Proposal:H.014243.6
Parish:Grant
Routes:LA 472
Description:LA 472: INDIAN & BIG BEAR CREEK BRS
Type Construction:CLEARING AND GRUBBING, REMOVAL OF PRECAST BRIDGES, GRADING, LIME TREATMENT, CLASS II BASE COURSE, PAVEMENT PATCHING, PRECAST CONCRETE PILES, CONCRETE SLAB SPAN BRIDGES, ASPHALT CONCRETE, AND RELATED WORK.
Estimated Construction Cost:$4,598,284.00
| Rank | License | Bidder | Construction Bid |
| 1 | 55505 | MERRICK, LLC | $4,295,638.70 |
| 2 | 12487 | Diamond B Construction Co., L.L.C. | $4,355,598.45 |
| 3 | 01516 | Elevate Heavy Civil Construction, LLC | $4,395,144.10 |
| 4 | 12312 | Gilchrist Construction Company, LLC | $4,674,059.45 |
| 5 | 56994 | Matt L. Guinn Construction, LLC | $4,920,695.72 |
| 6 | 49239 | WL Bass Construction Inc. | $4,982,039.10 |
| 7 | 39462 | JB JAMES CONSTRUCTION LLC | $5,148,726.58 |
| 8 | 27239 | Apeck Construction, LLC | $5,183,581.03 |
| 9 | 00044 | Guinn Construction, LLC | $5,293,997.75 |
Line Number | Item Number | Item Description | Quantity | Unit of Measure | - 1 - MERRICK, LLC | - 2 - Diamond B Construction Co., L.L.C. | - 3 - Elevate Heavy Civil Construction, LLC | - 4 - Gilchrist Construction Company, LLC | | Unit Price | Total Amount | Unit Price | Total Amount | Unit Price | Total Amount | Unit Price | Total Amount | | 0001 | 201-01-00100 | Clearing and Grubbing | 2.57 | LUMP | 50,000.00 | 50,000.00 | 33,000.00 | 33,000.00 | 250,000.00 | 250,000.00 | 137,000.00 | 137,000.00 | | 0002 | 202-02-03030 | Removal of Pavement Structure | 1,967.8 | SQYD | 9.00 | 17,710.20 | 7.00 | 13,774.60 | 10.00 | 19,678.00 | 17.00 | 33,452.60 | | 0003 | 202-02-04501 | Removal of Bridge Str. No. 082203650105021 (126' x 22' Precast Bridge) | 2,772 | LUMP | 70,000.00 | 70,000.00 | 30,000.00 | 30,000.00 | 100,000.00 | 100,000.00 | 90,000.00 | 90,000.00 | | 0004 | 202-02-04501 | Removal of Bridge Str. No. 082203650107901 (105' x 22' Precast Bridge) | 2,310 | LUMP | 70,000.00 | 70,000.00 | 30,000.00 | 30,000.00 | 87,350.00 | 87,350.00 | 90,000.00 | 90,000.00 | | 0005 | 202-02-14500 | Removal of Guard Rail | 514.9 | LNFT | 12.00 | 6,178.80 | 25.00 | 12,872.50 | 10.00 | 5,149.00 | 9.00 | 4,634.10 | | 0006 | 203-02-00100 | Drainage Excavation | 5,605 | CUYD | 18.00 | 100,890.00 | 15.00 | 84,075.00 | 8.00 | 44,840.00 | 20.00 | 112,100.00 | | 0007 | 203-05-00100 | Excavation and Embankment | 1 | LUMP | 70,000.00 | 70,000.00 | 45,000.00 | 45,000.00 | 80,000.00 | 80,000.00 | 75,000.00 | 75,000.00 | | 0008 | 204-05-00100 | Temporary Sediment Check Dams (Hay) | 16 | EACH | 185.00 | 2,960.00 | 150.00 | 2,400.00 | 160.00 | 2,560.00 | 32.00 | 512.00 | | 0009 | 204-06-00100 | Temporary Silt Fencing | 797 | LNFT | 3.50 | 2,789.50 | 3.00 | 2,391.00 | 4.00 | 3,188.00 | 5.00 | 3,985.00 | | 0010 | 302-02-04010 | Class II Base Course (4" Thick) (Asphalt Concrete Base) | 2,063.5 | SQYD | 35.00 | 72,222.50 | 28.00 | 57,778.00 | 46.00 | 94,921.00 | 45.00 | 92,857.50 | | 0011 | 304-01-00100 | Lime | 7.32 | TON | 400.00 | 2,928.00 | 1,200.00 | 8,784.00 | 400.00 | 2,928.00 | 525.00 | 3,843.00 | | 0012 | 304-05-00100 | Lime Treatment (Type E) | 517 | SQYD | 4.00 | 2,068.00 | 23.00 | 11,891.00 | 14.00 | 7,238.00 | 55.00 | 28,435.00 | | 0013 | 401-02-00100 | Aggregate Surface Course (Adjusted Vehicular Measurement) | 5 | CUYD | 180.00 | 900.00 | 185.00 | 925.00 | 500.00 | 2,500.00 | 400.00 | 2,000.00 | | 0014 | 402-01-00101 | Traffic Maintenance Surfacing (Aggregate) (Vehicular Measurement) | 25 | CUYD | 140.00 | 3,500.00 | 80.00 | 2,000.00 | 215.00 | 5,375.00 | 150.00 | 3,750.00 | | 0015 | 502-01-00100 | Asphalt Concrete | 458.6 | TON | 250.00 | 114,650.00 | 325.00 | 149,045.00 | 220.00 | 100,892.00 | 300.00 | 137,580.00 | | 0016 | 502-01-00200 | Asphalt Concrete, Drives, Turnouts and Miscellaneous | 155.3 | TON | 325.00 | 50,472.50 | 400.00 | 62,120.00 | 270.00 | 41,931.00 | 300.00 | 46,590.00 | | 0017 | 510-01-00001 | Pavement Patching (14.5" minimum thickness) | 132 | SQYD | 270.00 | 35,640.00 | 150.00 | 19,800.00 | 215.00 | 28,380.00 | 275.00 | 36,300.00 | | 0018 | 701-05-02067 | Side Drain Pipe (Erosion) (24" RPVCP/CPEPDW/CPPPDW) | 50 | LNFT | 135.00 | 6,750.00 | 165.00 | 8,250.00 | 120.00 | 6,000.00 | 225.00 | 11,250.00 | | 0019 | 704-03-00200 | Blocked Out Guard Rail - 31", (6'-3" Post Spacing) | 337.6 | LNFT | 32.00 | 10,803.20 | 35.00 | 11,816.00 | 30.00 | 10,128.00 | 30.00 | 10,128.00 | | 0020 | 704-07-00200 | Guard Rail Transitions (Double Thrie Beam) | 200 | LNFT | 130.00 | 26,000.00 | 135.00 | 27,000.00 | 116.00 | 23,200.00 | 118.00 | 23,600.00 | | 0021 | 704-10-00205 | Guard Rail End Treatment, MASH, (TL-3 Tangent) | 8 | EACH | 4,000.00 | 32,000.00 | 4,000.00 | 32,000.00 | 3,400.00 | 27,200.00 | 3,400.00 | 27,200.00 | | 0022 | 708-01-00100 | Right-of-Way Monument | 11 | EACH | 650.00 | 7,150.00 | 600.00 | 6,600.00 | 600.00 | 6,600.00 | 650.00 | 7,150.00 | | 0023 | 708-02-00100 | Right-of-Way Monument Witness Post | 11 | EACH | 220.00 | 2,420.00 | 200.00 | 2,200.00 | 200.00 | 2,200.00 | 250.00 | 2,750.00 | | 0024 | 711-03-00400 | Riprap (55 lb) | 1,380 | TON | 84.00 | 115,920.00 | 85.00 | 117,300.00 | 96.00 | 132,480.00 | 90.00 | 124,200.00 | | 0025 | 711-03-00500 | Riprap (130 lb) | 2,080 | TON | 84.00 | 174,720.00 | 89.00 | 185,120.00 | 92.00 | 191,360.00 | 90.00 | 187,200.00 | | 0026 | 711-04-00100 | Geotextile Fabric | 3,335 | SQYD | 3.00 | 10,005.00 | 1.00 | 3,335.00 | 2.00 | 6,670.00 | 3.50 | 11,672.50 | | 0027 | 713-01-00100 | Temporary Signs and Barricades | 1 | LUMP | 70,000.00 | 70,000.00 | 110,000.00 | 110,000.00 | 75,000.00 | 75,000.00 | 100,000.00 | 100,000.00 | | 0028 | 713-04-01020 | Temporary Pavement Markings (Solid Line) (4"Width) (Type 1 Removable) | 0.846 | MILE | 7,000.00 | 5,922.00 | 6,500.00 | 5,499.00 | 21,000.00 | 17,766.00 | 6,500.00 | 5,499.00 | | 0029 | 713-06-00100 | Temporary Reflectorized Raised Pavement Markers | 52 | EACH | 8.00 | 416.00 | 6.00 | 312.00 | 25.00 | 1,300.00 | 6.00 | 312.00 | | 0030 | 720-01-02020 | Erosion Control System, Flexible (Channel Liner) (Type D) | 56 | SQYD | 7.00 | 392.00 | 5.00 | 280.00 | 6.00 | 336.00 | 6.25 | 350.00 | | 0031 | 720-01-02060 | Erosion Control System, Flexible (Channel Liner) (Type F) | 111 | SQYD | 7.00 | 777.00 | 5.00 | 555.00 | 4.00 | 444.00 | 4.25 | 471.75 | | 0032 | 724-02-00100 | Rumble Strips (Shoulder/Edge) | 