Proposal:H.015853.6
Parish:Lafayette
Description:TEE MA ROAD SIDEWALKS CARENCRO
Type Construction:GRADING, DRAINAGE STRUCTURES, PAVEMENT PATCHING, SIDEWALK, CURB RAMPS, AND RELATED WORK.
Estimated Construction Cost:$422,070.00
| Rank | License | Bidder | Construction Bid |
| 1 | 46747 | Triumph Construction, LLC | $254,169.00 |
| 2 | 67770 | Reliant Industrial Solutions L.L.C. | $389,396.96 |
| 3 | 30774 | Progressive Construction Co., LLC | $414,527.50 |
| 4 | 54206 | Southern Constructors, LLC | $430,065.00 |
| 5 | 39001 | JD's Rebar & Construction, Inc. | $483,203.80 |
Line Number | Item Number | Item Description | Quantity | Unit of Measure | - 1 - Triumph Construction, LLC | - 2 - Reliant Industrial Solutions L.L.C. | - 3 - Progressive Construction Co., LLC | - 4 - Southern Constructors, LLC | | Unit Price | Total Amount | Unit Price | Total Amount | Unit Price | Total Amount | Unit Price | Total Amount | | 0001 | 202-02-06100 | Removal of Concrete Walks and Drives | 75 | SQYD | 60.00 | 4,500.00 | 88.50 | 6,637.50 | 25.00 | 1,875.00 | 65.00 | 4,875.00 | | 0002 | 202-02-06140 | Removal of Curbs (Concrete) | 41 | LNFT | 10.00 | 410.00 | 54.00 | 2,214.00 | 30.00 | 1,230.00 | 100.00 | 4,100.00 | | 0003 | 202-02-12000 | Removal of Fence | 140 | LNFT | 9.00 | 1,260.00 | 8.60 | 1,204.00 | 30.00 | 4,200.00 | 50.00 | 7,000.00 | | 0004 | 202-02-14000 | Removal of Gas Line | 297 | LNFT | 18.00 | 5,346.00 | 33.00 | 9,801.00 | 25.00 | 7,425.00 | 100.00 | 29,700.00 | | 0005 | 202-02-32120 | Removal of Pipe (Side Drain) (10" RCP) | 33 | LNFT | 24.00 | 792.00 | 63.00 | 2,079.00 | 75.00 | 2,475.00 | 100.00 | 3,300.00 | | 0006 | 202-02-32120 | Removal of Pipe (Side Drain) (12" RCP) | 50 | LNFT | 16.00 | 800.00 | 71.50 | 3,575.00 | 75.00 | 3,750.00 | 100.00 | 5,000.00 | | 0007 | 202-02-32120 | Removal of Pipe (Side Drain) (15" CPP) | 24 | LNFT | 32.00 | 768.00 | 89.50 | 2,148.00 | 75.00 | 1,800.00 | 100.00 | 2,400.00 | | 0008 | 202-02-32120 | Removal of Pipe (Side Drain) (15" RCP) | 6 | LNFT | 127.00 | 762.00 | 200.00 | 1,200.00 | 75.00 | 450.00 | 100.00 | 600.00 | | 0009 | 202-03-38000 | Relocation of Sign | 2 | EACH | 175.00 | 350.00 | 180.00 | 360.00 | 455.00 | 910.00 | 1,000.00 | 2,000.00 | | 0010 | 203-05-00100 | Excavation and Embankment | 1 | LUMP | 18,480.00 | 18,480.00 | 12,500.00 | 12,500.00 | 50,000.00 | 50,000.00 | 30,000.00 | 30,000.00 | | 0011 | 204-02-00100 | Temporary Hay Bales | 40 | EACH | 32.00 | 1,280.00 | 33.00 | 1,320.00 | 55.00 | 2,200.00 | 50.00 | 2,000.00 | | 0012 | 204-06-00100 | Temporary Silt Fencing | 522 | LNFT | 7.00 | 3,654.00 | 5.40 | 2,818.80 | 8.00 | 4,176.00 | 5.00 | 2,610.00 | | 0013 | 510-01-00100 | Pavement Patching (6" Minimum Thickness) | 56 | SQYD | 159.00 | 8,904.00 | 278.50 | 15,596.00 | 250.00 | 14,000.00 | 350.00 | 19,600.00 | | 0014 | 701-03-01002 | Storm Drain Pipe (15" RCP/RPVCP) | 511 | LNFT | 42.00 | 21,462.00 | 92.50 | 47,267.50 | 100.00 | 51,100.00 | 