Proposal:H.014252.6
Parish:Tangipahoa
Routes: LA 1054
Description:LA 1054: TYNER CREEK BRIDGE
Type Construction:CLEARING AND GRUBBING, REMOVAL OF SLAB SPAN BRIDGE & TIMBER HEADWALL, GRADING, DRAINAGE STRUCTURES, MILLING ASPHALT CONCRETE, PAVEMENT PATCHING, PAVEMENT WIDENING, ASPHALT CONCRETE PAVEMENT, 18" PRECAST CONCRETE PILES, CONCRETE SLAB SPAN BRIDGE, AND RELATED WORK.
Estimated Construction Cost:$1,872,341.00
| Rank | License | Bidder | Construction Bid |
| 1 | 39613 | Baker Pile Driving and Site Work, LLC | $1,645,682.91 |
| 2 | 28190 | Buck Town Contractors & Co. | $1,787,534.00 |
| 3 | 00009 | Coastal Contractors, LLC | $1,892,655.85 |
| 4 | 12487 | Diamond B Construction Co., L.L.C. | $1,936,213.50 |
| 5 | 00044 | Guinn Construction, LLC | $1,972,263.08 |
| 6 | 01516 | Elevate Heavy Civil Construction, LLC | $1,995,501.00 |
| 7 | 67770 | Reliant Industrial Solutions L.L.C. | $2,326,538.14 |
| 8 | 56994 | Matt L. Guinn Construction, LLC | $2,367,573.85 |
| 9 | 39462 | JB JAMES CONSTRUCTION LLC | $2,544,865.34 |
Line Number | Item Number | Item Description | Quantity | Unit of Measure | - 1 - Baker Pile Driving and Site Work, LLC | - 2 - Buck Town Contractors & Co. | - 3 - Coastal Contractors, LLC | - 4 - Diamond B Construction Co., L.L.C. | | Unit Price | Total Amount | Unit Price | Total Amount | Unit Price | Total Amount | Unit Price | Total Amount | | 0001 | 201-01-00100 | Clearing and Grubbing | 0.4 | LUMP | 13,028.88 | 13,028.88 | 19,000.01 | 19,000.01 | 25,000.00 | 25,000.00 | 35,000.00 | 35,000.00 | | 0003 | 202-02-02000 | Removal of Asphalt Drives | 113 | SQYD | 26.77 | 3,025.01 | 15.00 | 1,695.00 | 25.00 | 2,825.00 | 55.00 | 6,215.00 | | 0004 | 202-02-03030 | Removal of Pavement Structure | 112 | SQYD | 12.09 | 1,354.08 | 15.00 | 1,680.00 | 25.00 | 2,800.00 | 35.00 | 3,920.00 | | 0005 | 202-02-04501 | Removal of Bridge STR. NO. 625308532204401, 39' X 24' CONC. SLAB SPAN BRIDGE & TIMBER HEADWALL | 936 | LUMP | 36,605.71 | 36,605.71 | 26,000.00 | 26,000.00 | 45,000.00 | 45,000.00 | 35,000.00 | 35,000.00 | | 0006 | 202-02-12000 | Removal of Fence | 265 | LNFT | 7.40 | 1,961.00 | 6.00 | 1,590.00 | 7.00 | 1,855.00 | 14.00 | 3,710.00 | | 0007 | 202-02-14500 | Removal of Guard Rail | 164 | LNFT | 17.55 | 2,878.20 | 6.00 | 984.00 | 29.00 | 4,756.00 | 27.00 | 4,428.00 | | 0008 | 202-02-32120 | Removal of Pipe (Side Drain) CONCRETE 12" | 74 | LNFT | 29.20 | 2,160.80 | 30.00 | 2,220.00 | 28.00 | 2,072.00 | 40.00 | 2,960.00 | | 0009 | 202-02-32120 | Removal of Pipe (Side Drain) METAL 12" | 28 | LNFT | 31.53 | 882.84 | 30.00 | 840.00 | 30.00 | 840.00 | 106.00 | 2,968.00 | | 0010 | 202-02-32120 | Removal of Pipe (Side Drain) METAL 24" | 36 | LNFT | 31.41 | 1,130.76 | 30.00 | 1,080.00 | 35.00 | 1,260.00 | 85.00 | 3,060.00 | | 0011 | 203-01-00100 | General Excavation | 125 | CUYD | 22.58 | 2,822.50 | 25.00 | 3,125.00 | 38.00 | 4,750.00 | 45.00 | 5,625.00 | | 0012 | 203-02-00100 | Drainage Excavation | 340 | CUYD | 23.25 | 7,905.00 | 25.00 | 8,500.00 | 38.00 | 12,920.00 | 37.00 | 12,580.00 | | 0013 | 203-03-00100 | Embankment | 539 | CUYD | 74.95 | 40,398.05 | 41.00 | 22,099.00 | 50.00 | 26,950.00 | 34.00 | 18,326.00 | | 0014 | 204-02-00100 | Temporary Hay Bales | 49 | EACH | 31.42 | 1,539.58 | 10.00 | 490.00 | 35.00 | 1,715.00 | 35.00 | 1,715.00 | | 0015 | 204-06-00100 | Temporary Silt Fencing | 1,207 | LNFT | 2.68 | 3,234.76 | 1.00 | 1,207.00 | 3.00 | 3,621.00 | 2.00 | 2,414.00 | | 0016 | 401-02-00100 | Aggregate Surface