0.272 | MILE | 15,000.00 | 4,080.00 | 1,000.00 | 272.00 | 450.00 | 122.40 | 1,000.00 | 272.00 | | 0033 | 727-01-00100 | Mobilization | 1 | LUMP | 420,000.00 | 420,000.00 | 392,000.00 | 392,000.00 | 440,000.00 | 440,000.00 | 460,000.00 | 460,000.00 | | 0034 | 729-16-00300 | Object Marker Assembly (Type 3) | 8 | EACH | 100.00 | 800.00 | 135.00 | 1,080.00 | 85.00 | 680.00 | 90.00 | 720.00 | | 0035 | 731-01-00100 | Nonreflectorized Raised Pavement Markers | 688 | EACH | 10.00 | 6,880.00 | 9.00 | 6,192.00 | 15.00 | 10,320.00 | 9.00 | 6,192.00 | | 0036 | 731-02-00100 | Reflectorized Raised Pavement Markers | 52 | EACH | 7.00 | 364.00 | 6.00 | 312.00 | 25.00 | 1,300.00 | 6.25 | 325.00 | | 0037 | 732-02-02000 | Plastic Pavement Striping (Solid Line) (4" Width) (Thermoplastic 90 mil) | 0.812 | MILE | 7,000.00 | 5,684.00 | 6,000.00 | 4,872.00 | 15,000.00 | 12,180.00 | 6,000.00 | 4,872.00 | | 0038 | 732-03-02000 | Plastic Pavement Striping (Broken Line) (4" Width) (Thermoplastic 90 mil) | 0.035 | MILE | 3,000.00 | 105.00 | 2,500.00 | 87.50 | 17,200.00 | 602.00 | 2,500.00 | 87.50 | | 0039 | 735-01-00100 | Mailboxes | 1 | EACH | 100.00 | 100.00 | 25.00 | 25.00 | 10.00 | 10.00 | 1.00 | 1.00 | | 0040 | 735-02-00100 | Mailbox Supports (Single) | 1 | EACH | 350.00 | 350.00 | 300.00 | 300.00 | 300.00 | 300.00 | 425.00 | 425.00 | | 0041 | 739-01-00100 | Hydro-Seeding | 2.57 | ACRE | 3,200.00 | 8,224.00 | 2,800.00 | 7,196.00 | 2,850.00 | 7,324.50 | 3,000.00 | 7,710.00 | | 0042 | 740-01-00100 | Construction Layout | 1 | LUMP | 65,000.00 | 65,000.00 | 38,500.00 | 38,500.00 | 75,000.00 | 75,000.00 | 80,000.00 | 80,000.00 | | 0043 | 804-01-00400 | Precast Concrete Piles (18") | 5,620 | LNFT | 152.00 | 854,240.00 | 178.00 | 1,000,360.00 | 138.00 | 775,560.00 | 150.00 | 843,000.00 | | 0044 | 805-01-00100 | Class A1 Concrete (Slab Span) | 482.4 | CUYD | 1,500.00 | 723,600.00 | 1,575.00 | 759,780.00 | 1,350.00 | 651,240.00 | 1,400.00 | 675,360.00 | | 0045 | 805-01-00300 | Class A1 Concrete (Bent Cap) | 140.35 | CUYD | 2,700.00 | 378,945.00 | 2,500.00 | 350,875.00 | 2,600.00 | 364,910.00 | 2,500.00 | 350,875.00 | | 0046 | 805-18-00100 | Concrete Finish (Class 2 Rubbed Finish) | 4,378 | SQFT | 3.00 | 13,134.00 | 3.00 | 13,134.00 | 2.00 | 8,756.00 | 3.00 | 13,134.00 | | 0047 | 805-18-00200 | Concrete Finish (Class 3 Special Finish) | 4,378 | SQFT | 4.00 | 17,512.00 | 3.00 | 13,134.00 | 3.00 | 13,134.00 | 3.00 | 13,134.00 | | 0048 | 806-01-00100 | Deformed Reinforcing Steel | 119,073 | LB | 2.00 | 238,146.00 | 1.45 | 172,655.85 | 1.40 | 166,702.20 | 1.50 | 178,609.50 | | 0049 | 810-01-00120 | Concrete Bridge Railing (36 inch Height) | 640 | LNFT | 165.00 | 105,600.00 | 175.00 | 112,000.00 | 210.00 | 134,400.00 | 230.00 | 147,200.00 | | 0050 | 813-01-00100 | Concrete Approach Slabs (Cast-in-Place) | 2,400 | SQFT | 98.00 | 235,200.00 | 105.00 | 252,000.00 | 115.00 | 276,000.00 | 160.00 | 384,000.00 | | 0051 | 814-01-00100 | Elastomeric Bearing Pads (Non-Reinforced) | 384 | SFIN | 160.00 | 61,440.00 | 150.00 | 57,600.00 | 110.00 | 42,240.00 | 90.00 | 34,560.00 | | 0052 | 815-03-00300 | Joint Seal (Poured) | 558 | LNFT | 15.00 | 