140.00 | 71,540.00 | | 0015 | 701-15-00100 | Concrete Collar | 2 | EACH | 185.00 | 370.00 | 1,350.00 | 2,700.00 | 1,500.00 | 3,000.00 | 1,500.00 | 3,000.00 | | 0016 | 705-09-00100 | Rebuilt Fence | 140 | LNFT | 60.00 | 8,400.00 | 62.50 | 8,750.00 | 35.00 | 4,900.00 | 85.00 | 11,900.00 | | 0017 | 706-01-00100 | Concrete Walk (4" Thick) | 295.8 | SQYD | 60.00 | 17,748.00 | 125.00 | 36,975.00 | 135.00 | 39,933.00 | 125.00 | 36,975.00 | | 0018 | 706-02-00200 | Concrete Drive (6" Thick) | 57.4 | SQYD | 92.00 | 5,280.80 | 221.40 | 12,708.36 | 265.00 | 15,211.00 | 150.00 | 8,610.00 | | 0019 | 706-04-00110 | Curb Ramps (TYPE 1) | 12.8 | SQYD | 187.00 | 2,393.60 | 380.00 | 4,864.00 | 425.00 | 5,440.00 | 500.00 | 6,400.00 | | 0020 | 706-04-00110 | Curb Ramps (TYPE 3) | 32.4 | SQYD | 104.00 | 3,369.60 | 355.00 | 11,502.00 | 425.00 | 13,770.00 | 500.00 | 16,200.00 | | 0021 | 713-01-00100 | Temporary Signs and Barricades | 1 | LUMP | 8,590.00 | 8,590.00 | 60,000.00 | 60,000.00 | 30,000.00 | 30,000.00 | 30,000.00 | 30,000.00 | | 0022 | 717-01-00100 | Seeding | 4 | LB | 15.00 | 60.00 | 13.50 | 54.00 | 100.00 | 400.00 | 500.00 | 2,000.00 | | 0023 | 718-01-00100 | Fertilizer | 90 | LB | 20.00 | 1,800.00 | 19.65 | 1,768.50 | 4.00 | 360.00 | 35.00 | 3,150.00 | | 0024 | 726-01-00100 | Bedding Material | 52.5 | CUYD | 68.00 | 3,570.00 | 245.00 | 12,862.50 | 175.00 | 9,187.50 | 150.00 | 7,875.00 | | 0025 | 727-01-00100 | Mobilization | 1 | LUMP | 57,330.00 | 57,330.00 | 32,000.00 | 32,000.00 | 40,000.00 | 40,000.00 | 30,000.00 | 30,000.00 | | 0026 | 735-01-00100 | Mailboxes | 2 | EACH | 25.00 | 50.00 | 24.00 | 48.00 | 135.00 | 270.00 | 350.00 | 700.00 | | 0027 | 735-02-00100 | Mailbox Supports (Single) | 2 | EACH | 290.00 | 580.00 | 330.00 | 660.00 | 300.00 | 600.00 | 350.00 | 700.00 | | 0028 | 740-01-00100 | Construction Layout | 1 | LUMP | 7,500.00 | 7,500.00 | 8,500.00 | 8,500.00 | 35,000.00 | 35,000.00 | 7,500.00 | 7,500.00 | | 0029 | 741-35-00100 | Adjust Valve or Meter Box (Water Valve and Meter) | 3 | EACH | 847.00 | 2,541.00 | 950.00 | 2,850.00 | 750.00 | 2,250.00 | 2,000.00 | 6,000.00 | | 0030 | NS-201-00021 | Stump Removal (Under 36" Diameter) | 1 | EACH | 3,700.00 | 3,700.00 | 2,000.00 | 2,000.00 | 1,100.00 | 1,100.00 | 5,000.00 | 5,000.00 | | 0031 | NS-600-00220 | Saw Cutting Portland Cement Concrete Pavement | 283 | INLF | 6.00 | 1,698.00 | 8.60 | 2,433.80 | 5.00 | 1,415.00 | 10.00 | 2,830.00 | | 0032 | NS-MSC-00008 | Construction Photographs And Video | 1 | LUMP | 5,040.00 | 5,040.00 | 1,500.00 | 1,500.00 | 1,100.00 | 1,100.00 | 1,500.00 | 1,500.00 | | 0033 | TS-MSC-00120 | Drainage Structure (DROP INLET CATCH BASIN) | 10 | EACH | 5,538.00 | 55,380.00 | 7,850.00 | 78,500.00 | 6,500.00 | 65,000.00 | 6,500.00 | 65,000.00 | | | | | | | | | | | | | | | | | | CONTRACTOR TOTAL | | | | 254,169.00 | | 389,396.96 | | 414,527.50 | | 430,065.00 |
