Bid Tabulations for the Letting of 10/15/2025 LA DOTD Headquarters

Proposal:H.010346.6
Parish:Natchitoches
Routes:LA 487
Description:LA 487: LA 120 - LA 174
Type Construction:BORROW, MILLING ASPHALT CONCRETE, LIME TREATMENT, IN-PLACE CEMENT TREATED SUBGRADE, IN-PLACE CEMENT TREATED BASE COURSE, DRAINAGE STRUCTURES, ASPHALT CONCRETE PAVEMENT, AND RELATED WORK.
Estimated Construction Cost:$8,377,017.85
Rank License BidderConstruction Bid
108584Madden Contracting Co., LLC$8,997,119.38
212312Gilchrist Construction Company, LLC$17,860,120.05


Line
Number
Item NumberItem DescriptionQuantityUnit of
Measure
- 1 -
Madden Contracting Co., LLC
- 2 -
Gilchrist Construction Company, LLC
Unit PriceTotal
Amount
Unit PriceTotal
Amount
0001202-01-00100Removal of Structures and Obstructions 1     LUMP5,000.005,000.00250,000.00250,000.00
0002202-02-02020Removal of Asphalt Pavement 274.3   SQYD13.003,565.9065.0017,829.50
0003202-02-04560Removal of Bridge Joint (Poured Joint Seal)(Recall #038322 and #038352)550     LNFT10.005,500.0040.0022,000.00
0004202-02-06100Removal of Concrete Walks and Drives 82     SQYD29.002,378.0040.003,280.00
0005202-02-14500Removal of Guard Rail 1,021     LNFT13.0013,273.0010.0010,210.00
0006203-07-00100Borrow (Vehicular Measurement) 1,315     CUYD30.0039,450.00100.00131,500.00
0007303-02-00100Removal of Existing Patches 300     SQYD20.006,000.0060.0018,000.00
0008303-03-00400In-Place Cement Treated Base Course (12" Thick) 134,612.2   SQYD12.151,635,538.2320.002,692,244.00
0009304-01-00100Lime 745.25  TON375.00279,468.75500.00372,625.00
0010304-03-00400Lime Treatment (Type C) (12" Thick) 39,431     SQYD6.00236,586.0015.00591,465.00
0011304-05-00100Lime Treatment (Type E) 39,431     SQYD2.0078,862.0015.00591,465.00
0012309-01-12000In-Place Cement Treated Subgrade (12" Thick) 39,431     SQYD11.50453,456.5025.00985,775.00
0013401-02-00100Aggregate Surface Course (Adjusted Vehicular Measurement) 3,143     CUYD56.50177,579.50100.00314,300.00
0014502-01-00100Asphalt Concrete 25,195.5   TON135.503,413,990.25250.006,298,875.00
0015502-01-00200Asphalt Concrete, Drives, Turnouts and Miscellaneous 3,422.7   TON90.00308,043.00250.00855,675.00
0016509-01-00100Milling Asphalt Pavement 118,134     SQYD6.75797,404.508.00945,072.00
0017509-02-00100Contractor Retained Reclaimed Asphalt Pavement -9,615     CUYD0.10-961.500.01-96.15
0018701-01-01003Cross Drain Pipe (24" RCP/RPVCP/CPEPDW) 104     LNFT140.0014,560.00750.0078,000.00
0019701-01-01082Cross Drain Pipe (48" RCP/RPVCP/CPEPDW) 144     LNFT223.0032,112.001,100.00158,400.00
0020701-08-00100Relaying Pipe (36")64     LNFT103.006,592.00500.0032,000.00
0021701-10-01060Reinforced Concrete Pipe (Extension) (24") 24     LNFT230.005,520.00450.0010,800.00
0022701-10-01140Reinforced Concrete Pipe (Extension) (48") 48     LNFT300.0014,400.00750.0036,000.00
0023701-15-00100Concrete Collar 17     EACH1,050.0017,850.005,000.0085,000.00
0024701-17-00100Trench Excavation Safety Protection (Depth >5 feet) 206     LNFT5.001,030.0060.0012,360.00
0025702-05-01000Cross Drain End Treatment (1 Barrel, 24" RCP or 30" CMP) 2     EACH4,400.008,800.0075,000.00150,000.00