8,370.00 | 45.00 | 25,110.00 | 18.00 | 10,044.00 | 50.00 | 27,900.00 | | 0053 | NS-500-00240 | Sawing and Sealing Transverse Joints in Asphalt Concrete Overlay | 360 | LNFT | 12.00 | 4,320.00 | 10.00 | 3,600.00 | 9.50 | 3,420.00 | 11.00 | 3,960.00 | | 0054 | NS-500-00260 | Sawcuts in Asphalt Concrete Lifts | 600 | LNFT | 3.00 | 1,800.00 | 5.00 | 3,000.00 | 4.50 | 2,700.00 | 5.00 | 3,000.00 | | 0055 | NS-500-00340 | Saw Cutting Asphalt Concrete Pavement | 390 | INLF | 4.00 | 1,560.00 | 1.00 | 390.00 | 1.50 | 585.00 | 10.00 | 3,900.00 | | 0056 | NS-719-00002 | Tree Trimming | 1 | LUMP | 4,000.00 | 4,000.00 | 65,000.00 | 65,000.00 | 20,000.00 | 20,000.00 | 25,000.00 | 25,000.00 | | | | | | | | | | | | | | | | | | CONTRACTOR TOTAL | | | | 4,295,638.70 | | 4,355,598.45 | | 4,395,144.10 | | 4,674,059.45 |
Line Number | Item Number | Item Description | Quantity | Unit of Measure | - 5 - Matt L. Guinn Construction, LLC | - 6 - WL Bass Construction Inc. | - 7 - JB JAMES CONSTRUCTION LLC | - 8 - Apeck Construction, LLC | | Unit Price | Total Amount | Unit Price | Total Amount | Unit Price | Total Amount | Unit Price | Total Amount | | 0001 | 201-01-00100 | Clearing and Grubbing | 2.57 | LUMP | 85,000.00 | 85,000.00 | 230,000.00 | 230,000.00 | 400,000.00 | 400,000.00 | 437,261.65 | 437,261.65 | | 0002 | 202-02-03030 | Removal of Pavement Structure | 1,967.8 | SQYD | 14.00 | 27,549.20 | 13.00 | 25,581.40 | 21.00 | 41,323.80 | 22.17 | 43,626.13 | | 0003 | 202-02-04501 | Removal of Bridge Str. No. 082203650105021 (126' x 22' Precast Bridge) | 2,772 | LUMP | 55,000.00 | 55,000.00 | 120,000.00 | 120,000.00 | 110,000.00 | 110,000.00 | 68,294.79 | 68,294.79 | | 0004 | 202-02-04501 | Removal of Bridge Str. No. 082203650107901 (105' x 22' Precast Bridge) | 2,310 | LUMP | 55,000.00 | 55,000.00 | 100,000.00 | 100,000.00 | 55,000.00 | 55,000.00 | 68,294.79 | 68,294.79 | | 0005 | 202-02-14500 | Removal of Guard Rail | 514.9 | LNFT | 7.00 | 3,604.30 | 12.00 | 6,178.80 | 11.00 | 5,663.90 | 22.19 | 11,425.63 | | 0006 | 203-02-00100 | Drainage Excavation | 5,605 | CUYD | 33.50 | 187,767.50 | 18.00 | 100,890.00 | 27.00 | 151,335.00 | 25.33 | 141,974.65 | | 0007 | 203-05-00100 | Excavation and Embankment | 1 | LUMP | 75,000.00 | 75,000.00 | 137,500.00 | 137,500.00 | 100,000.00 | 100,000.00 | 42,514.90 | 42,514.90 | | 0008 | 204-05-00100 | Temporary Sediment Check Dams (Hay) | 16 | EACH | 150.00 | 2,400.00 | 150.00 | 2,400.00 | 30.00 | 480.00 | 178.83 | 2,861.28 | | 0009 | 204-06-00100 | Temporary Silt Fencing | 797 | LNFT | 3.00 | 2,391.00 | 5.00 | 3,985.00 | 9.00 | 7,173.00 | 4.77 | 3,801.69 | | 0010 | 302-02-04010 | Class II Base Course (4" Thick) (Asphalt Concrete Base) | 2,063.5 | SQYD | 53.50 | 110,397.25 | 65.00 | 134,127.50 | 46.00 | 94,921.00 | 60.30 | 124,429.05 | | 0011 | 304-01-00100 | Lime | 7.32 | TON | 1.00 | 7.32 | 370.00 | 2,708.40 | 500.00 | 3,660.00 | 615.64 | 4,506.48 | | 0012 | 304-05-00100 | Lime Treatment (Type E) | 517 | SQYD | 10.00 | 5,170.00 | 7.00 | 3,619.00 | 22.00 | 11,374.00 | 30.60 | 15,820.20 | | 0013 | 401-02-00100 | Aggregate Surface Course (Adjusted Vehicular Measurement) | 5 | CUYD | 200.00 | 