Proposal:H.016008.6
Parish:Calcasieu
Routes:LA 3256, US 90
Description:US 90 & LA 3256: ASPHALT OVERLAYS
Type Construction:DRAINAGE STRUCTURES, MILLING ASPHALT CONCRETE, PAVEMENT PATCHING, ASPHALT CONCRETE OVERLAY, HOT-MIX ASPHALT AGGREGATE SURFACE COURSE, AND RELATED WORK.
Estimated Construction Cost:$1,745,348.10
Rank | License | Bidder | Construction Bid |
1 | 00183 | R. E. Heidt Construction Co., LLC | $1,996,753.58 |
2 | 34356 | Prairie Contractors LLC | $2,240,901.73 |
Line Number | Item Number | Item Description | Quantity | Unit of Measure | - 1 - R. E. Heidt Construction Co., LLC | - 2 - Prairie Contractors LLC | Unit Price | Total Amount | Unit Price | Total Amount | 0001 | 202-01-00100 | Removal of Structures and Obstructions | 1 | LUMP | 6,918.50 | 6,918.50 | 2,500.00 | 2,500.00 | 0002 | 401-02-00100 | Aggregate Surface Course (Adjusted Vehicular Measurement) | 20 | CUYD | 385.00 | 7,700.00 | 250.00 | 5,000.00 | 0003 | 402-01-00101 | Traffic Maintenance Surfacing (Aggregate) (Vehicular Measurement) | 21.8 | CUYD | 191.90 | 4,183.42 | 150.00 | 3,270.00 | 0004 | 502-01-00100 | Asphalt Concrete | 5,675.4 | TON | 138.00 | 783,205.20 | 141.00 | 800,231.40 | 0005 | 502-01-00200 | Asphalt Concrete, Drives, Turnouts and Miscellaneous | 352.6 | TON | 230.00 | 81,098.00 | 311.00 | 109,658.60 | 0006 | 509-01-00100 | Milling Asphalt Pavement | 40,113 | SQYD | 5.00 | 200,565.00 | 5.25 | 210,593.25 | 0007 | 509-02-00100 | Contractor Retained Reclaimed Asphalt Pavement | -1,662 | CUYD | 0.01 | -16.62 | 0.01 | -16.62 | 0008 | 510-01-00100 | Pavement Patching (6" Minimum Thickness) | 19 | SQYD | 268.00 | 5,092.00 | 500.00 | 9,500.00 | 0009 | 510-01-00250 | Pavement Patching (14 inch Minimum Thickness) | 1,456 | SQYD | 140.00 | 203,840.00 | 152.00 | 221,312.00 | 0010 | 510-01-00260 | Pavement Patching (16 inch Minimum Thickness) | 803 | SQYD | 160.00 | 128,480.00 | 185.00 | 148,555.00 | 0011 | 701-02-01000 | Cross Drain Pipe Arch (24" Equiv. RCPA) | 40 | LNFT | 303.00 | 12,120.00 | 500.00 | 20,000.00 | 0012 | 702-04-00150 | Adjusting Manholes w/Manhole Adjustment Rings | 8 | EACH | 800.00 | 6,400.00 | 1,500.00 | 12,000.00 | 0013 | 710-01-00100 | Flowable Fill | 14 | CUYD | 404.00 | 5,656.00 | 300.00 | 4,200.00 | 0014 | 713-01-00100 | Temporary Signs and Barricades | 1 | LUMP | 65,000.00 | 65,000.00 | 176,000.00 | 176,000.00 | 0015 | 713-02-00300 | Temporary Pavement Markings (8" Width) | 2,086 | LNFT | 0.51 | 1,063.86 | 0.01 | 20.86 | 0016 | 713-02-00500 | Temporary Pavement Markings (24" Width) | 798 | LNFT | 1.01 | 805.98 | 0.01 | 7.98 | 0017 | 713-03-01000 | Temporary Pavement Markings (Broken Line) (4" Width) (4' Length) | 7.884 | MILE | 850.00 | 6,701.40 | 1.00 | 7.88 | 0018 | 713-03-02000 | Temporary Pavement Markings (Broken Line) (4" Width) (10' Length) | 3.928 | MILE | 656.50 | 2,578.73 | 1.00 | 3.93 | 0019 | 713-04-01000 | Temporary Pavement Markings (Solid Line) (4" Width) | 17.6 | MILE | 909.00 | 15,998.40 | 1.00 | 17.60 | 0020 | 713-05-00200 | Temporary Pavement Legends & Symbols (Arrow - Double) | 