Search


Bid Tabulations for the Letting of 10/15/2025 LA DOTD Headquarters

Proposal:H.013918.6
Parish:Caldwell, Catahoula, LaSalle
Routes:LA 126
Description:LA 126: LA 124 - LA 849 S.
Type Construction:CLEARING AND GRUBBING, MILLING ASPHALT CONCRETE, PAVEMENT PATCHING, ASPHALT CONCRETE OVERLAY, AND RELATED WORK.
Estimated Construction Cost:$5,000,776.74
Rank License BidderConstruction Bid
112487Diamond B Construction Co., L.L.C.$4,764,092.59
212312Gilchrist Construction Company, LLC$5,058,208.00
305789D & J CONSTRUCTION CO., LLC$5,900,531.90


Line
Number
Item NumberItem DescriptionQuantityUnit of
Measure
- 1 -
Diamond B Construction Co., L.L.C.
- 2 -
Gilchrist Construction Company, LLC
- 3 -
D & J CONSTRUCTION CO., LLC
Unit PriceTotal
Amount
Unit PriceTotal
Amount
Unit PriceTotal
Amount
0001201-01-00200Clearing and Grubbing (Selective) 25.2   LUMP145,250.00145,250.00200,000.00200,000.00250,000.00250,000.00
0002202-02-14500Removal of Guard Rail 1,436     LNFT14.0020,104.0015.0021,540.0035.0050,260.00
0003202-02-32100Removal of Pipe (Cross Drain) 24" RCP148     LNFT25.003,700.0050.007,400.0050.007,400.00
0004202-02-32100Removal of Pipe (Cross Drain) 24" RCP, 30" RCP60     LNFT25.001,500.0050.003,000.0050.003,000.00
0005203-07-00100Borrow (Vehicular Measurement) 422     CUYD35.0014,770.0050.0021,100.0050.0021,100.00
0006203-08-00100Geotextile Fabric 55     SQYD5.00275.003.00165.0010.00550.00
0007401-02-00100Aggregate Surface Course (Adjusted Vehicular Measurement) 2,631     CUYD110.00289,410.0080.00210,480.0095.00249,945.00
0008502-01-00100Asphalt Concrete 14,501.3   TON142.002,059,184.60150.002,175,195.00195.002,827,753.50
0009502-01-00200Asphalt Concrete, Drives, Turnouts and Miscellaneous 1,461.5   TON275.00401,912.50150.00219,225.00195.00284,992.50
0010509-01-00100Milling Asphalt Pavement 130,276     SQYD3.00390,828.003.00390,828.004.50586,242.00
0011509-02-00100Contractor Retained Reclaimed Asphalt Pavement -5,429     CUYD1.00-5,429.001.00-5,429.001.00-5,429.00
0012510-01-00001Pavement Patching 20" MINIMUM THICKNESS1,235     SQYD210.00259,350.00250.00308,750.00300.00370,500.00
0013701-05-02064Side Drain Pipe (Erosion) (24" RPVCP/CPEPDW) 200     LNFT125.0025,000.00150.0030,000.00150.0030,000.00
0014701-10-01060Reinforced Concrete Pipe (Extension) (24") 200     LNFT310.0062,000.00325.0065,000.00300.0060,000.00
0015701-10-01080Reinforced Concrete Pipe (Extension) (30") 32     LNFT355.0011,360.00325.0010,400.00325.0010,400.00
0016701-14-00100Cleaning Existing Pipes .52     LNFT40.002,080.0012.00624.0015.00780.00
0017701-15-00100Concrete Collar 29     EACH2,100.0060,900.003,000.0087,000.003,000.0087,000.00
0018704-01-01020Guard Rail (Single Thrie Beam) (6'-3" post spacing) 504     LNFT155.0078,120.00160.0080,640.00165.0083,160.00
0019704-03-00200Blocked Out Guard Rail - 31", (6'-3" Post Spacing) 475     LNFT35.0016,625.0040.0019,000.0040.0019,000.00