1,000.00 | 125.00 | 625.00 | 375.00 | 1,875.00 | 154.98 | 774.90 | | 0014 | 402-01-00101 | Traffic Maintenance Surfacing (Aggregate) (Vehicular Measurement) | 25 | CUYD | 225.00 | 5,625.00 | 100.00 | 2,500.00 | 250.00 | 6,250.00 | 154.98 | 3,874.50 | | 0015 | 502-01-00100 | Asphalt Concrete | 458.6 | TON | 300.00 | 137,580.00 | 220.00 | 100,892.00 | 220.00 | 100,892.00 | 296.16 | 135,818.98 | | 0016 | 502-01-00200 | Asphalt Concrete, Drives, Turnouts and Miscellaneous | 155.3 | TON | 350.00 | 54,355.00 | 270.00 | 41,931.00 | 270.00 | 41,931.00 | 282.78 | 43,915.73 | | 0017 | 510-01-00001 | Pavement Patching (14.5" minimum thickness) | 132 | SQYD | 235.00 | 31,020.00 | 230.00 | 30,360.00 | 215.00 | 28,380.00 | 277.45 | 36,623.40 | | 0018 | 701-05-02067 | Side Drain Pipe (Erosion) (24" RPVCP/CPEPDW/CPPPDW) | 50 | LNFT | 145.00 | 7,250.00 | 140.00 | 7,000.00 | 175.00 | 8,750.00 | 190.60 | 9,530.00 | | 0019 | 704-03-00200 | Blocked Out Guard Rail - 31", (6'-3" Post Spacing) | 337.6 | LNFT | 45.00 | 15,192.00 | 30.00 | 10,128.00 | 29.50 | 9,959.20 | 41.73 | 14,088.05 | | 0020 | 704-07-00200 | Guard Rail Transitions (Double Thrie Beam) | 200 | LNFT | 135.00 | 27,000.00 | 116.00 | 23,200.00 | 116.00 | 23,200.00 | 160.95 | 32,190.00 | | 0021 | 704-10-00205 | Guard Rail End Treatment, MASH, (TL-3 Tangent) | 8 | EACH | 4,300.00 | 34,400.00 | 3,350.00 | 26,800.00 | 3,350.00 | 26,800.00 | 4,768.75 | 38,150.00 | | 0022 | 708-01-00100 | Right-of-Way Monument | 11 | EACH | 650.00 | 7,150.00 | 300.00 | 3,300.00 | 600.00 | 6,600.00 | 715.31 | 7,868.41 | | 0023 | 708-02-00100 | Right-of-Way Monument Witness Post | 11 | EACH | 400.00 | 4,400.00 | 200.00 | 2,200.00 | 200.00 | 2,200.00 | 238.44 | 2,622.84 | | 0024 | 711-03-00400 | Riprap (55 lb) | 1,380 | TON | 130.00 | 179,400.00 | 107.00 | 147,660.00 | 100.00 | 138,000.00 | 84.67 | 116,844.60 | | 0025 | 711-03-00500 | Riprap (130 lb) | 2,080 | TON | 140.00 | 291,200.00 | 115.00 | 239,200.00 | 105.00 | 218,400.00 | 88.45 | 183,976.00 | | 0026 | 711-04-00100 | Geotextile Fabric | 3,335 | SQYD | 4.00 | 13,340.00 | 5.00 | 16,675.00 | 3.00 | 10,005.00 | 3.44 | 11,472.40 | | 0027 | 713-01-00100 | Temporary Signs and Barricades | 1 | LUMP | 45,000.00 | 45,000.00 | 200,000.00 | 200,000.00 | 110,000.00 | 110,000.00 | 61,338.02 | 61,338.02 | | 0028 | 713-04-01020 | Temporary Pavement Markings (Solid Line) (4"Width) (Type 1 Removable) | 0.846 | MILE | 6,500.00 | 5,499.00 | 6,500.00 | 5,499.00 | 6,530.00 | 5,524.38 | 7,785.85 | 6,586.83 | | 0029 | 713-06-00100 | Temporary Reflectorized Raised Pavement Markers | 52 | EACH | 8.00 | 416.00 | 6.00 | 312.00 | 6.00 | 312.00 | 7.15 | 371.80 | | 0030 | 720-01-02020 | Erosion Control System, Flexible (Channel Liner) (Type D) | 56 | SQYD | 50.00 | 2,800.00 | 3.00 | 168.00 | 6.00 | 336.00 | 3.58 | 200.48 | | 0031 | 720-01-02060 | Erosion Control System, Flexible (Channel Liner) (Type F) | 111 | SQYD | 55.00 | 6,105.00 | 3.00 | 333.00 | 4.00 | 444.00 | 3.58 | 397.38 | | 0032 | 724-02-00100 | Rumble Strips (Shoulder/Edge) | 0.272 | MILE | 10,000.00 | 2,720.00 | 400.00 | 108.80 | 1,000.00 | 272.00 | 1,227.24 | 333.81 | | 0033 | 727-01-00100 | Mobilization | 1 | LUMP | 400,000.00 | 400,000.00 | 498,000.00 | 498,000.00 | 515,000.00 | 515,000.00 | 113,055.61 | 113,055.61 | | 0034 | 729-16-00300 | Object Marker Assembly (Type 3) | 8 | EACH | 150.00 | 1,200.00 | 85.00 | 680.00 | 85.00 | 680.00 | 160.95 | 1,287.60 | | 0035 | 731-01-00100 | Nonreflectorized Raised Pavement Markers | 688 | EACH | 12.00 | 8,256.00 | 8.50 | 5,848.00 | 8.50 | 5,848.00 | 10.13 | 6,969.44 | | 0036 | 731-02-00100 | Reflectorized Raised Pavement Markers | 52 | EACH | 50.00 | 2,600.00 | 6.00 | 312.00 | 6.00 | 312.00 | 7.15 | 371.80 | | 0037 | 732-02-02000 | Plastic Pavement Striping (Solid Line) (4" Width) (Thermoplastic 90 mil) | 0.812 | MILE | 8,000.00 | 6,496.00 | 5,850.00 | 4,750.20 | 5,900.00 | 4,790.80 | 7,043.00 | 5,718.92 | | 0038 | 732-03-02000 | Plastic Pavement Striping (Broken Line) (4" Width) (Thermoplastic 90 mil) | 0.035 | MILE | 10,000.00 | 350.00 | 2,900.00 | 101.50 | 3,300.00 | 115.50 | 3,951.14 | 138.29 | | 0039 | 735-01-00100 | Mailboxes | 1 | EACH | 200.00 | 200.00 | 40.00 | 40.00 | 20.00 | 20.00 | 1.19 | 1.19 | | 0040 | 735-02-00100 | Mailbox Supports (Single) | 1 | EACH | 200.00 | 200.00 | 150.00 | 150.00 | 250.00 | 250.00 | 834.53 | 834.53 | | 0041 | 739-01-00100 | Hydro-Seeding | 2.57 | ACRE | 3,000.00 | 7,710.00 | 3,100.00 | 7,967.00 | 2,800.00 | 7,196.00 | 3,695.78 | 9,498.15 | | 0042 | 740-01-00100 | Construction Layout | 1 | LUMP | 35,000.00 | 35,000.00 | 75,000.00 | 75,000.00 | 75,000.00 | 75,000.00 | 14,348.39 | 14,348.39 | | 0043 | 804-01-00400 | Precast Concrete Piles (18") | 5,620 | LNFT | 150.00 | 843,000.00 | 220.00 | 1,236,400.00 | 190.00 | 1,067,800.00 | 167.83 | 943,204.60 | | 0044 | 805-01-00100 | Class A1 Concrete (Slab Span) | 482.4 | CUYD | 2,150.00 | 1,037,160.00 | 350.00 | 168,840.00 | 1,500.00 | 723,600.00 | 2,478.10 | 1,195,435.44 | | 0045 | 805-01-00300 | Class A1 Concrete (Bent Cap) | 140.35 | CUYD | 2,800.00 | 392,980.00 | 350.00 | 49,122.50 | 2,400.00 | 336,840.00 | 3,320.93 | 466,092.53 | | 0046 | 805-18-00100 | Concrete Finish (Class 2 Rubbed Finish) | 4,378 | SQFT | 2.00 | 8,756.00 | 1.00 | 4,378.00 | 1.50 | 6,567.00 | 3.74 | 16,373.72 | | 0047 | 805-18-00200 | Concrete Finish (Class 3 Special Finish) | 4,378 | SQFT | 2.00 | 8,756.00 | 2.00 | 8,756.00 | 3.50 | 15,323.00 | 3.74 | 16,373.72 | | 0048 | 806-01-00100 | Deformed Reinforcing Steel | 119,073 | LB | 1.55 | 184,563.15 | 4.00 | 476,292.00 | 1.50 | 178,609.50 | 1.35 | 160,748.55 | | 0049 | 810-01-00120 | Concrete Bridge Railing (36 inch Height) | 640 | LNFT | 250.00 | 160,000.00 | 250.00 | 160,000.00 | 180.00 | 115,200.00 | 255.92 | 163,788.80 | | 0050 | 813-01-00100 | Concrete Approach Slabs (Cast-in-Place) | 2,400 | SQFT | 115.00 | 276,000.00 | 200.00 | 480,000.00 | 120.00 | 288,000.00 | 121.50 | 291,600.00 | | 0051 | 814-01-00100 | Elastomeric Bearing Pads (Non-Reinforced) | 384 | SFIN | 125.00 | 48,000.00 | 135.00 | 51,840.00 | 100.00 | 38,400.00 | 164.55 | 63,187.20 | | 0052 | 815-03-00300 | Joint Seal (Poured) | 558 | LNFT | 20.00 | 11,160.00 | 15.00 | 8,370.00 | 22.00 | 12,276.00 | 24.96 | 13,927.68 | | 0053 | NS-500-00240 | Sawing and Sealing Transverse Joints in