0026704-01-01020Guard Rail (Single Thrie Beam) (6'-3" post spacing) 160     LNFT70.0011,200.0050.008,000.00
0027704-03-00200Blocked Out Guard Rail - 31", (6'-3" Post Spacing) 418.8   LNFT35.0014,658.0035.0014,658.00
0028704-06-00200Guard Rail Bridge Attachments (Single Thrie Beam) 100     LNFT80.008,000.0075.007,500.00
0029704-07-00200Guard Rail Transitions (Double Thrie Beam) 300     LNFT135.0040,500.00125.0037,500.00
0030704-10-00205Guard Rail End Treatment, MASH, (TL-3 Tangent) 4     EACH4,200.0016,800.003,500.0014,000.00
0031704-10-00310Guard Rail End Treatment, NCHRP 350 - 31" (TL-3 Flared) 8     EACH3,800.0030,400.003,500.0028,000.00
0032707-04-00100Asphalt Curb 54     LNFT100.005,400.00130.007,020.00
0033711-01-04000Riprap (55 lb, 18" Thick) 60     SQYD140.008,400.00600.0036,000.00
0034711-04-00100Geotextile Fabric 60     SQYD3.00180.004.00240.00
0035713-01-00100Temporary Signs and Barricades 1     LUMP418,500.00418,500.00500,000.00500,000.00
0036713-03-01000Temporary Pavement Markings (Broken Line) (4" Width) (4' Length) 29.562 MILE300.008,868.60500.0014,781.00
0037713-03-02000Temporary Pavement Markings (Broken Line) (4" Width) (10' Length) 10.446 MILE600.006,267.60700.007,312.20
0038713-04-01000Temporary Pavement Markings (Solid Line) (4" Width) 106.858 MILE850.0090,829.301,000.00106,858.00
0039722-02-00100Project Site Laboratory (Equipped) 1     EACH10,000.0010,000.0050,000.0050,000.00
0040724-02-00100Rumble Strips (Shoulder/Edge) 19.615 MILE1,000.0019,615.002,000.0039,230.00
0041726-01-00100Bedding Material 89.5   CUYD140.0012,530.00300.0026,850.00
0042727-01-00100Mobilization 1     LUMP418,500.00418,500.001,700,000.001,700,000.00
0043729-16-00200Object Marker Assembly (Type 2) 16     EACH75.001,200.00125.002,000.00
0044729-16-00300Object Marker Assembly (Type 3) 12     EACH135.001,620.00100.001,200.00
0045731-02-00100Reflectorized Raised Pavement Markers 2,200     EACH5.5012,100.006.0013,200.00
0046732-02-02000Plastic Pavement Striping (Solid Line) (4" Width) (Thermoplastic 90 mil) 35.909 MILE5,500.00197,499.506,000.00215,454.00
0047732-03-02000Plastic Pavement Striping (Broken Line) (4" Width) (Thermoplastic 90 mil) 3.497 MILE2,800.009,791.603,500.0012,239.50
0048732-05-00100Removal of Existing Markings 0.051 MILE7,500.00382.50100,000.005,100.00
0049735-01-00100Mailboxes 67     EACH20.001,340.0035.002,345.00
0050735-02-00100Mailbox Supports (Single) 61     EACH305.0018,605.00300.0018,300.00
0051735-03-00100Mailbox Supports (Double) 3     EACH400.001,200.00350.001,050.00
0052739-01-00100Hydro-Seeding 7.133 ACRE3,750.0026,748.753,000.0021,399.00
0053815-03-00300Joint Seal (Poured) 550     LNFT37.7320,751.5050.0027,500.00
0054NS-500-00240Sawing and Sealing Transverse Joints in Asphalt Concrete Overlay 120     LNFT9.501,140.0050.006,000.00
0055NS-500-00260Sawcuts in Asphalt Concrete Lifts 120     LNFT5.00600.0050.006,000.00
0056NS-600-00220Saw Cutting Portland Cement Concrete Pavement 2,934     INLF0.852,493.906.0017,604.00
0057740-01-00100Construction Layout 1     LUMP25,000.0025,000.00250,000.00250,000.00
         
  CONTRACTOR TOTAL   8,997,119.38 17,860,120.05