LNFT | 9.50 | 2,850.00 | 14.00 | 4,200.00 | 9.68 | 2,904.00 | | 0025 | 602-10-00100 | Longitudinal Shoulder Joints | 373 | LNFT | 9.50 | 3,543.50 | 11.00 | 4,103.00 | 9.52 | 3,550.96 | | 0026 | 701-03-01042 | Storm Drain Pipe (24" RCP/RPVCP) | 316 | LNFT | 165.00 | 52,140.00 | 237.00 | 74,892.00 | 175.82 | 55,559.12 | | 0027 | 702-03-00500 | Catch Basins (CB-06) | 3 | EACH | 6,700.00 | 20,100.00 | 7,408.00 | 22,224.00 | 7,812.35 | 23,437.05 | | 0028 | 702-04-00100 | Adjusting Manholes | 2 | EACH | 2,687.82 | 5,375.64 | 1,985.00 | 3,970.00 | 4,923.75 | 9,847.50 | | 0029 | 702-04-00200 | Adjusting Catch Basins | 4 | EACH | 4,680.00 | 18,720.00 | 4,602.00 | 18,408.00 | 4,529.85 | 18,119.40 | | 0030 | 702-04-00210 | Convert Catch Basins to Manholes | 1 | EACH | 3,385.00 | 3,385.00 | 6,624.00 | 6,624.00 | 8,354.50 | 8,354.50 | | 0031 | 706-01-00100 | Concrete Walk (4" Thick) | 27 | SQYD | 250.00 | 6,750.00 | 185.00 | 4,995.00 | 75.38 | 2,035.26 | | 0032 | 706-02-00200 | Concrete Drive (6" Thick) | 308 | SQYD | 125.00 | 38,500.00 | 158.00 | 48,664.00 | 86.97 | 26,786.76 | | 0033 | 706-03-00300 | Incidental Concrete Paving (6" Thick) | 119 | SQYD | 111.00 | 13,209.00 | 102.00 | 12,138.00 | 86.92 | 10,343.48 | | 0034 | 706-04-00110 | Curb Ramps (Type 7) | 26.6 | SQYD | 211.00 | 5,612.60 | 440.00 | 11,704.00 | 91.04 | 2,421.66 | | 0035 | 707-03-00100 | Combination Concrete Curb and Gutter | 1,017 | LNFT | 33.00 | 33,561.00 | 78.00 | 79,326.00 | 53.61 | 54,521.37 | | 0036 | 713-01-00100 | Temporary Signs and Barricades | 1 | LUMP | 75,000.00 | 75,000.00 | 50,000.00 | 50,000.00 | 253,311.84 | 253,311.84 | | 0037 | 713-02-00500 | Temporary Pavement Markings (24" Width) | 134 | LNFT | 0.50 | 67.00 | 1.00 | 134.00 | 1.16 | 155.44 | | 0038 | 713-03-01000 | Temporary Pavement Markings (Broken Line) (4" Width) (4' Length) | 0.123 | MILE | 17,320.00 | 2,130.36 | 750.00 | 92.25 | 1,313.00 | 161.50 | | 0039 | 713-03-02000 | Temporary Pavement Markings (Broken Line) (4" Width) (10' Length) | 0.43 | MILE | 1,730.00 | 743.90 | 875.00 | 376.25 | 1,161.50 | 499.45 | | 0040 | 713-04-01000 | Temporary Pavement Markings (Solid Line) (4" Width) | 0.907 | MILE | 3,000.00 | 2,721.00 | 1,000.00 | 907.00 | 1,451.88 | 1,316.86 | | 0041 | 713-05-00220 | Temporary Pavement Legends & Symbols (Arrow - Left Turn) | 3 | EACH | 29.00 | 87.00 | 38.00 | 114.00 | 29.04 | 87.12 | | 0042 | 713-05-00230 | Temporary Pavement Legends & Symbols (Arrow - Right Turn) | 2 | EACH | 29.00 | 58.00 | 38.00 | 76.00 | 29.04 | 58.08 | | 0043 | 713-05-00300 | Temporary Pavement Legends & Symbols (ONLY) | 3 | EACH | 29.00 | 87.00 | 38.00 | 114.00 | 29.04 | 87.12 | | 0044 | 722-02-00100 | Project Site Laboratory (Equipped) | 1 | EACH | 27,000.00 | 27,000.00 | 23,697.00 | 23,697.00 | 18,382.00 | 18,382.00 | | 0045 | 726-01-00100 | Bedding Material | 69.9 | CUYD | 140.00 | 9,786.00 | 173.00 | 12,092.70 | 186.10 | 13,008.39 | | 0046 | 727-01-00100 | Mobilization | 1 | LUMP | 170,000.00 | 170,000.00 | 180,000.00 | 180,000.00 | 309,474.10 | 309,474.10 | | 0047 | 731-02-00100 | Reflectorized Raised Pavement Markers | 229 | EACH | 8.00 | 1,832.00 | 5.00 | 1,145.00 | 7.55 | 1,728.95 | | 0048 | 732-01-02080 | Plastic Pavement Striping (24" Width) (Thermoplastic 125 mil) | 288 | LNFT | 21.00 | 6,048.00 | 18.00 | 5,184.00 | 12.78 | 3,680.64 | | 0049 | 732-02-02000 | Plastic Pavement Striping (Solid Line) (4" Width) (Thermoplastic 90 mil) | 0.859 | MILE | 8,675.00 | 7,451.83 | 8,750.00 | 7,516.25 | 7,549.75 | 6,485.24 | | 0050 | 732-02-02040 | Plastic Pavement Striping (Solid Line) (8" Width) (Thermoplastic 90 mil) | 0.06 | MILE | 29,000.00 | 1,740.00 | 16,250.00 | 975.00 | 15,680.25 | 940.82 | | 0051 | 732-03-02000 | Plastic Pavement Striping (Broken Line) (4" Width) (Thermoplastic 90 mil) | 0.43 | MILE | 1,735.00 | 746.05 | 3,750.00 | 1,612.50 | 4,413.70 | 1,897.89 | | 0052 | 732-03-02010 | Plastic Pavement Striping (Dotted Line)(4" W)(2' L)(Thermo 90 mil) | 0.03 | MILE | 12,125.00 | 363.75 | 1,750.00 | 52.50 | 4,936.38 | 148.09 | | 0053 | 732-03-02030 | Plastic Pavement Striping (Dotted Line)(8" W)(2' L)(Thermo 90 mil) | 0.084 | MILE | 14,500.00 | 1,218.00 | 3,250.00 | 273.00 | 11,034.25 | 926.88 | | 0054 | 732-04-01080 | Plastic Pavement Legends and Symbols (Arrow - Left Turn) | 3 | EACH | 462.00 | 1,386.00 | 344.00 | 1,032.00 | 348.45 | 1,045.35 | | 0055 | 732-04-01100 | Plastic Pavement Legends and Symbols (Arrow - Right Turn) | 2 | EACH | 462.00 | 924.00 | 344.00 | 688.00 | 348.45 | 696.90 | | 0056 | 732-04-15020 | Plastic Pavement Legends and Symbols (ONLY) | 3 | EACH | 575.00 | 1,725.00 | 375.00 | 1,125.00 | 464.60 | 1,393.80 | | 0057 | 732-05-00100 | Removal of Existing Markings | 0.238 | MILE | 17,320.00 | 4,122.16 | 3,750.00 | 892.50 | 9,872.75 | 2,349.71 | | 0058 | 739-01-00100 | Hydro-Seeding | 0.15 | ACRE | 0.35 | 0.05 | 25,000.00 | 3,750.00 | 17,422.50 | 2,613.38 | | 0059 | 740-01-00100 | Construction Layout | 1 | LUMP | 8,000.00 | 8,000.00 | 20,000.00 | 20,000.00 | 166,094.50 | 166,094.50 | | 0060 | NS-500-00180 | Roadway Reinforcing Mesh (Complete Road System) | 7,871 | SQYD | 13.00 | 102,323.00 | 15.00 | 118,065.00 | 8.87 | 69,815.77 | | 0061 | NS-500-00340 | Saw Cutting Asphalt Concrete Pavement | 644 | INLF | 3.00 | 1,932.00 | 6.00 | 3,864.00 | 0.79 | 508.76 | | 0062 | NS-500-00360 | Saw Cutting Asphalt Concrete Pavement Over Portland Cement Concrete Composite Pavement | 11,009 | INLF | 1.75 | 19,265.75 | 2.00 | 22,018.00 | 1.17 | 12,880.53 | | 0063 | NS-600-00220 | Saw Cutting Portland Cement Concrete Pavement | 3,770 | INLF | 1.50 | 5,655.00 | 2.00 | 7,540.00 | 1.31 | 4,938.70 | | | | | | | | | | | | | | | | CONTRACTOR TOTAL | | | | 1,736,811.79 | | 1,828,814.05 | | 2,276,050.49 |
|