Asphalt Concrete Overlay | 360 | LNFT | 10.00 | 3,600.00 | 12.00 | 4,320.00 | 10.00 | 3,600.00 | 14.31 | 5,151.60 | | 0054 | NS-500-00260 | Sawcuts in Asphalt Concrete Lifts | 600 | LNFT | 3.00 | 1,800.00 | 1.00 | 600.00 | 1.25 | 750.00 | 2.38 | 1,428.00 | | 0055 | NS-500-00340 | Saw Cutting Asphalt Concrete Pavement | 390 | INLF | 3.00 | 1,170.00 | 1.00 | 390.00 | 1.25 | 487.50 | 2.38 | 928.20 | | 0056 | NS-719-00002 | Tree Trimming | 1 | LUMP | 1,000.00 | 1,000.00 | 14,000.00 | 14,000.00 | 31,000.00 | 31,000.00 | 21,327.70 | 21,327.70 | | | | | | | | | | | | | | | | | | CONTRACTOR TOTAL | | | | 4,920,695.72 | | 4,982,039.10 | | 5,148,726.58 | | 5,183,581.03 |
Line Number | Item Number | Item Description | Quantity | Unit of Measure | - 9 - Guinn Construction, LLC | | Unit Price | Total Amount | | 0001 | 201-01-00100 | Clearing and Grubbing | 2.57 | LUMP | 90,000.00 | 90,000.00 | | 0002 | 202-02-03030 | Removal of Pavement Structure | 1,967.8 | SQYD | 15.00 | 29,517.00 | | 0003 | 202-02-04501 | Removal of Bridge Str. No. 082203650105021 (126' x 22' Precast Bridge) | 2,772 | LUMP | 60,000.00 | 60,000.00 | | 0004 | 202-02-04501 | Removal of Bridge Str. No. 082203650107901 (105' x 22' Precast Bridge) | 2,310 | LUMP | 55,000.00 | 55,000.00 | | 0005 | 202-02-14500 | Removal of Guard Rail | 514.9 | LNFT | 10.00 | 5,149.00 | | 0006 | 203-02-00100 | Drainage Excavation | 5,605 | CUYD | 30.00 | 168,150.00 | | 0007 | 203-05-00100 | Excavation and Embankment | 1 | LUMP | 75,000.00 | 75,000.00 | | 0008 | 204-05-00100 | Temporary Sediment Check Dams (Hay) | 16 | EACH | 500.00 | 8,000.00 | | 0009 | 204-06-00100 | Temporary Silt Fencing | 797 | LNFT | 4.00 | 3,188.00 | | 0010 | 302-02-04010 | Class II Base Course (4" Thick) (Asphalt Concrete Base) | 2,063.5 | SQYD | 60.00 | 123,810.00 | | 0011 | 304-01-00100 | Lime | 7.32 | TON | 1,000.00 | 7,320.00 | | 0012 | 304-05-00100 | Lime Treatment (Type E) | 517 | SQYD | 60.00 | 31,020.00 | | 0013 | 401-02-00100 | Aggregate Surface Course (Adjusted Vehicular Measurement) | 5 | CUYD | 500.00 | 2,500.00 | | 0014 | 402-01-00101 | Traffic Maintenance Surfacing (Aggregate) (Vehicular Measurement) | 25 | CUYD | 100.00 | 2,500.00 | | 0015 | 502-01-00100 | Asphalt Concrete | 458.6 | TON | 350.00 | 160,510.00 | | 0016 | 502-01-00200 | Asphalt Concrete, Drives, Turnouts and Miscellaneous | 155.3 | TON | 400.00 | 62,120.00 | | 0017 | 510-01-00001 | Pavement Patching (14.5" minimum thickness) | 132 | SQYD | 350.00 | 46,200.00 | | 0018 | 701-05-02067 | Side Drain Pipe (Erosion) (24" RPVCP/CPEPDW/CPPPDW) | 50 | LNFT | 150.00 | 7,500.00 | | 0019 | 704-03-00200 | Blocked Out Guard Rail - 31", (6'-3" Post Spacing) | 337.6 | LNFT | 40.00 | 13,504.00 | | 0020 | 704-07-00200 | Guard Rail Transitions (Double Thrie Beam) | 200 | LNFT | 150.00 | 30,000.00 | | 0021 | 704-10-00205 | Guard Rail End Treatment, MASH, (TL-3 Tangent) | 8 | EACH | 4,750.00 | 38,000.00 | | 0022 | 708-01-00100 | Right-of-Way Monument | 11 | EACH | 850.00 | 9,350.00 | | 0023 | 708-02-00100 | Right-of-Way Monument Witness Post | 11 | EACH | 400.00 | 4,400.00 | | 0024 | 711-03-00400 | Riprap (55 lb) | 1,380 | TON | 115.00 | 