0020704-07-00200Guard Rail Transitions (Double Thrie Beam) 300     LNFT135.0040,500.00137.0041,100.00145.0043,500.00
0021704-10-00205Guard Rail End Treatment, MASH, (TL-3 Tangent) 12     EACH4,200.0050,400.004,200.0050,400.006,000.0072,000.00
0022704-10-00310Guard Rail End Treatment, NCHRP 350 - 31" (TL-3 Flared) 8     EACH3,800.0030,400.003,800.0030,400.005,500.0044,000.00
0023707-04-00100Asphalt Curb 162     LNFT76.0012,312.00100.0016,200.0020.003,240.00
0024711-01-04000Riprap (55 lb, 18" Thick) 22     SQYD230.005,060.00160.003,520.00200.004,400.00
0025711-01-05000Riprap (130 lb, 24" Thick) 33     SQYD260.008,580.00210.006,930.00250.008,250.00
0026713-01-00100Temporary Signs and Barricades 1     LUMP93,000.0093,000.00157,000.00157,000.00100,000.00100,000.00
0027713-03-01000Temporary Pavement Markings (Broken Line) (4" Width) (4' Length) 22.359 MILE154.003,443.29300.006,707.70300.006,707.70
0028713-03-02000Temporary Pavement Markings (Broken Line) (4" Width) (10' Length) 3.769 MILE700.002,638.30600.002,261.40800.003,015.20
0029713-04-01000Temporary Pavement Markings (Solid Line) (4" Width) 85.435 MILE900.0076,891.50700.0059,804.50900.0076,891.50
0030726-01-00100Bedding Material 86.5   CUYD180.0015,570.00200.0017,300.00175.0015,137.50
0031727-01-00100Mobilization 1     LUMP340,000.00340,000.00500,000.00500,000.00250,000.00250,000.00
0032729-16-00200Object Marker Assembly (Type 2) 46     EACH125.005,750.00130.005,980.00130.005,980.00
0033729-16-00300Object Marker Assembly (Type 3) 20     EACH135.002,700.00140.002,800.00140.002,800.00
0034731-02-00100Reflectorized Raised Pavement Markers 2,708     EACH5.0013,540.005.0013,540.007.5020,310.00
0035732-02-02000Plastic Pavement Striping (Solid Line) (4" Width) (Thermoplastic 90 mil) 42.718 MILE4,300.00183,687.404,200.00179,415.606,000.00256,308.00
0036732-03-02000Plastic Pavement Striping (Broken Line) (4" Width) (Thermoplastic 90 mil) 1.884 MILE1,300.002,449.201,300.002,449.202,000.003,768.00
0037732-03-02010Plastic Pavement Striping (Dotted Line)(4" W)(2' L)(Thermo 90 mil) 0.138 MILE9,100.001,255.80700.0096.6015,000.002,070.00
0038732-05-00100Removal of Existing Markings Bridge Decks and Approaches0.029 MILE15,000.00435.0025,000.00725.0015,000.00435.00
0039732-05-00100Removal of Existing Markings Bridge Locations0.048 MILE15,000.00720.0025,000.001,200.0015,000.00720.00
0040735-01-00100Mailboxes 39     EACH30.001,170.0040.001,560.0030.001,170.00
0041735-02-00100Mailbox Supports (Single) 31     EACH250.007,750.00300.009,300.00325.0010,075.00
0042735-03-00100Mailbox Supports (Double) 4     EACH350.001,400.00400.001,600.00400.001,600.00
0043739-01-00100Hydro-Seeding 0.05  ACRE50,000.002,500.0060,000.003,000.0030,000.001,500.00
0044740-01-00100Construction Layout 1     LUMP25,000.0025,000.00100,000.00100,000.0030,000.0030,000.00
           
  CONTRACTOR TOTAL   4,764,092.59 5,058,208.00 5,900,531.90