Line Number | Item Number | Item Description | Quantity | Unit of Measure | - 5 - JD's Rebar & Construction, Inc. | | Unit Price | Total Amount | | 0001 | 202-02-06100 | Removal of Concrete Walks and Drives | 75 | SQYD | 60.00 | 4,500.00 | | 0002 | 202-02-06140 | Removal of Curbs (Concrete) | 41 | LNFT | 46.00 | 1,886.00 | | 0003 | 202-02-12000 | Removal of Fence | 140 | LNFT | 24.00 | 3,360.00 | | 0004 | 202-02-14000 | Removal of Gas Line | 297 | LNFT | 12.00 | 3,564.00 | | 0005 | 202-02-32120 | Removal of Pipe (Side Drain) (10" RCP) | 33 | LNFT | 53.00 | 1,749.00 | | 0006 | 202-02-32120 | Removal of Pipe (Side Drain) (12" RCP) | 50 | LNFT | 69.00 | 3,450.00 | | 0007 | 202-02-32120 | Removal of Pipe (Side Drain) (15" CPP) | 24 | LNFT | 145.00 | 3,480.00 | | 0008 | 202-02-32120 | Removal of Pipe (Side Drain) (15" RCP) | 6 | LNFT | 217.00 | 1,302.00 | | 0009 | 202-03-38000 | Relocation of Sign | 2 | EACH | 867.00 | 1,734.00 | | 0010 | 203-05-00100 | Excavation and Embankment | 1 | LUMP | 21,000.00 | 21,000.00 | | 0011 | 204-02-00100 | Temporary Hay Bales | 40 | EACH | 84.00 | 3,360.00 | | 0012 | 204-06-00100 | Temporary Silt Fencing | 522 | LNFT | 9.00 | 4,698.00 | | 0013 | 510-01-00100 | Pavement Patching (6" Minimum Thickness) | 56 | SQYD | 222.00 | 12,432.00 | | 0014 | 701-03-01002 | Storm Drain Pipe (15" RCP/RPVCP) | 511 | LNFT | 110.00 | 56,210.00 | | 0015 | 701-15-00100 | Concrete Collar | 2 | EACH | 2,057.00 | 4,114.00 | | 0016 | 705-09-00100 | Rebuilt Fence | 140 | LNFT | 91.00 | 12,740.00 | | 0017 | 706-01-00100 | Concrete Walk (4" Thick) | 295.8 | SQYD | 98.00 | 28,988.40 | | 0018 | 706-02-00200 | Concrete Drive (6" Thick) | 57.4 | SQYD | 126.00 | 7,232.40 | | 0019 | 706-04-00110 | Curb Ramps (TYPE 1) | 12.8 | SQYD | 241.00 | 3,084.80 | | 0020 | 706-04-00110 | Curb Ramps (TYPE 3) | 32.4 | SQYD | 178.00 | 5,767.20 | | 0021 | 713-01-00100 | Temporary Signs and Barricades | 1 | LUMP | 6,500.00 | 6,500.00 | | 0022 | 717-01-00100 | Seeding | 4 | LB | 213.00 | 852.00 | | 0023 | 718-01-00100 | Fertilizer | 90 | LB | 6.00 | 540.00 | | 0024 | 726-01-00100 | Bedding Material | 52.5 | CUYD | 142.00 | 7,455.00 | | 0025 | 727-01-00100 | Mobilization | 1 | LUMP | 240,000.00 | 240,000.00 | | 0026 | 735-01-00100 | Mailboxes | 2 | EACH | 106.00 | 212.00 | | 0027 | 735-02-00100 | Mailbox Supports (Single) | 2 | EACH | 266.00 | 532.00 | | 0028 | 740-01-00100 | Construction Layout | 1 | LUMP | 8,000.00 | 8,000.00 | | 0029 | 741-35-00100 | Adjust Valve or Meter Box (Water Valve and Meter) | 3 | EACH | 893.00 | 2,679.00 | | 0030 | NS-201-00021 | Stump Removal (Under 36" Diameter) | 1 | EACH | 3,253.00 | 3,253.00 | | 0031 | NS-600-00220 | Saw Cutting Portland Cement Concrete Pavement | 283 | INLF | 3.00 | 849.00 | | 0032 | NS-MSC-00008 | Construction Photographs And Video | 1 | LUMP | 10,000.00 | 10,000.00 | | 0033 | TS-MSC-00120 | Drainage Structure (DROP INLET CATCH BASIN) | 10 | EACH | 1,768.00 | 17,680.00 | | | | | | | | | | | | CONTRACTOR TOTAL | | | | 483,203.80 |
|