Course (Adjusted Vehicular Measurement) | 7 | CUYD | 158.67 | 1,110.69 | 280.00 | 1,960.00 | 225.00 | 1,575.00 | 265.00 | 1,855.00 | | 0017 | 402-01-00101 | Traffic Maintenance Surfacing (Aggregate) (Vehicular Measurement) | 19 | CUYD | 157.32 | 2,989.08 | 130.00 | 2,470.00 | 100.00 | 1,900.00 | 210.00 | 3,990.00 | | 0018 | 502-01-00100 | Asphalt Concrete | 289.9 | TON | 206.00 | 59,719.40 | 226.00 | 65,517.40 | 250.00 | 72,475.00 | 210.00 | 60,879.00 | | 0019 | 502-01-00200 | Asphalt Concrete, Drives, Turnouts and Miscellaneous | 78.3 | TON | 209.00 | 16,364.70 | 226.00 | 17,695.80 | 425.00 | 33,277.50 | 270.00 | 21,141.00 | | 0020 | 509-01-00100 | Milling Asphalt Pavement | 1,184 | SQYD | 16.00 | 18,944.00 | 17.00 | 20,128.00 | 11.50 | 13,616.00 | 15.00 | 17,760.00 | | 0021 | 509-02-00100 | Contractor Retained Reclaimed Asphalt Pavement | -66 | CUYD | 5.60 | -369.60 | 0.01 | -0.66 | 0.10 | -6.60 | 1.00 | -66.00 | | 0022 | 510-01-00001 | Pavement Patching (14.4 inch minimum thickness) | 78 | SQYD | 213.79 | 16,675.62 | 232.00 | 18,096.00 | 285.00 | 22,230.00 | 195.00 | 15,210.00 | | 0023 | 510-02-00100 | Pavement Widening 12'' THICK | 324.2 | SQYD | 215.00 | 69,703.00 | 232.00 | 75,214.40 | 200.00 | 64,840.00 | 145.00 | 47,009.00 | | 0024 | 701-05-01049 | Side Drain Pipe (18" RCP/RPVCP/CPEPDW/CPPPDW) | 222 | LNFT | 77.01 | 17,096.22 | 120.00 | 26,640.00 | 135.00 | 29,970.00 | 80.00 | 17,760.00 | | 0025 | 701-05-01068 | Side Drain Pipe (24" RCP/RPVCP/CPEPDW/CPPPDW) | 254 | LNFT | 98.22 | 24,947.88 | 150.00 | 38,100.00 | 145.00 | 36,830.00 | 90.00 | 22,860.00 | | 0026 | 701-05-02067 | Side Drain Pipe (Erosion) (24" RPVCP/CPEPDW/CPPPDW) | 402 | LNFT | 97.55 | 39,215.10 | 150.00 | 60,300.00 | 145.00 | 58,290.00 | 70.00 | 28,140.00 | | 0027 | 701-17-00100 | Trench Excavation Safety Protection (Depth >5 feet) | 878 | LNFT | 5.92 | 5,197.76 | 47.00 | 41,266.00 | 4.00 | 3,512.00 | 3.00 | 2,634.00 | | 0028 | 702-03-00100 | Catch Basins (CB-01) | 7 | EACH | 3,759.51 | 26,316.57 | 4,500.00 | 31,500.00 | 6,800.00 | 47,600.00 | 6,000.00 | 42,000.00 | | 0029 | 702-08-00100 | Side Drain Safety End (Type 1) | 1 | EACH | 3,025.77 | 3,025.77 | 3,100.00 | 3,100.00 | 5,000.00 | 5,000.00 | 3,700.00 | 3,700.00 | | 0030 | 704-03-00200 | Blocked Out Guard Rail - 31", (6'-3" Post Spacing) | 112.5 | LNFT | 32.00 | 3,600.00 | 29.00 | 3,262.50 | 35.00 | 3,937.50 | 37.00 | 4,162.50 | | 0031 | 704-07-00200 | Guard Rail Transitions (Double Thrie Beam) | 50 | LNFT | 110.92 | 5,546.00 | 115.00 | 5,750.00 | 140.00 | 7,000.00 | 140.00 | 7,000.00 | | 0032 | 704-10-00205 | Guard Rail End Treatment, MASH, (TL-3 Tangent) | 2 | EACH | 3,297.89 | 6,595.78 | 3,475.00 | 6,950.00 | 4,000.00 | 8,000.00 | 4,250.00 | 8,500.00 | | 0033 | 705-01-00100 | Barbed Wire Fence | 265 | LNFT | 26.38 | 6,990.70 | 26.00 | 6,890.00 | 21.00 | 5,565.00 | 12.00 | 3,180.00 | | 0034 | 706-03-00300 | Incidental Concrete Paving (6" Thick) | 17.8 | SQYD | 95.00 | 1,691.00 | 160.00 | 2,848.00 | 215.00 | 3,827.00 | 700.00 | 12,460.00 | | 0035 | 708-01-00100 | Right-of-Way Monument | 8 | EACH | 719.47 | 5,755.76 | 160.00 | 1,280.00 | 750.00 | 6,000.00 | 700.00 | 5,600.00 | | 0036 | 708-02-00100 | Right-of-Way Monument Witness Post | 8 | EACH | 299.47 | 2,395.76 | 190.00 | 1,520.00 | 290.00 | 2,320.00 | 300.00 | 2,400.00 | | 0037 | 711-01-04000 | Riprap (55 lb, 18" Thick) | 888 | SQYD | 131.81 | 117,047.28 | 125.00 | 111,000.00 | 90.00 | 79,920.00 | 85.00 | 75,480.00 | | 0038 | 711-04-00100 | Geotextile