Proposal:H.014253.6
Parish:West Feliciana
Routes:LA 421
Description:LA 421: THOM CREEK BRIDGE
Type Construction:CLEARING AND GRUBBING, REMOVAL OF TIMBER TRESTLE BRIDGE, GRADING, DRAINAGE STRUCTURES, MILLING ASPHALT CONCRETE, PAVEMENT PATCHING, CLASS II BASE COURSE, PRECAST CONCRETE PILES, SLAB SPAN BRIDGE, AND RELATED WORK.
Estimated Construction Cost:$3,420,087.81
| Rank | License | Bidder | Construction Bid |
| 1 | 00044 | Guinn Construction, LLC | $3,287,509.50 |
| 2 | 12487 | Diamond B Construction Co., L.L.C. | $3,310,443.24 |
| 3 | 55505 | MERRICK, LLC | $3,401,678.40 |
| 4 | 01516 | Elevate Heavy Civil Construction, LLC | $3,490,754.50 |
| 5 | 00009 | Coastal Contractors, LLC | $3,537,360.80 |
| 6 | 39613 | Baker Pile Driving and Site Work, LLC | $3,597,303.05 |
| 7 | 39462 | JB JAMES CONSTRUCTION LLC | $3,685,349.36 |
| 8 | 56994 | Matt L. Guinn Construction, LLC | $3,803,723.30 |
| 9 | 52306 | SIEMA CONSTRUCTION, LLC | $3,902,778.96 |
Line Number | Item Number | Item Description | Quantity | Unit of Measure | - 1 - Guinn Construction, LLC | - 2 - Diamond B Construction Co., L.L.C. | - 3 - MERRICK, LLC | - 4 - Elevate Heavy Civil Construction, LLC | | Unit Price | Total Amount | Unit Price | Total Amount | Unit Price | Total Amount | Unit Price | Total Amount | | 0001 | 201-01-00100 | Clearing and Grubbing | 0.7 | LUMP | 60,000.00 | 60,000.00 | 75,000.00 | 75,000.00 | 65,000.00 | 65,000.00 | 450,000.00 | 450,000.00 | | 0002 | 202-02-03030 | Removal of Pavement Structure | 300.9 | SQYD | 15.00 | 4,513.50 | 25.00 | 7,522.50 | 15.00 | 4,513.50 | 20.00 | 6,018.00 | | 0003 | 202-02-04501 | Removal of Bridge (Str. No. 8630207791, 136' x 24' Timber Trestle Bridge) | 3,264 | LUMP | 50,000.00 | 50,000.00 | 75,000.00 | 75,000.00 | 195,000.00 | 195,000.00 | 250,000.00 | 250,000.00 | | 0004 | 202-02-14500 | Removal of Guard Rail | 299 | LNFT | 8.00 | 2,392.00 | 25.00 | 7,475.00 | 20.00 | 5,980.00 | 12.00 | 3,588.00 | | 0005 | 203-01-00100 | General Excavation | 198 | CUYD | 30.00 | 5,940.00 | 30.00 | 5,940.00 | 30.00 | 5,940.00 | 40.00 | 7,920.00 | | 0006 | 203-02-00100 | Drainage Excavation | 772 | CUYD | 35.00 | 27,020.00 | 50.00 | 38,600.00 | 30.00 | 23,160.00 | 26.00 | 20,072.00 | | 0007 | 203-03-00100 | Embankment | 2,028 | CUYD | 42.00 | 85,176.00 | 35.00 | 70,980.00 | 40.00 | 81,120.00 | 48.00 | 97,344.00 | | 0008 | 204-05-00100 | Temporary Sediment Check Dams (Hay) | 2 | EACH | 500.00 | 1,000.00 | 175.00 | 350.00 | 500.00 | 1,000.00 | 150.00 | 300.00 | | 0009 | 204-06-00100 | Temporary Silt Fencing | 1,703 | LNFT | 3.00 | 5,109.00 | 2.00 | 3,406.00 | 4.00 | 6,812.00 | 2.50 | 4,257.50 | | 0010 | 302-02-12080 | Class II Base Course (12" Thick) (Asphalt Concrete Base) | 511.5 | SQYD | 175.00 | 89,512.50 | 130.00 | 66,495.00 | 150.00 | 76,725.00 | 150.00 | 76,725.00 | | 0011 | 401-01-00100 | Aggregate Surface Course (Net Section) | 7.6 | CUYD | 300.00 | 2,280.00 | 260.00 | 1,976.00 | 190.00 | 1,444.00 | 260.00 | 1,976.00 | | 0012 | 402-01-00101 | Traffic Maintenance Surfacing (Aggregate) (Vehicular Measurement) | 7.6 | CUYD | 100.00 | 760.00 | 260.00 | 1,976.00 | 190.00 | 1,444.00 | 