158,700.00 | | 0025 | 711-03-00500 | Riprap (130 lb) | 2,080 | TON | 125.00 | 260,000.00 | | 0026 | 711-04-00100 | Geotextile Fabric | 3,335 | SQYD | 5.00 | 16,675.00 | | 0027 | 713-01-00100 | Temporary Signs and Barricades | 1 | LUMP | 25,000.00 | 25,000.00 | | 0028 | 713-04-01020 | Temporary Pavement Markings (Solid Line) (4"Width) (Type 1 Removable) | 0.846 | MILE | 12,000.00 | 10,152.00 | | 0029 | 713-06-00100 | Temporary Reflectorized Raised Pavement Markers | 52 | EACH | 10.00 | 520.00 | | 0030 | 720-01-02020 | Erosion Control System, Flexible (Channel Liner) (Type D) | 56 | SQYD | 25.00 | 1,400.00 | | 0031 | 720-01-02060 | Erosion Control System, Flexible (Channel Liner) (Type F) | 111 | SQYD | 35.00 | 3,885.00 | | 0032 | 724-02-00100 | Rumble Strips (Shoulder/Edge) | 0.272 | MILE | 2,000.00 | 544.00 | | 0033 | 727-01-00100 | Mobilization | 1 | LUMP | 495,000.00 | 495,000.00 | | 0034 | 729-16-00300 | Object Marker Assembly (Type 3) | 8 | EACH | 200.00 | 1,600.00 | | 0035 | 731-01-00100 | Nonreflectorized Raised Pavement Markers | 688 | EACH | 12.00 | 8,256.00 | | 0036 | 731-02-00100 | Reflectorized Raised Pavement Markers | 52 | EACH | 8.00 | 416.00 | | 0037 | 732-02-02000 | Plastic Pavement Striping (Solid Line) (4" Width) (Thermoplastic 90 mil) | 0.812 | MILE | 8,000.00 | 6,496.00 | | 0038 | 732-03-02000 | Plastic Pavement Striping (Broken Line) (4" Width) (Thermoplastic 90 mil) | 0.035 | MILE | 5,000.00 | 175.00 | | 0039 | 735-01-00100 | Mailboxes | 1 | EACH | 200.00 | 200.00 | | 0040 | 735-02-00100 | Mailbox Supports (Single) | 1 | EACH | 200.00 | 200.00 | | 0041 | 739-01-00100 | Hydro-Seeding | 2.57 | ACRE | 2,500.00 | 6,425.00 | | 0042 | 740-01-00100 | Construction Layout | 1 | LUMP | 40,000.00 | 40,000.00 | | 0043 | 804-01-00400 | Precast Concrete Piles (18") | 5,620 | LNFT | 160.00 | 899,200.00 | | 0044 | 805-01-00100 | Class A1 Concrete (Slab Span) | 482.4 | CUYD | 2,250.00 | 1,085,400.00 | | 0045 | 805-01-00300 | Class A1 Concrete (Bent Cap) | 140.35 | CUYD | 3,000.00 | 421,050.00 | | 0046 | 805-18-00100 | Concrete Finish (Class 2 Rubbed Finish) | 4,378 | SQFT | 3.00 | 13,134.00 | | 0047 | 805-18-00200 | Concrete Finish (Class 3 Special Finish) | 4,378 | SQFT | 3.00 | 13,134.00 | | 0048 | 806-01-00100 | Deformed Reinforcing Steel | 119,073 | LB | 1.75 | 208,377.75 | | 0049 | 810-01-00120 | Concrete Bridge Railing (36 inch Height) | 640 | LNFT | 300.00 | 192,000.00 | | 0050 | 813-01-00100 | Concrete Approach Slabs (Cast-in-Place) | 2,400 | SQFT | 115.00 | 276,000.00 | | 0051 | 814-01-00100 | Elastomeric Bearing Pads (Non-Reinforced) | 384 | SFIN | 165.00 | 63,360.00 | | 0052 | 815-03-00300 | Joint Seal (Poured) | 558 | LNFT | 20.00 | 11,160.00 | | 0053 | NS-500-00240 | Sawing and Sealing Transverse Joints in Asphalt Concrete Overlay | 360 | LNFT | 25.00 | 9,000.00 | | 0054 | NS-500-00260 | Sawcuts in Asphalt Concrete Lifts | 600 | LNFT | 10.00 | 6,000.00 | | 0055 | NS-500-00340 | Saw Cutting Asphalt Concrete Pavement | 390 | INLF | 20.00 | 7,800.00 | | 0056 | NS-719-00002 | Tree Trimming | 1 | LUMP | 20,000.00 | 20,000.00 | | | | | | | | | | | | CONTRACTOR TOTAL | | | | 5,293,997.75 |
|