Fabric | 888 | SQYD | 3.80 | 3,374.40 | 2.00 | 1,776.00 | 5.00 | 4,440.00 | 1.00 | 888.00 | | 0039 | 713-01-00100 | Temporary Signs and Barricades | 1 | LUMP | 23,532.00 | 23,532.00 | 18,000.00 | 18,000.00 | 35,000.00 | 35,000.00 | 82,000.00 | 82,000.00 | | 0040 | 716-01-00100 | Mulch (Vegetative) | 0.6 | TON | 3,911.00 | 2,346.60 | 3,800.00 | 2,280.00 | 3,000.00 | 1,800.00 | 3,500.00 | 2,100.00 | | 0041 | 726-01-00100 | Bedding Material | 5.6 | CUYD | 254.00 | 1,422.40 | 320.00 | 1,792.00 | 230.00 | 1,288.00 | 240.00 | 1,344.00 | | 0042 | 727-01-00100 | Mobilization | 1 | LUMP | 174,790.50 | 174,790.50 | 156,000.00 | 156,000.00 | 180,000.00 | 180,000.00 | 190,000.00 | 190,000.00 | | 0043 | 729-16-00300 | Object Marker Assembly (Type 3) | 4 | EACH | 173.69 | 694.76 | 115.00 | 460.00 | 100.00 | 400.00 | 140.00 | 560.00 | | 0044 | 731-01-00100 | Nonreflectorized Raised Pavement Markers | 206 | EACH | 22.44 | 4,622.64 | 17.00 | 3,502.00 | 17.00 | 3,502.00 | 14.00 | 2,884.00 | | 0045 | 731-02-00100 | Reflectorized Raised Pavement Markers | 29 | EACH | 18.60 | 539.40 | 12.00 | 348.00 | 11.50 | 333.50 | 10.00 | 290.00 | | 0046 | 732-02-02000 | Plastic Pavement Striping (Solid Line) (4" Width) (Thermoplastic 90 mil) | 0.428 | MILE | 9,100.00 | 3,894.80 | 8,700.00 | 3,723.60 | 8,500.00 | 3,638.00 | 10,000.00 | 4,280.00 | | 0047 | 735-01-00100 | Mailboxes | 3 | EACH | 26.25 | 78.75 | 29.00 | 87.00 | 45.00 | 135.00 | 25.00 | 75.00 | | 0048 | 735-02-00100 | Mailbox Supports (Single) | 3 | EACH | 157.50 | 472.50 | 170.00 | 510.00 | 400.00 | 1,200.00 | 250.00 | 750.00 | | 0049 | 739-01-00100 | Hydro-Seeding | 0.39 | ACRE | 5,431.00 | 2,118.09 | 8,300.00 | 3,237.00 | 8,500.00 | 3,315.00 | 11,000.00 | 4,290.00 | | 0050 | 740-01-00100 | Construction Layout | 1 | LUMP | 17,453.99 | 17,453.99 | 16,100.00 | 16,100.00 | 25,000.00 | 25,000.00 | 95,000.00 | 95,000.00 | | 0051 | 804-01-00400 | Precast Concrete Piles (18") | 1,740 | LNFT | 148.12 | 257,728.80 | 194.00 | 337,560.00 | 135.00 | 234,900.00 | 185.00 | 321,900.00 | | 0052 | 805-01-00100 | Class A1 Concrete (Slab Span) | 120.52 | CUYD | 1,505.00 | 181,382.60 | 1,815.00 | 218,743.80 | 2,400.00 | 289,248.00 | 1,550.00 | 186,806.00 | | 0053 | 805-01-00300 | Class A1 Concrete (Bent Cap) | 38.85 | CUYD | 2,579.00 | 100,194.15 | 2,575.00 | 100,038.75 | 3,000.00 | 116,550.00 | 2,500.00 | 97,125.00 | | 0054 | 805-18-00100 | Concrete Finish (Class 2 Rubbed Finish) | 1,114 | SQFT | 4.67 | 5,202.38 | 1.00 | 1,114.00 | 2.00 | 2,228.00 | 4.00 | 4,456.00 | | 0055 | 805-18-00200 | Concrete Finish (Class 3 Special Finish) | 1,114 | SQFT | 5.01 | 5,581.14 | 2.00 | 2,228.00 | 3.00 | 3,342.00 | 7.00 | 7,798.00 | | 0056 | 806-01-00100 | Deformed Reinforcing Steel | 29,097 | LB | 1.38 | 40,153.86 | 1.20 | 34,916.40 | 1.35 | 39,280.95 | 2.00 | 58,194.00 | | 0057 | 810-01-00120 | Concrete Bridge Railing (36 inch Height) | 160 | LNFT | 175.39 | 28,062.40 | 270.00 | 43,200.00 | 265.00 | 42,400.00 | 275.00 | 44,000.00 | | 0058 | 813-01-00100 | Concrete Approach Slabs (Cast-in-Place) | 1,200 | SQFT | 93.62 | 112,344.00 | 101.00 | 121,200.00 | 125.00 | 150,000.00 | 120.00 | 144,000.00 | | 0059 | 814-01-00100 | Elastomeric Bearing Pads (Non-Reinforced) | 96 | SFIN | 267.00 | 25,632.00 | 172.00 | 16,512.00 | 120.00 | 11,520.00 | 130.00 | 12,480.00 | | 0060 | 815-03-00300 | Joint Seal (Poured) | 150 | LNFT | 33.53 | 5,029.50 | 35.00 | 5,250.00 | 35.00 | 5,250.00 | 35.00 | 5,250.00 | | 0061 | NS-500-00240 | Sawing