260.00 | 1,976.00 | | 0013 | 502-01-00100 | Asphalt Concrete | 228.6 | TON | 325.00 | 74,295.00 | 255.00 | 58,293.00 | 300.00 | 68,580.00 | 230.00 | 52,578.00 | | 0014 | 502-01-00200 | Asphalt Concrete, Drives, Turnouts and Miscellaneous | 71.8 | TON | 375.00 | 26,925.00 | 255.00 | 18,309.00 | 300.00 | 21,540.00 | 230.00 | 16,514.00 | | 0015 | 509-01-00100 | Milling Asphalt Pavement | 1,070 | SQYD | 15.00 | 16,050.00 | 18.00 | 19,260.00 | 18.00 | 19,260.00 | 13.00 | 13,910.00 | | 0016 | 509-02-00100 | Contractor Retained Reclaimed Asphalt Pavement | -60 | CUYD | 0.00 | 0.00 | 1.00 | -60.00 | 0.01 | -0.60 | 1.00 | -60.00 | | 0017 | 510-01-00001 | Pavement Patching (16.5 Inch Minimum Thickness) | 78 | SQYD | 250.00 | 19,500.00 | 270.00 | 21,060.00 | 250.00 | 19,500.00 | 210.00 | 16,380.00 | | 0018 | 701-05-02085 | Side Drain Pipe (Erosion) (30" RPVCP/CPEPDW/CPPPDW/CPPPTW/CMP) | 150 | LNFT | 225.00 | 33,750.00 | 145.00 | 21,750.00 | 160.00 | 24,000.00 | 140.00 | 21,000.00 | | 0019 | 701-17-00100 | Trench Excavation Safety Protection (Depth >5 feet) | 150 | LNFT | 10.00 | 1,500.00 | 16.00 | 2,400.00 | 14.00 | 2,100.00 | 10.00 | 1,500.00 | | 0020 | 704-03-00200 | Blocked Out Guard Rail - 31", (6'-3" Post Spacing) | 256.3 | LNFT | 50.00 | 12,815.00 | 36.00 | 9,226.80 | 25.00 | 6,407.50 | 30.00 | 7,689.00 | | 0021 | 704-07-00200 | Guard Rail Transitions (Double Thrie Beam) | 100 | LNFT | 150.00 | 15,000.00 | 136.00 | 13,600.00 | 120.00 | 12,000.00 | 120.00 | 12,000.00 | | 0022 | 704-10-00120 | Guard Rail End Treatment, MASH, (TL-3 Flared) | 2 | EACH | 4,250.00 | 8,500.00 | 3,800.00 | 7,600.00 | 3,500.00 | 7,000.00 | 3,500.00 | 7,000.00 | | 0023 | 704-10-00205 | Guard Rail End Treatment, MASH, (TL-3 Tangent) | 2 | EACH | 5,000.00 | 10,000.00 | 4,200.00 | 8,400.00 | 3,500.00 | 7,000.00 | 3,400.00 | 6,800.00 | | 0024 | 705-02-00100 | Combination Mesh & Barbed Wire Fence | 225 | LNFT | 30.00 | 6,750.00 | 15.00 | 3,375.00 | 18.00 | 4,050.00 | 15.00 | 3,375.00 | | 0025 | 705-04-00100 | Single Swinging Driveway Gates | 1 | EACH | 2,000.00 | 2,000.00 | 750.00 | 750.00 | 800.00 | 800.00 | 750.00 | 750.00 | | 0026 | 708-01-00100 | Right-of-Way Monument | 10 | EACH | 850.00 | 8,500.00 | 600.00 | 6,000.00 | 750.00 | 7,500.00 | 600.00 | 6,000.00 | | 0027 | 708-02-00100 | Right-of-Way Monument Witness Post | 10 | EACH | 400.00 | 4,000.00 | 200.00 | 2,000.00 | 250.00 | 2,500.00 | 200.00 | 2,000.00 | | 0028 | 711-01-04000 | Riprap (55 lb, 18" Thick) | 1,959 | SQYD | 110.00 | 215,490.00 | 90.00 | 176,310.00 | 100.00 | 195,900.00 | 125.00 | 244,875.00 | | 0029 | 711-04-00100 | Geotextile Fabric | 1,959 | SQYD | 4.00 | 7,836.00 | 0.91 | 1,782.69 | 4.00 | 7,836.00 | 2.50 | 4,897.50 | | 0030 | 713-01-00100 | Temporary Signs and Barricades | 1 | LUMP | 20,000.00 | 20,000.00 | 130,000.00 | 130,000.00 | 30,000.00 | 30,000.00 | 50,000.00 | 50,000.00 | | 0031 | 713-11-00100 | Portable Changeable Message Signs | 3 | EACH | 7,500.00 | 22,500.00 | 8,000.00 | 24,000.00 | 12,000.00 | 36,000.00 | 4,000.00 | 12,000.00 | | 0032 | 717-01-00100 | Seeding | 20 | LB | 50.00 | 1,000.00 | 25.00 | 500.00 | 30.00 | 600.00 | 25.00 | 500.00 | | 0033 | 718-01-00100 | Fertilizer | 680 | LB | 2.00 | 1,360.00 | 1.00 | 680.00 | 1.20 | 816.00 | 1.00 | 680.00 | | 0034 | 722-02-00100 | Project Site Laboratory (Equipped) | 1 | EACH | 20,000.00 | 20,000.00 | 58,500.00 | 58,500.00 | 15,000.00 | 15,000.00 | 20,000.00 | 20,000.00 | | 0035 | 724-01-00100 | Rumble Strips (Centerline) | 0.19 | MILE | 1,000.00 | 190.00 | 1,100.00 | 209.00 | 1,500.00 | 285.00 | 400.00 | 76.00 | | 0036 | 726-01-00100 | Bedding Material | 16.1 | CUYD | 200.00 | 3,220.00 | 250.00 | 4,025.00 | 230.00 | 3,703.00 | 180.00 | 2,898.00 | | 0037 | 727-01-00100 | Mobilization | 1 | LUMP | 300,000.00 | 300,000.00 | 330,000.00 | 330,000.00 | 330,000.00 | 330,000.00 | 340,000.00 | 340,000.00 | | 0038 | 729-16-00300 | Object Marker Assembly (Type 3) | 4 | EACH | 150.00 | 600.00 | 135.00 | 540.00 | 130.00 | 520.00 | 90.00 | 360.00 | | 0039 | 731-02-00100 | Reflectorized Raised Pavement Markers | 36 | EACH | 50.00 | 1,800.00 | 25.00 | 900.00 | 30.00 | 1,080.00 | 25.00 | 900.00 | | 0040 | 732-02-02000 | Plastic Pavement Striping (Solid Line) (4" Width) (Thermoplastic 90 mil) | 0.531 | MILE | 12,000.00 | 6,372.00 | 10,000.00 | 5,310.00 | 12,000.00 | 6,372.00 | 8,000.00 | 4,248.00 | | 0041 | 738-01-00100 | Mulch Sodding | 542 | CUYD | 50.00 | 27,100.00 | 55.00 | 29,810.00 | 30.00 | 16,260.00 | 25.00 | 13,550.00 | | 0042 | 740-01-00100 | Construction Layout | 1 | LUMP | 20,000.00 | 20,000.00 | 75,000.00 | 75,000.00 | 60,000.00 | 60,000.00 | 50,000.00 | 50,000.00 | | 0043 | 804-01-00600 | Precast Concrete Piles (24") | 2,112 | LNFT | 285.00 | 601,920.00 | 350.00 | 739,200.00 | 315.00 | 665,280.00 | 240.00 | 506,880.00 | | 0044 | 804-17-00100 | Construction Site Survey | 1 | LUMP | 12,500.00 | 12,500.00 | 11,000.00 | 11,000.00 | 15,000.00 | 15,000.00 | 5,000.00 | 5,000.00 | | 0045 | 804-18-00100 | Vibration Monitoring | 11 | DAY | 1,500.00 | 16,500.00 | 1,000.00 | 11,000.00 | 1,300.00 | 14,300.00 | 800.00 | 8,800.00 | | 0046 | 805-01-00100 | Class A1 Concrete (Slab Span) | 301.3 | CUYD | 2,250.00 | 677,925.00 | 1,750.00 | 527,275.00 | 1,800.00 | 542,340.00 | 1,350.00 | 406,755.00 | | 0047 | 805-01-00300 | Class A1 Concrete (Bent Cap) | 105.93 | CUYD | 2,850.00 | 301,900.50 | 1,825.00 | 193,322.25 | 3,000.00 | 317,790.00 | 3,000.00 | 317,790.00 | | 0048 | 805-18-00100 | Concrete Finish (Class 2 Rubbed Finish) | 2,727 | SQFT | 2.00 | 5,454.00 | 6.00 | 16,362.00 | 4.00 | 10,908.00 | 2.50 | 6,817.50 | | 0049 | 805-18-00200 | Concrete Finish (Class 3 Special Finish) | 2,727 | SQFT | 2.00 | 5,454.00 | 9.00 | 24,543.00 | 4.00 | 10,908.00 | 3.00 | 8,181.00 | | 0050 | 806-01-00100 | Deformed Reinforcing Steel | 72,380 | LB | 1.75 | 126,665.00 | 1.50 | 108,570.00 | 2.00 | 144,760.00 | 1.60 | 115,808.00 | | 0051 | 810-01-00120 | Concrete Bridge Railing (36 inch Height) | 400 | LNFT | 300.00 | 120,000.00 | 245.00 | 98,000.00 | 200.00 | 80,000.00 | 210.00 | 84,000.00 | | 0052 | 813-01-00100 | Concrete Approach Slabs (Cast-in-Place) | 1,200 | SQFT | 115.00 | 138,000.00 | 130.00 | 156,000.00 | 135.00 | 162,000.00 | 125.00 | 150,000.00 | | 0053 | 814-01-00100 | Elastomeric Bearing Pads (Non-Reinforced) | 231 | SFIN | 175.00 | 40,425.00 | 95.00 | 21,945.00 | 175.00 | 40,425.00 | 140.00 | 32,340.00 | | 0054 | 815-03-00300 | Joint Seal (Poured) | 330 | LNFT | 20.00 | 6,600.00 | 30.00 | 9,900.00 | 20.00 | 6,600.00 | 20.00 | 6,600.00 | | 0055 | NS-500-00240 | Sawing and Sealing Transverse Joints in Asphalt Concrete Overlay | 180 | LNFT | 20.00 | 3,600.00 | 10.00 | 1,800.00 | 10.00 | 1,800.00 | 25.00 | 4,500.00 | | 0056 | NS-500-00260 | Sawcuts in Asphalt Concrete Lifts | 300 | LNFT | 10.00 | 3,000.00 | 1.55 | 465.00 | 4.00 | 1,200.00 | 2.00 | 600.00 | | 0057 | NS-500-00340 | Saw Cutting Asphalt Concrete Pavement | 6,810 | INLF | 1.00 | 6,810.00 | 1.00 | 6,810.00 | 2.00 | 13,620.00 | 0.60 | 4,086.00 | | | | | | | | | | | | | | | | | | CONTRACTOR TOTAL | | | | 3,287,509.50 | | 3,310,443.24 | | 3,401,678.40 | | 3,490,754.50 |
Line Number | Item Number | Item Description | Quantity | Unit of Measure | - 5 - Coastal Contractors, LLC | - 6 - Baker Pile Driving and Site Work, LLC | - 7 - JB JAMES CONSTRUCTION LLC | - 8 - Matt L. Guinn Construction, LLC | | Unit Price | Total Amount | Unit Price | Total Amount | Unit Price | Total Amount | Unit Price | Total Amount | | 0001 | 201-01-00100 | Clearing and Grubbing | 0.7 | LUMP | 85,000.00 | 85,000.00 | 34,031.85 | 34,031.85 | 500,000.00 | 500,000.00 | 175,000.00 | 175,000.00 | | 0002 | 202-02-03030 | Removal of Pavement Structure | 300.9 | SQYD | 32.40 | 9,749.16 | 80.00 | 24,072.00 | 30.00 | 9,027.00 | 12.00 | 3,610.80 | | 0003 | 202-02-04501 | Removal of Bridge (Str. No. 8630207791, 136' x 24' Timber Trestle Bridge) | 3,264 | LUMP | 150,000.00 | 150,000.00 | 355,488.66 | 355,488.66 | 400,000.00 | 400,000.00 | 100,000.00 | 100,000.00 | | 0004 | 202-02-14500 | Removal of Guard Rail | 299 | LNFT | 30.00 | 8,970.00 | 16.22 | 4,849.78 | 12.00 | 3,588.00 | 8.00 | 2,392.00 | | 0005 | 203-01-00100 | General Excavation | 198 | CUYD | 50.00 | 9,900.00 | 23.75 | 4,702.50 | 50.00 | 9,900.00 | 60.00 | 11,880.00 | | 0006 | 203-02-00100 | Drainage Excavation | 772 | CUYD | 65.00 | 50,180.00 | 36.55 | 28,216.60 | 26.00 | 20,072.00 | 60.00 | 46,320.00 | | 0007 | 203-03-00100 | Embankment | 2,028 | CUYD | 65.00 | 131,820.00 | 59.08 | 119,814.24 | 56.00 | 113,568.00 | 60.00 | 121,680.00 | | 0008 | 204-05-00100 | Temporary Sediment Check Dams (Hay) | 2 | EACH | 220.00 | 440.00 | 320.34 | 640.68 | 150.00 | 300.00 | 250.00 | 500.00 | | 0009 | 204-06-00100 | Temporary Silt Fencing | 1,703 | LNFT | 3.00 | 5,109.00 | 3.09 | 5,262.27 | 7.00 | 11,921.00 | 4.00 | 6,812.00 | | 0010 | 302-02-12080 | Class II Base Course (12" Thick) (Asphalt Concrete Base) | 511.5 | SQYD | 140.00 | 71,610.00 | 159.00 | 81,328.50 | 90.00 | 46,035.00 | 195.00 | 99,742.50 | | 0011 | 401-01-00100 | Aggregate Surface Course (Net Section) | 7.6 | CUYD | 240.00 | 1,824.00 | 228.00 | 1,732.80 | 300.00 | 2,280.00 | 250.00 | 1,900.00 | | 0012 | 402-01-00101 | Traffic Maintenance Surfacing (Aggregate) (Vehicular Measurement) | 7.6 | CUYD | 240.00 | 1,824.00 | 226.00 | 1,717.60 | 300.00 | 2,280.00 | 250.00 | 1,900.00 | | 0013 | 502-01-00100 | Asphalt Concrete | 228.6 | TON | 265.00 | 60,579.00 | 