Proposal:H.016137.6
Parish:Lafourche, Terrebonne
Routes:LA 3185
Description:LA 3185: LA 1 - LA 20
Type Construction:GRADING, MILLING ASPHALT CONCRETE, PAVEMENT PATCHING, ASPHALT CONCRETE OVERLAY, AND RELATED WORK.
Estimated Construction Cost:$3,942,090.15
| Rank | License | Bidder | Construction Bid |
| 1 | 62139 | Huey P. Stockstill, LLC | $2,741,956.75 |
| 2 | 00046 | Barber Bros. Contracting Co., L.L.C | $3,196,577.81 |
| 3 | 06276 | Barriere Construction Co., LLC | $3,357,222.00 |
| 4 | 46747 | Triumph Construction, LLC | $4,134,647.21 |
Line Number | Item Number | Item Description | Quantity | Unit of Measure | - 1 - Huey P. Stockstill, LLC | - 2 - Barber Bros. Contracting Co., L.L.C | - 3 - Barriere Construction Co., LLC | - 4 - Triumph Construction, LLC | | Unit Price | Total Amount | Unit Price | Total Amount | Unit Price | Total Amount | Unit Price | Total Amount | | 0001 | 202-02-14500 | Removal of Guard Rail | 909.5 | LNFT | 9.50 | 8,640.25 | 10.00 | 9,095.00 | 10.00 | 9,095.00 | 11.00 | 10,004.50 | | 0002 | 202-02-38240 | Removal of Signs and Supports | 51 | EACH | 10.00 | 510.00 | 10.50 | 535.50 | 26.00 | 1,326.00 | 76.00 | 3,876.00 | | 0003 | 203-03-00100 | Embankment | 34.4 | CUYD | 65.00 | 2,236.00 | 150.00 | 5,160.00 | 102.00 | 3,508.80 | 31.00 | 1,066.40 | | 0004 | 203-07-00100 | Borrow (Vehicular Measurement) | 490 | CUYD | 35.00 | 17,150.00 | 60.00 | 29,400.00 | 20.00 | 9,800.00 | 70.00 | 34,300.00 | | 0005 | 502-01-00100 | Asphalt Concrete | 11,553.2 | TON | 110.00 | 1,270,852.00 | 120.00 | 1,386,384.00 | 131.00 | 1,513,469.20 | 174.00 | 2,010,256.80 | | 0006 | 502-01-00200 | Asphalt Concrete, Drives, Turnouts and Miscellaneous | 1,135 | TON | 225.00 | 255,375.00 | 185.00 | 209,975.00 | 235.00 | 266,725.00 | 174.00 | 197,490.00 | | 0007 | 509-01-00100 | Milling Asphalt Pavement | 110,438 | SQYD | 1.00 | 110,438.00 | 4.00 | 441,752.00 | 3.75 | 414,142.50 | 7.00 | 773,066.00 | | 0008 | 509-02-00100 | Contractor Retained Reclaimed Asphalt Pavement | -6,136 | CUYD | 0.01 | -61.36 | 0.00 | 0.00 | 4.00 | -24,544.00 | 0.06 | -368.16 | | 0009 | 510-01-00260 | Pavement Patching (16 inch Minimum Thickness) | 2,700 | SQYD | 108.00 | 291,600.00 | 165.00 | 445,500.00 | 152.00 | 410,400.00 | 44.00 | 118,800.00 | | 0010 | 701-10-01060 | Reinforced Concrete Pipe (Extension) (24") | 42 | LNFT | 475.00 | 19,950.00 | 370.00 | 15,540.00 | 475.00 | 19,950.00 | 83.00 | 3,486.00 | | 0011 | 701-15-00100 | Concrete Collar | 3 | EACH | 4,000.00 | 12,000.00 | 3,000.00 | 9,000.00 | 6,400.00 | 19,200.00 | 187.00 | 561.00 | | 0012 | 704-01-01000 | Guard Rail (Single Thrie Beam) (3'-1 1/2" post spacing) | 269.1 | LNFT | 55.00 | 14,800.50 | 57.00 | 15,338.70 | 57.00 | 15,338.70 | 84.00 | 22,604.40 | | 0013 | 704-01-01020 | Guard Rail (Single Thrie Beam) (6'-3" post spacing) | 342 | LNFT | 130.00 | 44,460.00 | 132.50 | 45,315.00 | 135.00 | 46,170.00 | 191.00 | 65,322.00 | | 0014 | 704-03-00200 | Blocked Out Guard Rail - 31", (6'-3" Post Spacing) | 331.3 | LNFT | 30.00 | 9,939.00 | 31.00 | 10,270.30 | 31.00 | 10,270.30 | 35.00 | 11,595.50 | | 0015 | 704-10-00105 | Guard Rail End Treatment (Flared, 12' - 6" Length) | 8 | EACH | 1,800.00 | 14,400.00 | 2,000.00 | 16,000.00 | 1,900.00 | 15,200.00 | 4,615.00 | 36,920.00 | | 0016 | 704-10-00204 | Guard Rail End Treatment, MASH, (TL-2 Tangent) | 2 | EACH | 4,350.00 | 8,700.00 | 4,500.00 | 9,000.00 | 4,600.00 | 9,200.00 | 3,290.00 | 6,580.00 | | 0017 | 704-10-00205 | Guard Rail End Treatment, MASH, (TL-3 Tangent) | 6 | EACH | 4,500.00 | 27,000.00 | 4,800.00 | 28,800.00 | 4,800.00 | 28,800.00 | 3,924.00 | 23,544.00 | | 0018 | 713-01-00100 | Temporary Signs and Barricades | 1 | LUMP | 95,000.00 | 95,000.00 | 95,000.00 | 95,000.00 | 155,000.00 | 155,000.00 | 26,520.00 | 26,520.00 | | 0019 | 713-02-00300 | Temporary Pavement Markings (8" Width) | 660 | LNFT | 0.15 | 99.00 | 0.20 | 132.00 | 0.15 | 99.00 | 2.00 | 1,320.00 | | 0020 | 713-02-00500 | Temporary Pavement Markings (24" Width) | 282 | LNFT | 0.25 | 70.50 | 0.25 | 70.50 | 0.25 | 70.50 | 4.00 | 1,128.00 | | 0021 | 713-03-01000 | Temporary Pavement Markings (Broken Line) (4" Width) (4' Length) | 8.292 | MILE | 165.00 | 1,368.18 | 600.00 | 4,975.20 | 660.00 | 5,472.72 | 671.00 | 5,563.93 | | 0022 | 713-03-02000 | Temporary Pavement Markings (Broken Line) (4" Width) (10' Length) | 8.292 | MILE | 600.00 | 4,975.20 | 650.00 | 5,389.80 | 600.00 | 4,975.20 | 786.00 | 6,517.51 | | 0023 | 713-04-01000 | Temporary Pavement Markings (Solid Line) (4" Width) | 29.112 | MILE | 900.00 | 26,200.80 | 900.00 | 26,200.80 | 900.00 | 26,200.80 | 835.00 | 24,308.52 | | 0024 | 713-05-00190 | Temporary Pavement Legends & Symbols (Arrow - Straight) | 4 | EACH | 25.00 | 100.00 | 35.00 | 140.00 | 25.00 | 100.00 | 235.00 | 940.00 | | 0025 | 713-05-00220 | Temporary Pavement Legends & Symbols (Arrow - Left Turn) | 4 | EACH | 25.00 | 100.00 | 35.00 | 140.00 | 25.00 | 100.00 | 235.00 | 940.00 | | 0026 | 713-05-00230 | Temporary Pavement Legends & Symbols (Arrow - Right Turn) | 8 | EACH | 25.00 | 200.00 | 35.00 | 280.00 | 25.00 | 200.00 | 138.00 | 1,104.00 | | 0027 | 716-01-00100 | Mulch (Vegetative) | 2.5 | TON | 1,750.00 | 4,375.00 | 1,750.00 | 4,375.00 | 1,800.00 | 4,500.00 | 2,016.00 | 5,040.00 | | 0028 | 717-01-00100 | Seeding | 75 | LB | 5.00 | 375.00 | 11.50 | 862.50 | 11.50 | 862.50 | 14.00 | 1,050.00 | | 0029 | 718-01-00100 | Fertilizer | 1,250 | LB | 0.75 | 937.50 | 1.00 | 1,250.00 | 1.05 | 1,312.50 | 2.00 | 2,500.00 | | 0030 | 724-01-00100 | Rumble Strips (Centerline) | 5.24 | MILE | 650.00 | 3,406.00 | 300.00 | 1,572.00 | 290.00 | 1,519.60 | 567.00 | 2,971.08 | | 0031 | 724-02-00100 | Rumble Strips (Shoulder/Edge) | 10.48 | MILE | 505.00 | 5,292.40 | 300.00 | 3,144.00 | 290.00 | 3,039.20 | 445.00 | 4,663.60 | | 0032 | 726-01-00100 | Bedding Material | 9.2 | CUYD | 210.00 | 1,932.00 | 135.00 | 1,242.00 | 415.00 | 3,818.00 | 68.00 | 625.60 | | 0033 | 727-01-00100 | Mobilization | 1 | LUMP | 270,000.00 | 270,000.00 | 135,000.00 | 135,000.00 | 165,000.00 | 165,000.00 | 380,920.00 | 380,920.00 | | 0034 | 729-01-00102 | Sign (Type A)(Furnish and Install) | 110 | SQFT | 20.00 | 2,200.00 | 21.00 | 2,310.00 | 26.00 | 2,860.00 | 41.00 | 4,510.00 | | 0035 | 729-16-00300 | Object Marker Assembly (Type 3) | 45 | EACH | 100.00 | 4,500.00 | 105.00 | 4,725.00 | 105.00 | 4,725.00 | 99.00 | 