and Sealing Transverse Joints in Asphalt Concrete Overlay | 180 | LNFT | 9.89 | 1,780.20 | 11.00 | 1,980.00 | 30.00 | 5,400.00 | 10.00 | 1,800.00 | | 0062 | NS-500-00260 | Sawcuts in Asphalt Concrete Lifts | 300 | LNFT | 6.74 | 2,022.00 | 2.00 | 600.00 | 2.25 | 675.00 | 2.00 | 600.00 | | 0063 | NS-500-00340 | Saw Cutting Asphalt Concrete Pavement | 768 | INLF | 4.08 | 3,133.44 | 1.00 | 768.00 | 1.00 | 768.00 | 1.00 | 768.00 | | 0064 | NS-700-00840 | Impact Attenuator (Reusable, Test Level 3) | 2 | EACH | 29,022.89 | 58,045.78 | 31,800.00 | 63,600.00 | 38,500.00 | 77,000.00 | 55,000.00 | 110,000.00 | | 0065 | 202-01-00100 | Removal of Structures and Obstructions | 1 | LUMP | 14,564.19 | 14,564.19 | 10.00 | 10.00 | 10,000.00 | 10,000.00 | 15,000.00 | 15,000.00 | | | | | | | | | | | | | | | | | | CONTRACTOR TOTAL | | | | 1,645,682.91 | | 1,787,534.00 | | 1,892,655.85 | | 1,936,213.50 |
Line Number | Item Number | Item Description | Quantity | Unit of Measure | - 5 - Guinn Construction, LLC | - 6 - Elevate Heavy Civil Construction, LLC | - 7 - Reliant Industrial Solutions L.L.C. | - 8 - Matt L. Guinn Construction, LLC | | Unit Price | Total Amount | Unit Price | Total Amount | Unit Price | Total Amount | Unit Price | Total Amount | | 0001 | 201-01-00100 | Clearing and Grubbing | 0.4 | LUMP | 45,000.00 | 45,000.00 | 200,000.00 | 200,000.00 | 72,000.00 | 72,000.00 | 75,000.00 | 75,000.00 | | 0003 | 202-02-02000 | Removal of Asphalt Drives | 113 | SQYD | 15.00 | 1,695.00 | 26.00 | 2,938.00 | 43.00 | 4,859.00 | 25.00 | 2,825.00 | | 0004 | 202-02-03030 | Removal of Pavement Structure | 112 | SQYD | 15.00 | 1,680.00 | 44.00 | 4,928.00 | 72.50 | 8,120.00 | 25.00 | 2,800.00 | | 0005 | 202-02-04501 | Removal of Bridge STR. NO. 625308532204401, 39' X 24' CONC. SLAB SPAN BRIDGE & TIMBER HEADWALL | 936 | LUMP | 40,000.00 | 40,000.00 | 42,000.00 | 42,000.00 | 40,000.00 | 40,000.00 | 35,000.00 | 35,000.00 | | 0006 | 202-02-12000 | Removal of Fence | 265 | LNFT | 8.00 | 2,120.00 | 5.00 | 1,325.00 | 12.45 | 3,299.25 | 15.00 | 3,975.00 | | 0007 | 202-02-14500 | Removal of Guard Rail | 164 | LNFT | 10.00 | 1,640.00 | 18.00 | 2,952.00 | 16.00 | 2,624.00 | 10.00 | 1,640.00 | | 0008 | 202-02-32120 | Removal of Pipe (Side Drain) CONCRETE 12" | 74 | LNFT | 10.00 | 740.00 | 23.00 | 1,702.00 | 39.00 | 2,886.00 | 30.00 | 2,220.00 | | 0009 | 202-02-32120 | Removal of Pipe (Side Drain) METAL 12" | 28 | LNFT | 10.00 | 280.00 | 43.00 | 1,204.00 | 50.00 | 1,400.00 | 30.00 | 840.00 | | 0010 | 202-02-32120 | Removal of Pipe (Side Drain) METAL 24" | 36 | LNFT | 10.00 | 360.00 | 33.00 | 1,188.00 | 40.00 | 1,440.00 | 30.00 | 1,080.00 | | 0011 | 203-01-00100 | General Excavation | 125 | CUYD | 25.00 | 3,125.00 | 38.00 | 4,750.00 | 90.00 | 11,250.00 | 60.00 | 7,500.00 | | 0012 | 203-02-00100 | Drainage Excavation | 340 | CUYD | 25.00 | 8,500.00 | 34.00 | 11,560.00 | 84.00 | 28,560.00 | 60.00 | 20,400.00 | | 0013 | 203-03-00100 | Embankment | 539 | CUYD | 45.00 | 24,255.00 | 45.00 | 24,255.00 | 87.00 | 46,893.00 | 60.00 | 32,340.00 | | 0014 | 204-02-00100 | Temporary Hay Bales | 49 | EACH | 50.00 | 2,450.00 | 30.00 | 1,470.00 | 42.00 | 2,058.00 | 30.00 | 1,470.00 | | 0015 | 204-06-00100 | Temporary Silt Fencing | 1,207 | LNFT | 4.00 | 4,828.00 | 3.00 | 3,621.00 | 2.40 | 2,896.80 | 3.00 | 3,621.00 | | 0016 | 401-02-00100 | Aggregate Surface Course (Adjusted Vehicular Measurement) | 7 | CUYD | 500.00 | 3,500.00 | 300.00 | 2,100.00 | 190.00 | 1,330.00 | 250.00 | 1,750.00 | | 0017 | 402-01-00101 | Traffic Maintenance Surfacing (Aggregate) (Vehicular Measurement) | 19 | CUYD | 100.00 | 1,900.00 | 135.00 | 2,565.00 | 129.50 | 2,460.50 | 250.00 | 4,750.00 | | 0018 | 502-01-00100 | Asphalt Concrete | 289.9 | TON | 325.00 | 94,217.50 | 225.00 | 65,227.50 | 270.00 | 78,273.00 | 355.00 | 102,914.50 | | 0019 | 502-01-00200 | Asphalt Concrete, Drives, Turnouts and Miscellaneous | 78.3 | TON | 375.00 | 29,362.50 | 225.00 | 17,617.50 | 240.00 | 18,792.00 | 355.00 | 27,796.50 | | 0020 | 509-01-00100 | Milling Asphalt Pavement | 1,184 | SQYD | 15.00 | 17,760.00 | 11.00 | 13,024.00 | 14.40 | 17,049.60 | 30.00 | 35,520.00 | | 0021 | 509-02-00100 | Contractor Retained Reclaimed Asphalt Pavement | -66 | CUYD | 0.00 | 0.00 | 1.00 | -66.00 | 0.01 | -0.66 | 1.00 | -66.00 | | 0022 | 510-01-00001 | Pavement Patching (14.4 inch minimum thickness) | 78 | SQYD | 175.00 | 13,650.00 | 190.00 | 14,820.00 | 216.00 | 16,848.00 | 235.00 | 18,330.00 | | 0023 | 510-02-00100 | Pavement Widening 12'' THICK | 324.2 | SQYD | 150.00 | 48,630.00 | 190.00 | 61,598.00 | 174.00 | 56,410.80 | 220.00 | 71,324.00 | | 0024 | 701-05-01049 | Side Drain Pipe (18" RCP/RPVCP/CPEPDW/CPPPDW) | 222 | LNFT | 75.39 | 16,736.58 | 75.00 | 16,650.00 | 110.00 | 24,420.00 | 105.00 | 23,310.00 | | 0025 | 701-05-01068 | Side Drain Pipe (24" RCP/RPVCP/CPEPDW/CPPPDW) | 254 | LNFT | 135.00 | 34,290.00 | 90.00 | 22,860.00 | 146.00 | 37,084.00 | 135.00 | 34,290.00 | | 0026 | 701-05-02067 | Side Drain Pipe (Erosion) (24" RPVCP/CPEPDW/CPPPDW) | 402 | LNFT | 135.00 | 54,270.00 | 90.00 | 36,180.00 | 134.50 | 54,069.00 | 135.00 | 54,270.00 | | 0027 | 701-17-00100 | Trench Excavation Safety Protection (Depth >5 feet) | 878 | LNFT | 5.00 | 4,390.00 | 17.00 | 14,926.00 | 20.00 | 17,560.00 | 5.00 | 4,390.00 | | 0028 | 702-03-00100 | Catch Basins (CB-01) | 7 | EACH | 6,500.00 | 45,500.00 | 5,300.00 | 37,100.00 | 11,890.00 | 83,230.00 | 7,000.00 | 49,000.00 | | 0029 | 702-08-00100 | Side Drain Safety End (Type 1) | 1 | EACH | 3,500.00 | 3,500.00 | 4,300.00 | 4,300.00 | 5,300.00 | 5,300.00 | 7,000.00 | 7,000.00 | | 0030 | 704-03-00200 | Blocked Out Guard Rail - 31", (6'-3" Post Spacing) | 112.5 | LNFT | 42.50 | 4,781.25 | 30.00 | 3,375.00 | 36.00 | 4,050.00 | 40.00 | 4,500.00 | | 0031 | 704-07-00200 | Guard Rail Transitions (Double Thrie Beam) | 50 | LNFT | 155.00 | 7,750.00 | 115.00 | 5,750.00 | 138.00 | 6,900.00 | 145.00 | 7,250.00 | | 0032 | 704-10-00205 | Guard Rail End Treatment, MASH, (TL-3 Tangent) | 2 | EACH | 5,500.00 | 11,000.00 | 3,300.00 | 6,600.00 | 3,950.00 | 7,900.00 | 4,500.00 | 9,000.00 | | 0033 | 705-01-00100 | Barbed Wire Fence | 265 | LNFT | 15.00 | 3,975.00 | 20.00 | 5,300.00 | 14.40 | 3,816.00 | 30.00 | 7,950.00 | | 0034 | 706-03-00300 | Incidental Concrete Paving (6" Thick) | 17.8 | SQYD | 200.00 | 3,560.00 | 120.00 | 2,136.00 | 251.50 | 4,476.70 | 420.00 | 7,476.00 | | 0035 | 708-01-00100 | Right-of-Way Monument | 8 | EACH | 1,000.00 | 8,000.00 | 650.00 | 5,200.00 | 675.00 | 5,400.00 | 750.00 | 6,000.00 | | 0036 | 708-02-00100 | Right-of-Way Monument Witness Post | 8 | EACH | 350.00 | 2,800.00 | 250.00 | 2,000.00 | 240.00 | 1,920.00 | 750.00 | 6,000.00 | | 0037 | 711-01-04000 | Riprap (55 lb, 18" Thick) | 888 | SQYD | 125.00 | 111,000.00 | 145.00 | 128,760.00 | 128.00 | 113,664.00 | 125.00 | 111,000.00 | | 0038 | 711-04-00100 | Geotextile Fabric | 888 | SQYD | 5.00 | 4,440.00 | 3.00 | 2,664.00 | 5.40 | 4,795.20 | 6.50 | 5,772.00 | | 0039 | 713-01-00100 | Temporary Signs and Barricades | 1 | LUMP | 25,000.00 | 25,000.00 | 50,000.00 | 50,000.00 | 67,500.00 | 67,500.00 | 68,000.00 | 68,000.00 | | 0040 | 716-01-00100 | Mulch (Vegetative) | 0.6 | TON | 4,000.00 | 2,400.00 | 3,300.00 | 1,980.00 | 4,200.00 | 2,520.00 | 4,200.00 | 2,520.00 | | 0041 | 726-01-00100 | Bedding Material | 5.6 | CUYD | 250.00 | 1,400.00 | 140.00 | 784.00 | 290.00 | 1,624.00 | 300.00 | 1,680.00 | | 0042 | 727-01-00100 | Mobilization | 1 | LUMP | 175,000.00 | 175,000.00 | 190,000.00 | 190,000.00 | 200,000.00 | 200,000.00 | 235,000.00 | 235,000.00 | | 0043 | 729-16-00300 | Object Marker Assembly (Type 3) | 4 | EACH | 200.00 | 800.00 | 90.00 | 360.00 | 160.00 | 640.00 | 250.00 | 1,000.00 | | 0044 | 731-01-00100 | Nonreflectorized Raised Pavement Markers | 206 | EACH | 25.00 | 5,150.00 | 20.00 | 4,120.00 | 24.00 | 4,944.00 | 30.00 | 6,180.00 | | 0045 | 731-02-00100 | Reflectorized Raised Pavement Markers | 29 | EACH | 15.00 | 435.00 | 8.00 | 232.00 | 9.60 | 278.40 | 30.00 | 870.00 | | 0046 | 732-02-02000 | Plastic Pavement Striping (Solid Line) (4" Width) (Thermoplastic 90 mil) | 0.428 | MILE | 12,000.00 | 5,136.00 | 8,300.00 | 3,552.40 | 9,600.00 | 4,108.80 | 25,000.00 | 10,700.00 | | 0047 | 735-01-00100 | Mailboxes | 3 | EACH | 200.00 | 600.00 | 35.00 | 105.00 | 26.50 | 79.50 | 150.00 | 450.00 | | 0048 | 735-02-00100 | Mailbox Supports (Single) | 3 | EACH | 200.00 | 600.00 | 250.00 | 750.00 | 330.00 | 990.00 | 150.00 | 450.00 | | 0049 | 739-01-00100 | Hydro-Seeding | 0.39 | ACRE | 10,000.00 | 3,900.00 | 7,200.00 | 2,808.00 | 13,200.00 | 5,148.00 | 10,000.00 | 3,900.00 | | 0050 | 740-01-00100 | Construction Layout | 1 | LUMP | 15,000.00 | 15,000.00 | 30,000.00 | 30,000.00 | 47,500.00 | 47,500.00 | 30,000.00 | 30,000.00 | | 0051 | 804-01-00400 | Precast Concrete Piles (18") | 1,740 | LNFT | 160.00 | 278,400.00 | 155.00 | 269,700.00 | 170.00 | 295,800.00 | 180.00 | 313,200.00 | | 0052 | 805-01-00100 | Class A1 Concrete (Slab Span) | 120.52 | CUYD | 2,500.00 | 301,300.00 | 1,600.00 | 192,832.00 | 2,655.00 | 319,980.60 | 2,600.00 | 313,352.00 | | 0053 | 805-01-00300 | Class A1 Concrete (Bent Cap) | 38.85 | CUYD | 3,250.00 | 126,262.50 | 2,900.00 | 112,665.00 | 4,660.00 | 181,041.00 | 3,950.00 | 153,457.50 | | 0054 | 805-18-00100 | Concrete Finish (Class 2 Rubbed Finish) | 1,114 | SQFT | 2.00 | 2,228.00 | 2.00 | 2,228.00 | 2.90 | 3,230.60 | 1.50 | 1,671.00 | | 0055 | 805-18-00200 | Concrete Finish (Class 3 Special Finish) | 1,114 | SQFT | 3.00 | 3,342.00 | 3.00 | 3,342.00 | 9.10 | 10,137.40 | 1.50 | 1,671.00 | | 0056 | 806-01-00100 | Deformed Reinforcing Steel | 29,097 | LB | 1.75 | 50,919.75 | 1.80 | 52,374.60 | 1.65 | 48,010.05 | 1.55 | 45,100.35 | | 0057 | 810-01-00120 | Concrete Bridge Railing (36 inch Height) | 160 | LNFT | 300.00 | 48,000.00 | 280.00 | 44,800.00 | 305.00 | 48,800.00 | 300.00 | 48,000.00 | | 0058 | 813-01-00100 | Concrete Approach Slabs (Cast-in-Place) | 1,200 | SQFT | 115.00 | 138,000.00 | 130.00 | 156,000.00 | 151.00 | 181,200.00 | 155.00 | 186,000.00 | | 0059 | 814-01-00100 | Elastomeric Bearing Pads (Non-Reinforced) | 96 | SFIN | 158.00 | 15,168.00 | 170.00 | 16,320.00 | 105.00 | 10,080.00 | 150.00 | 14,400.00 | | 0060 | 815-03-00300 | Joint Seal (Poured) | 150 | LNFT | 20.00 | 3,000.00 | 34.00 | 5,100.00 | 29.00 | 4,350.00 | 25.00 | 3,750.00 | | 0061 | NS-500-00240 | Sawing and Sealing Transverse Joints in Asphalt Concrete Overlay | 180 | LNFT | 20.00 | 3,600.00 | 25.00 | 4,500.00 | 30.00 | 5,400.00 | 3.50 | 630.00 | | 0062 | NS-500-00260 | Sawcuts in Asphalt Concrete Lifts | 300 | LNFT | 8.00 | 2,400.00 | 2.00 | 600.00 | 2.40 | 720.00 | 3.50 | 1,050.00 | | 0063 | NS-500-00340 | Saw Cutting Asphalt Concrete Pavement | 768 | INLF | 2.00 | 1,536.00 | 1.00 | 768.00 | 1.20 | 921.60 | 3.00 | 2,304.00 | | 0064 | NS-700-00840 | Impact Attenuator (Reusable, Test Level 3) | 2 | EACH | 48,000.00 | 96,000.00 | 32,000.00 | 64,000.00 | 40,500.00 | 81,000.00 | 60,000.00 | 120,000.00 | | 0065 | 202-01-00100 | Removal of Structures and Obstructions | 1 | LUMP | 5,000.00 | 5,000.00 | 11,000.00 | 11,000.00 | 6,500.00 | 6,500.00 | 12,000.00 | 12,000.00 | | | | | | | | | | | | | | | | | | CONTRACTOR TOTAL | | | | 1,972,263.08 | | 1,995,501.00 | | 2,326,538.14 | | 2,367,573.85 |
Line Number | Item Number | Item Description | Quantity | Unit of Measure | - 9 - JB JAMES CONSTRUCTION LLC | | Unit Price | Total Amount | | 0001 | 201-01-00100 | Clearing and Grubbing | 0.4 | LUMP | 360,000.00 | 360,000.00 | | 0003 | 202-02-02000 | Removal of Asphalt Drives | 113 | SQYD | 34.00 | 3,842.00 | | 0004 | 202-02-03030 | Removal of Pavement Structure | 112 | SQYD | 50.00 | 5,600.00 | | 0005 | 202-02-04501 | Removal of Bridge STR. NO. 625308532204401, 39' X 24' CONC. SLAB SPAN BRIDGE & TIMBER HEADWALL | 936 | LUMP | 360,000.00 | 360,000.00 | | 0006 | 202-02-12000 | Removal of Fence | 265 | LNFT | 6.00 | 1,590.00 | | 0007 | 202-02-14500 | Removal of Guard Rail | 164 | LNFT | 11.00 | 1,804.00 | | 0008 | 202-02-32120 | Removal of Pipe (Side Drain) CONCRETE 12" | 74 | LNFT | 40.00 | 2,960.00 | | 0009 | 202-02-32120 | Removal of Pipe (Side Drain) METAL 12" | 28 | LNFT | 60.00 | 1,680.00 | | 0010 | 202-02-32120 | Removal of Pipe (Side Drain) METAL 24" | 36 | LNFT | 42.00 | 1,512.00 | | 0011 | 203-01-00100 | General Excavation | 125 | CUYD | 70.00 | 8,750.00 | | 0012 | 203-02-00100 | Drainage Excavation | 340 | CUYD | 40.00 | 13,600.00 | | 0013 | 203-03-00100 | Embankment | 539 | CUYD | 80.00 | 43,120.00 | | 0014 | 204-02-00100 | Temporary Hay Bales | 49 | EACH | 35.00 | 1,715.00 | | 0015 | 204-06-00100 | Temporary Silt Fencing | 1,207 | LNFT | 8.00 | 9,656.00 | | 0016 | 401-02-00100 | Aggregate Surface Course (Adjusted Vehicular Measurement) | 7 | CUYD | 400.00 | 2,800.00 | | 0017 | 402-01-00101 | Traffic Maintenance Surfacing (Aggregate) (Vehicular Measurement) | 19 | CUYD | 250.00 | 4,750.00 | | 0018 | 502-01-00100 | Asphalt Concrete | 289.9 | TON | 260.00 | 75,374.00 | | 0019 | 502-01-00200 | Asphalt Concrete, Drives, Turnouts and Miscellaneous | 78.3 | TON | 340.00 | 26,622.00 | | 0020 | 509-01-00100 | Milling Asphalt Pavement | 1,184 | SQYD | 12.00 | 14,208.00 | | 0021 | 509-02-00100 | Contractor Retained Reclaimed Asphalt Pavement | -66 | CUYD | 0.01 | -0.66 | | 0022 | 510-01-00001 | Pavement Patching (14.4 inch minimum thickness) | 78 | SQYD | 250.00 | 19,500.00 | | 0023 | 510-02-00100 | Pavement Widening 12'' THICK | 324.2 | SQYD | 119.00 | 38,579.80 | | 0024 | 701-05-01049 | Side Drain Pipe (18" RCP/RPVCP/CPEPDW/CPPPDW) | 222 | LNFT | 150.00 | 33,300.00 | | 0025 | 701-05-01068 | Side Drain Pipe (24" RCP/RPVCP/CPEPDW/CPPPDW) | 254 | LNFT | 210.00 | 53,340.00 | | 0026 | 701-05-02067 | Side Drain Pipe (Erosion) (24" RPVCP/CPEPDW/CPPPDW) | 402 | LNFT | 150.00 | 60,300.00 | | 0027 | 701-17-00100 | Trench Excavation Safety Protection (Depth >5 feet) | 878 | LNFT | 0.10 | 87.80 | | 0028 | 702-03-00100 | Catch Basins (CB-01) | 7 | EACH | 6,000.00 | 42,000.00 | | 0029 | 702-08-00100 | Side Drain Safety End (Type 1) | 1 | EACH | 4,000.00 | 4,000.00 | | 0030 | 704-03-00200 | Blocked Out Guard Rail - 31", (6'-3" Post Spacing) | 112.5 | LNFT | 30.00 | 3,375.00 | | 0031 | 704-07-00200 | Guard Rail Transitions (Double Thrie Beam) | 50 | LNFT | 115.00 | 5,750.00 | | 0032 | 704-10-00205 | Guard Rail End Treatment, MASH, (TL-3 Tangent) | 2 | EACH | 3,300.00 | 6,600.00 | | 0033 | 705-01-00100 | Barbed Wire Fence | 265 | LNFT | 12.00 | 3,180.00 | | 0034 | 706-03-00300 | Incidental Concrete Paving (6" Thick) | 17.8 | SQYD | 300.00 | 5,340.00 | | 0035 | 708-01-00100 | Right-of-Way Monument | 8 | EACH | 650.00 | 5,200.00 | | 0036 | 708-02-00100 | Right-of-Way Monument Witness Post | 8 | EACH | 250.00 | 2,000.00 | | 0037 | 711-01-04000 | Riprap (55 lb, 18" Thick) | 888 | SQYD | 120.00 | 106,560.00 | | 0038 | 711-04-00100 | Geotextile Fabric | 888 | SQYD | 4.00 | 3,552.00 | | 0039 | 713-01-00100 | Temporary Signs and Barricades | 1 | LUMP | 44,000.00 | 44,000.00 | | 0040 | 716-01-00100 | Mulch (Vegetative) | 0.6 | TON | 3,500.00 | 2,100.00 | | 0041 | 726-01-00100 | Bedding Material | 5.6 | CUYD | 200.00 | 1,120.00 | | 0042 | 727-01-00100 | Mobilization | 1 | LUMP | 250,000.00 | 250,000.00 | | 0043 | 729-16-00300 | Object Marker Assembly (Type 3) | 4 | EACH | 90.00 | 360.00 | | 0044 | 731-01-00100 | Nonreflectorized Raised Pavement Markers | 206 | EACH | 15.00 | 3,090.00 | | 0045 | 731-02-00100 | Reflectorized Raised Pavement Markers | 29 | EACH | 10.00 | 290.00 | | 0046 | 732-02-02000 | Plastic Pavement Striping (Solid Line) (4" Width) (Thermoplastic 90 mil) | 0.428 | MILE | 6,500.00 | 2,782.00 | | 0047 | 735-01-00100 | Mailboxes | 3 | EACH | 25.00 | 75.00 | | 0048 | 735-02-00100 | Mailbox Supports (Single) | 3 | EACH | 250.00 | 750.00 | | 0049 | 739-01-00100 | Hydro-Seeding | 0.39 | ACRE | 11,000.00 | 4,290.00 | | 0050 | 740-01-00100 | Construction Layout | 1 | LUMP | 25,000.00 | 25,000.00 | | 0051 | 804-01-00400 | Precast Concrete Piles (18") | 1,740 | LNFT | 175.00 | 304,500.00 | | 0052 | 805-01-00100 | Class A1 Concrete (Slab Span) | 120.52 | CUYD | 1,300.00 | 156,676.00 | | 0053 | 805-01-00300 | Class A1 Concrete (Bent Cap) | 38.85 | CUYD | 2,400.00 | 93,240.00 | | 0054 | 805-18-00100 | Concrete Finish (Class 2 Rubbed Finish) | 1,114 | SQFT | 1.50 | 1,671.00 | | 0055 | 805-18-00200 | Concrete Finish (Class 3 Special Finish) | 1,114 | SQFT | 3.00 | 3,342.00 | | 0056 | 806-01-00100 | Deformed Reinforcing Steel | 29,097 | LB | 1.60 | 46,555.20 | | 0057 | 810-01-00120 | Concrete Bridge Railing (36 inch Height) | 160 | LNFT | 220.00 | 35,200.00 | | 0058 | 813-01-00100 | Concrete Approach Slabs (Cast-in-Place) | 1,200 | SQFT | 110.00 | 132,000.00 | | 0059 | 814-01-00100 | Elastomeric Bearing Pads (Non-Reinforced) | 96 | SFIN | 90.00 | 8,640.00 | | 0060 | 815-03-00300 | Joint Seal (Poured) | 150 | LNFT | 18.00 | 2,700.00 | | 0061 | NS-500-00240 | Sawing and Sealing Transverse Joints in Asphalt Concrete Overlay | 180 | LNFT | 25.08 | 4,514.40 | | 0062 | NS-500-00260 | Sawcuts in Asphalt Concrete Lifts | 300 | LNFT | 2.00 | 600.00 | | 0063 | NS-500-00340 | Saw Cutting Asphalt Concrete Pavement | 768 | INLF | 1.00 | 768.00 | | 0064 | NS-700-00840 | Impact Attenuator (Reusable, Test Level 3) | 2 | EACH | 40,000.00 | 80,000.00 | | 0065 | 202-01-00100 | Removal of Structures and Obstructions | 1 | LUMP | 8,354.80 | 8,354.80 | | | | | | | | | | | | CONTRACTOR TOTAL | | | | 2,544,865.34 |
|