275.00 | 62,865.00 | 210.00 | 48,006.00 | 380.00 | 86,868.00 | | 0014 | 502-01-00200 | Asphalt Concrete, Drives, Turnouts and Miscellaneous | 71.8 | TON | 490.00 | 35,182.00 | 500.00 | 35,900.00 | 370.00 | 26,566.00 | 385.00 | 27,643.00 | | 0015 | 509-01-00100 | Milling Asphalt Pavement | 1,070 | SQYD | 14.50 | 15,515.00 | 15.00 | 16,050.00 | 11.00 | 11,770.00 | 28.00 | 29,960.00 | | 0016 | 509-02-00100 | Contractor Retained Reclaimed Asphalt Pavement | -60 | CUYD | 0.10 | -6.00 | 0.01 | -0.60 | 0.01 | -0.60 | 1.00 | -60.00 | | 0017 | 510-01-00001 | Pavement Patching (16.5 Inch Minimum Thickness) | 78 | SQYD | 250.00 | 19,500.00 | 262.50 | 20,475.00 | 230.00 | 17,940.00 | 195.00 | 15,210.00 | | 0018 | 701-05-02085 | Side Drain Pipe (Erosion) (30" RPVCP/CPEPDW/CPPPDW/CPPPTW/CMP) | 150 | LNFT | 125.00 | 18,750.00 | 231.25 | 34,687.50 | 300.00 | 45,000.00 | 180.00 | 27,000.00 | | 0019 | 701-17-00100 | Trench Excavation Safety Protection (Depth >5 feet) | 150 | LNFT | 20.00 | 3,000.00 | 50.00 | 7,500.00 | 1.00 | 150.00 | 5.00 | 750.00 | | 0020 | 704-03-00200 | Blocked Out Guard Rail - 31", (6'-3" Post Spacing) | 256.3 | LNFT | 26.00 | 6,663.80 | 27.50 | 7,048.25 | 22.00 | 5,638.60 | 40.00 | 10,252.00 | | 0021 | 704-07-00200 | Guard Rail Transitions (Double Thrie Beam) | 100 | LNFT | 115.00 | 11,500.00 | 118.75 | 11,875.00 | 95.00 | 9,500.00 | 145.00 | 14,500.00 | | 0022 | 704-10-00120 | Guard Rail End Treatment, MASH, (TL-3 Flared) | 2 | EACH | 3,650.00 | 7,300.00 | 3,750.00 | 7,500.00 | 3,000.00 | 6,000.00 | 4,250.00 | 8,500.00 | | 0023 | 704-10-00205 | Guard Rail End Treatment, MASH, (TL-3 Tangent) | 2 | EACH | 3,650.00 | 7,300.00 | 3,750.00 | 7,500.00 | 3,000.00 | 6,000.00 | 4,250.00 | 8,500.00 | | 0024 | 705-02-00100 | Combination Mesh & Barbed Wire Fence | 225 | LNFT | 35.00 | 7,875.00 | 31.18 | 7,015.50 | 15.00 | 3,375.00 | 21.50 | 4,837.50 | | 0025 | 705-04-00100 | Single Swinging Driveway Gates | 1 | EACH | 1,000.00 | 1,000.00 | 999.54 | 999.54 | 750.00 | 750.00 | 1,500.00 | 1,500.00 | | 0026 | 708-01-00100 | Right-of-Way Monument | 10 | EACH | 730.00 | 7,300.00 | 750.00 | 7,500.00 | 600.00 | 6,000.00 | 750.00 | 7,500.00 | | 0027 | 708-02-00100 | Right-of-Way Monument Witness Post | 10 | EACH | 250.00 | 2,500.00 | 250.00 | 2,500.00 | 200.00 | 2,000.00 | 750.00 | 7,500.00 | | 0028 | 711-01-04000 | Riprap (55 lb, 18" Thick) | 1,959 | SQYD | 101.06 | 197,976.54 | 123.25 | 241,446.75 | 120.00 | 235,080.00 | 115.00 | 225,285.00 | | 0029 | 711-04-00100 | Geotextile Fabric | 1,959 | SQYD | 5.00 | 9,795.00 | 3.39 | 6,641.01 | 3.00 | 5,877.00 | 5.00 | 9,795.00 | | 0030 | 713-01-00100 | Temporary Signs and Barricades | 1 | LUMP | 25,000.00 | 25,000.00 | 17,950.28 | 17,950.28 | 50,000.00 | 50,000.00 | 65,000.00 | 65,000.00 | | 0031 | 713-11-00100 | Portable Changeable Message Signs | 3 | EACH | 13,500.00 | 40,500.00 | 1,625.00 | 4,875.00 | 18,000.00 | 54,000.00 | 13,000.00 | 39,000.00 | | 0032 | 717-01-00100 | Seeding | 20 | LB | 20.00 | 400.00 | 25.00 | 500.00 | 25.00 | 500.00 | 50.00 | 1,000.00 | | 0033 | 718-01-00100 | Fertilizer | 680 | LB | 4.00 | 2,720.00 | 1.23 | 836.40 | 0.85 | 578.00 | 2.00 | 1,360.00 | | 0034 | 722-02-00100 | Project Site Laboratory (Equipped) | 1 | EACH | 35,000.00 | 35,000.00 | 12,500.00 | 12,500.00 | 20,000.00 | 20,000.00 | 15,000.00 | 15,000.00 | | 0035 | 724-01-00100 | Rumble Strips (Centerline) | 0.19 | MILE | 500.00 | 95.00 | 6,250.00 | 1,187.50 | 400.00 | 76.00 | 21,000.00 | 3,990.00 | | 0036 | 726-01-00100 | Bedding Material | 16.1 | CUYD | 250.00 | 4,025.00 | 183.00 | 2,946.30 | 150.00 | 2,415.00 | 200.00 | 3,220.00 | | 0037 | 727-01-00100 | Mobilization | 1 | LUMP | 300,000.00 | 300,000.00 | 196,937.41 | 196,937.41 | 360,000.00 | 360,000.00 | 355,000.00 | 355,000.00 | | 0038 | 729-16-00300 | Object Marker Assembly (Type 3) | 4 | EACH | 120.00 | 480.00 | 118.75 | 475.00 | 100.00 | 400.00 | 250.00 | 1,000.00 | | 0039 | 731-02-00100 | Reflectorized Raised Pavement Markers | 36 | EACH | 30.00 | 1,080.00 | 31.25 | 1,125.00 | 25.00 | 900.00 | 25.00 | 900.00 | | 0040 | 732-02-02000 | Plastic Pavement Striping (Solid Line) (4" Width) (Thermoplastic 90 mil) | 0.531 | MILE | 10,000.00 | 5,310.00 | 10,000.00 | 5,310.00 | 6,500.00 | 3,451.50 | 15,000.00 | 7,965.00 | | 0041 | 738-01-00100 | Mulch Sodding | 542 | CUYD | 30.00 | 16,260.00 | 42.27 | 22,910.34 | 7.00 | 3,794.00 | 50.00 | 27,100.00 | | 0042 | 740-01-00100 | Construction Layout | 1 | LUMP | 60,000.00 | 60,000.00 | 71,534.16 | 71,534.16 | 30,000.00 | 30,000.00 | 45,000.00 | 45,000.00 | | 0043 | 804-01-00600 | Precast Concrete Piles (24") | 2,112 | LNFT | 255.00 | 538,560.00 | 290.57 | 613,683.84 | 300.00 | 633,600.00 | 285.00 | 601,920.00 | | 0044 | 804-17-00100 | Construction Site Survey | 1 | LUMP | 12,000.00 | 12,000.00 | 85,284.16 | 85,284.16 | 9,000.00 | 9,000.00 | 15,000.00 | 15,000.00 | | 0045 | 804-18-00100 | Vibration Monitoring | 11 | DAY | 1,150.00 | 12,650.00 | 843.75 | 9,281.25 | 936.36 | 10,299.96 | 1,400.00 | 15,400.00 | | 0046 | 805-01-00100 | Class A1 Concrete (Slab Span) | 301.3 | CUYD | 2,600.00 | 783,380.00 | 1,980.00 | 596,574.00 | 1,300.00 | 391,690.00 | 2,300.00 | 692,990.00 | | 0047 | 805-01-00300 | Class A1 Concrete (Bent Cap) | 105.93 | CUYD | 3,100.00 | 328,383.00 | 2,888.00 | 305,925.84 | 2,100.00 | 222,453.00 | 3,950.00 | 418,423.50 | | 0048 | 805-18-00100 | Concrete Finish (Class 2 Rubbed Finish) | 2,727 | SQFT | 2.00 | 5,454.00 | 6.40 | 17,452.80 | 0.50 | 1,363.50 | 2.50 | 6,817.50 | | 0049 | 805-18-00200 | Concrete Finish (Class 3 Special Finish) | 2,727 | SQFT | 3.00 | 8,181.00 | 5.68 | 15,489.36 | 3.00 | 8,181.00 | 2.50 | 6,817.50 | | 0050 | 806-01-00100 | Deformed Reinforcing Steel | 72,380 | LB | 1.26 | 91,198.80 | 1.46 | 105,674.80 | 1.30 | 94,094.00 | 1.40 | 101,332.00 | | 0051 | 810-01-00120 | Concrete Bridge Railing (36 inch Height) | 400 | LNFT | 275.00 | 110,000.00 | 253.38 | 101,352.00 | 150.00 | 60,000.00 | 250.00 | 100,000.00 | | 0052 | 813-01-00100 | Concrete Approach Slabs (Cast-in-Place) | 1,200 | SQFT | 140.00 | 168,000.00 | 146.87 | 176,244.00 | 120.00 | 144,000.00 | 150.00 | 180,000.00 | | 0053 | 814-01-00100 | Elastomeric Bearing Pads (Non-Reinforced) | 231 | SFIN | 120.00 | 27,720.00 | 212.28 | 49,036.68 | 90.00 | 20,790.00 | 100.00 | 