4,455.00 | | 0036 | 729-22-00100 | Square Tubing Post with 2-1/4" Anchor | 16 | EACH | 150.00 | 2,400.00 | 160.00 | 2,560.00 | 155.00 | 2,480.00 | 203.00 | 3,248.00 | | 0037 | 731-02-00100 | Reflectorized Raised Pavement Markers | 3,393 | EACH | 4.50 | 15,268.50 | 4.75 | 16,116.75 | 4.75 | 16,116.75 | 5.00 | 16,965.00 | | 0038 | 732-01-01040 | Plastic Pavement Striping (8" Width) (Thermoplastic 90 mil) | 330 | LNFT | 4.00 | 1,320.00 | 4.00 | 1,320.00 | 4.15 | 1,369.50 | 6.00 | 1,980.00 | | 0039 | 732-01-02080 | Plastic Pavement Striping (24" Width) (Thermoplastic 125 mil) | 141 | LNFT | 16.00 | 2,256.00 | 16.25 | 2,291.25 | 16.50 | 2,326.50 | 20.00 | 2,820.00 | | 0040 | 732-02-02000 | Plastic Pavement Striping (Solid Line) (4" Width) (Thermoplastic 90 mil) | 14.556 | MILE | 4,300.00 | 62,590.80 | 4,305.00 | 62,663.58 | 4,450.00 | 64,774.20 | 5,821.00 | 84,730.48 | | 0041 | 732-03-02000 | Plastic Pavement Striping (Broken Line) (4" Width) (Thermoplastic 90 mil) | 4.146 | MILE | 1,200.00 | 4,975.20 | 1,205.00 | 4,995.93 | 1,250.00 | 5,182.50 | 1,918.00 | 7,952.03 | | 0042 | 732-03-02030 | Plastic Pavement Striping (Dotted Line)(8" W)(2' L)(Thermo 90 mil) | 0.072 | MILE | 9,240.00 | 665.28 | 9,250.00 | 666.00 | 10,000.00 | 720.00 | 11,667.00 | 840.02 | | 0043 | 732-04-01020 | Plastic Pavement Legends and Symbols (Arrow - Straight) | 2 | EACH | 350.00 | 700.00 | 375.00 | 750.00 | 355.00 | 710.00 | 675.00 | 1,350.00 | | 0044 | 732-04-01080 | Plastic Pavement Legends and Symbols (Arrow - Left Turn) | 2 | EACH | 350.00 | 700.00 | 375.00 | 750.00 | 355.00 | 710.00 | 705.00 | 1,410.00 | | 0045 | 732-04-01100 | Plastic Pavement Legends and Symbols (Arrow - Right Turn) | 4 | EACH | 350.00 | 1,400.00 | 375.00 | 1,500.00 | 355.00 | 1,420.00 | 510.00 | 2,040.00 | | 0046 | 732-04-15020 | Plastic Pavement Legends and Symbols (ONLY) | 4 | EACH | 450.00 | 1,800.00 | 475.00 | 1,900.00 | 465.00 | 1,860.00 | 540.00 | 2,160.00 | | 0047 | 735-01-00100 | Mailboxes | 46 | EACH | 50.00 | 2,300.00 | 55.00 | 2,530.00 | 1.00 | 46.00 | 24.00 | 1,104.00 | | 0048 | 735-02-00100 | Mailbox Supports (Single) | 46 | EACH | 150.00 | 6,900.00 | 165.00 | 7,590.00 | 210.00 | 9,660.00 | 289.00 | 13,294.00 | | 0049 | 740-01-00100 | Construction Layout | 1 | LUMP | 8,250.00 | 8,250.00 | 12,500.00 | 12,500.00 | 5,286.03 | 5,286.03 | 11,540.00 | 11,540.00 | | 0050 | NS-500-00220 | Sawing and Sealing Longitudinal Joints in Asphalt Concrete Overlay | 15,820 | LNFT | 1.50 | 23,730.00 | 2.25 | 35,595.00 | 1.95 | 30,849.00 | 3.00 | 47,460.00 | | 0051 | NS-500-00240 | Sawing and Sealing Transverse Joints in Asphalt Concrete Overlay | 6,650 | LNFT | 1.55 | 10,307.50 | 2.50 | 16,625.00 | 2.00 | 13,300.00 | 3.00 | 19,950.00 | | 0052 | NS-500-00260 | Sawcuts in Asphalt Concrete Lifts | 22,450 | LNFT | 1.05 | 23,572.50 | 1.00 | 22,450.00 | 0.90 | 20,205.00 | 2.00 | 44,900.00 | | 0053 | NS-830-00100 | Concrete Bridge Railing Repair and Rehabilitation | 38 | LNFT | 1,150.00 | 43,700.00 | 1,050.00 | 39,900.00 | 850.00 | 32,300.00 | 2,019.00 | 76,722.00 | | | | | | | | | | | | | | | | | | CONTRACTOR TOTAL | | | | 2,741,956.75 | | 3,196,577.81 | | 3,357,222.00 | | 4,134,647.21 |
|