23,100.00 | | 0054 | 815-03-00300 | Joint Seal (Poured) | 330 | LNFT | 35.00 | 11,550.00 | 39.30 | 12,969.00 | 18.00 | 5,940.00 | 30.00 | 9,900.00 | | 0055 | NS-500-00240 | Sawing and Sealing Transverse Joints in Asphalt Concrete Overlay | 180 | LNFT | 30.00 | 5,400.00 | 13.75 | 2,475.00 | 25.08 | 4,514.40 | 5.00 | 900.00 | | 0056 | NS-500-00260 | Sawcuts in Asphalt Concrete Lifts | 300 | LNFT | 2.50 | 750.00 | 6.25 | 1,875.00 | 2.00 | 600.00 | 5.00 | 1,500.00 | | 0057 | NS-500-00340 | Saw Cutting Asphalt Concrete Pavement | 6,810 | INLF | 0.75 | 5,107.50 | 3.75 | 25,537.50 | 0.60 | 4,086.00 | 1.00 | 6,810.00 | | | | | | | | | | | | | | | | | | CONTRACTOR TOTAL | | | | 3,537,360.80 | | 3,597,303.05 | | 3,685,349.36 | | 3,803,723.30 |
Line Number | Item Number | Item Description | Quantity | Unit of Measure | - 9 - SIEMA CONSTRUCTION, LLC | | Unit Price | Total Amount | | 0001 | 201-01-00100 | Clearing and Grubbing | 0.7 | LUMP | 150,000.00 | 150,000.00 | | 0002 | 202-02-03030 | Removal of Pavement Structure | 300.9 | SQYD | 17.00 | 5,115.30 | | 0003 | 202-02-04501 | Removal of Bridge (Str. No. 8630207791, 136' x 24' Timber Trestle Bridge) | 3,264 | LUMP | 150,000.00 | 150,000.00 | | 0004 | 202-02-14500 | Removal of Guard Rail | 299 | LNFT | 24.00 | 7,176.00 | | 0005 | 203-01-00100 | General Excavation | 198 | CUYD | 48.00 | 9,504.00 | | 0006 | 203-02-00100 | Drainage Excavation | 772 | CUYD | 25.00 | 19,300.00 | | 0007 | 203-03-00100 | Embankment | 2,028 | CUYD | 44.50 | 90,246.00 | | 0008 | 204-05-00100 | Temporary Sediment Check Dams (Hay) | 2 | EACH | 150.00 | 300.00 | | 0009 | 204-06-00100 | Temporary Silt Fencing | 1,703 | LNFT | 2.00 | 3,406.00 | | 0010 | 302-02-12080 | Class II Base Course (12" Thick) (Asphalt Concrete Base) | 511.5 | SQYD | 57.00 | 29,155.50 | | 0011 | 401-01-00100 | Aggregate Surface Course (Net Section) | 7.6 | CUYD | 335.00 | 2,546.00 | | 0012 | 402-01-00101 | Traffic Maintenance Surfacing (Aggregate) (Vehicular Measurement) | 7.6 | CUYD | 274.00 | 2,082.40 | | 0013 | 502-01-00100 | Asphalt Concrete | 228.6 | TON | 180.00 | 41,148.00 | | 0014 | 502-01-00200 | Asphalt Concrete, Drives, Turnouts and Miscellaneous | 71.8 | TON | 180.00 | 12,924.00 | | 0015 | 509-01-00100 | Milling Asphalt Pavement | 1,070 | SQYD | 1.55 | 1,658.50 | | 0016 | 509-02-00100 | Contractor Retained Reclaimed Asphalt Pavement | -60 | CUYD | 15.50 | -930.00 | | 0017 | 510-01-00001 | Pavement Patching (16.5 Inch Minimum Thickness) | 78 | SQYD | 125.00 | 9,750.00 | | 0018 | 701-05-02085 | Side Drain Pipe (Erosion) (30" RPVCP/CPEPDW/CPPPDW/CPPPTW/CMP) | 150 | LNFT | 145.00 | 21,750.00 | | 0019 | 701-17-00100 | Trench Excavation Safety Protection (Depth >5 feet) | 150 | LNFT | 47.00 | 7,050.00 | | 0020 | 704-03-00200 | Blocked Out Guard Rail - 31", (6'-3" Post Spacing) | 256.3 | LNFT | 30.00 | 7,689.00 | | 0021 | 704-07-00200 | Guard Rail Transitions (Double Thrie Beam) | 100 | LNFT | 130.00 | 13,000.00 | | 0022 | 704-10-00120 | Guard Rail End Treatment, MASH, (TL-3 Flared) | 2 | EACH | 3,300.00 | 6,600.00 | | 0023 | 704-10-00205 | Guard Rail End Treatment, MASH, (TL-3 Tangent) | 2 | EACH | 3,600.00 | 7,200.00 | | 0024 | 705-02-00100 | Combination Mesh & Barbed Wire Fence | 225 | LNFT | 15.50 | 3,487.50 | | 0025 | 705-04-00100 | Single Swinging Driveway Gates | 1 | EACH | 770.00 | 770.00 | | 0026 | 708-01-00100 | Right-of-Way Monument | 10 | EACH | 411.00 | 4,110.00 | | 0027 | 708-02-00100 | Right-of-Way Monument Witness Post | 10 | EACH | 411.00 | 4,110.00 | | 0028 | 711-01-04000 | Riprap (55 lb, 18" Thick) | 1,959 | SQYD | 155.00 | 303,645.00 | | 0029 | 711-04-00100 | Geotextile Fabric | 1,959 | SQYD | 3.00 | 5,877.00 | | 0030 | 713-01-00100 | Temporary Signs and Barricades | 1 | LUMP | 17,000.00 | 17,000.00 | | 0031 | 713-11-00100 | Portable Changeable Message Signs | 3 | EACH | 7,000.00 | 21,000.00 | | 0032 | 717-01-00100 | Seeding | 20 | LB | 28.75 | 575.00 | | 0033 | 718-01-00100 | Fertilizer | 680 | LB | 1.00 | 680.00 | | 0034 | 722-02-00100 | Project Site Laboratory (Equipped) | 1 | EACH | 25,000.00 | 25,000.00 | | 0035 | 724-01-00100 | Rumble Strips (Centerline) | 0.19 | MILE | 410.68 | 78.03 | | 0036 | 726-01-00100 | Bedding Material | 16.1 | CUYD | 300.00 | 4,830.00 | | 0037 | 727-01-00100 | Mobilization | 1 | LUMP | 385,000.00 | 385,000.00 | | 0038 | 729-16-00300 | Object Marker Assembly (Type 3) | 4 | EACH | 100.00 | 400.00 | | 0039 | 731-02-00100 | Reflectorized Raised Pavement Markers | 36 | EACH | 11.00 | 396.00 | | 0040 | 732-02-02000 | Plastic Pavement Striping (Solid Line) (4" Width) (Thermoplastic 90 mil) | 0.531 | MILE | 9,225.00 | 4,898.48 | | 0041 | 738-01-00100 | Mulch Sodding | 542 | CUYD | 52.00 | 28,184.00 | | 0042 | 740-01-00100 | Construction Layout | 1 | LUMP | 33,000.00 | 33,000.00 | | 0043 | 804-01-00600 | Precast Concrete Piles (24") | 2,112 | LNFT | 400.00 | 844,800.00 | | 0044 | 804-17-00100 | Construction Site Survey | 1 | LUMP | 15,000.00 | 15,000.00 | | 0045 | 804-18-00100 | Vibration Monitoring | 11 | DAY | 825.00 | 9,075.00 | | 0046 | 805-01-00100 | Class A1 Concrete (Slab Span) | 301.3 | CUYD | 1,700.00 | 512,210.00 | | 0047 | 805-01-00300 | Class A1 Concrete (Bent Cap) | 105.93 | CUYD | 4,800.00 | 508,464.00 | | 0048 | 805-18-00100 | Concrete Finish (Class 2 Rubbed Finish) | 2,727 | SQFT | 3.00 | 8,181.00 | | 0049 | 805-18-00200 | Concrete Finish (Class 3 Special Finish) | 2,727 | SQFT | 4.25 | 11,589.75 | | 0050 | 806-01-00100 | Deformed Reinforcing Steel | 72,380 | LB | 3.00 | 217,140.00 | | 0051 | 810-01-00120 | Concrete Bridge Railing (36 inch Height) | 400 | LNFT | 165.00 | 66,000.00 | | 0052 | 813-01-00100 | Concrete Approach Slabs (Cast-in-Place) | 1,200 | SQFT | 160.00 | 192,000.00 | | 0053 | 814-01-00100 | Elastomeric Bearing Pads (Non-Reinforced) | 231 | SFIN | 250.00 | 57,750.00 | | 0054 | 815-03-00300 | Joint Seal (Poured) | 330 | LNFT | 21.00 | 6,930.00 | | 0055 | NS-500-00240 | Sawing and Sealing Transverse Joints in Asphalt Concrete Overlay | 180 | LNFT | 25.75 | 4,635.00 | | 0056 | NS-500-00260 | Sawcuts in Asphalt Concrete Lifts | 300 | LNFT | 2.60 | 780.00 | | 0057 | NS-500-00340 | Saw Cutting Asphalt Concrete Pavement | 6,810 | INLF | 1.25 | 8,512.50 | | | | | | | | | | | | CONTRACTOR TOTAL | | | | 3,902,778.96 |
|