2 | EACH | 50.50 | 101.00 | 1.00 | 2.00 | 0021 | 713-05-00220 | Temporary Pavement Legends & Symbols (Arrow - Left Turn) | 8 | EACH | 50.50 | 404.00 | 1.00 | 8.00 | 0022 | 713-05-00230 | Temporary Pavement Legends & Symbols (Arrow - Right Turn) | 2 | EACH | 50.50 | 101.00 | 1.00 | 2.00 | 0023 | 713-05-00240 | Temporary Pavement Legends & Symbols (Arrow - Merge) | 4 | EACH | 50.50 | 202.00 | 1.00 | 4.00 | 0024 | 713-05-00400 | Temporary Pavement Legends & Symbols (RR Crossing) | 8 | EACH | 101.00 | 808.00 | 1.00 | 8.00 | 0025 | 724-01-00100 | Rumble Strips (Centerline) | 0.612 | MILE | 1,313.00 | 803.56 | 1,500.00 | 918.00 | 0026 | 724-02-00100 | Rumble Strips (Shoulder/Edge) | 1.224 | MILE | 1,313.00 | 1,607.11 | 1,500.00 | 1,836.00 | 0027 | 726-01-00100 | Bedding Material | 4.6 | CUYD | 303.00 | 1,393.80 | 175.00 | 805.00 | 0028 | 727-01-00100 | Mobilization | 1 | LUMP | 212,000.00 | 212,000.00 | 230,000.00 | 230,000.00 | 0029 | 729-16-00200 | Object Marker Assembly (Type 2) | 2 | EACH | 45.45 | 90.90 | 90.00 | 180.00 | 0030 | 731-02-00100 | Reflectorized Raised Pavement Markers | 1,030 | EACH | 6.06 | 6,241.80 | 8.00 | 8,240.00 | 0031 | 732-01-01040 | Plastic Pavement Striping (8" Width) (Thermoplastic 90 mil) | 250 | LNFT | 3.03 | 757.50 | 4.00 | 1,000.00 | 0032 | 732-01-02040 | Plastic Pavement Striping (8" Width) (Thermoplastic 125 mil) | 668 | LNFT | 3.29 | 2,197.72 | 4.00 | 2,672.00 | 0033 | 732-01-02080 | Plastic Pavement Striping (24" Width) (Thermoplastic 125 mil) | 306 | LNFT | 13.64 | 4,173.84 | 18.00 | 5,508.00 | 0034 | 732-01-05000 | Plastic Pavement Striping (Dotted Line)(4" W)(2' L)(Thermo 125 mil) | 301 | LNFT | 1.01 | 304.01 | 1.25 | 376.25 | 0035 | 732-02-02000 | Plastic Pavement Striping (Solid Line) (4" Width) (Thermoplastic 90 mil) | 6.656 | MILE | 5,252.00 | 34,957.31 | 6,500.00 | 43,264.00 | 0036 | 732-03-02000 | Plastic Pavement Striping (Broken Line) (4" Width) (Thermoplastic 90 mil) | 1.528 | MILE | 3,838.00 | 5,864.46 | 4,750.00 | 7,258.00 | 0037 | 732-03-02012 | Plastic Pavement Striping (Dotted Line)(4" W)(3' L)(Thermo 90 mil) | 0.086 | MILE | 505.00 | 43.43 | 600.00 | 51.60 | 0038 | 732-04-01040 | Plastic Pavement Legends and Symbols (Arrow - Double) | 1 | EACH | 303.00 | 303.00 | 400.00 | 400.00 | 0039 | 732-04-01080 | Plastic Pavement Legends and Symbols (Arrow - Left Turn) | 4 | EACH | 303.00 | 1,212.00 | 400.00 | 1,600.00 | 0040 | 732-04-01100 | Plastic Pavement Legends and Symbols (Arrow - Right Turn) | 1 | EACH | 505.00 | 505.00 | 600.00 | 600.00 | 0041 | 732-04-01120 | Plastic Pavement Legends and Symbols (Arrow - Merge) | 2 | EACH | 505.00 | 1,010.00 | 600.00 | 1,200.00 | 0042 | 732-04-18000 | Plastic Pavement Legends and Symbols (RR Crossing) | 3 | EACH | 101.00 | 303.00 | 200.00 | 600.00 | 0043 | 732-05-00100 | Removal of Existing Markings | 0.022 | MILE | 8,585.00 | 188.87 | 10,000.00 | 220.00 | 0044 | 735-01-00100 | Mailboxes | 15 | EACH | 20.20 | 303.00 | 10.00 | 150.00 | 0045 | 735-02-00100 | Mailbox Supports (Single) | 11 | EACH | 141.40 | 1,555.40 | 550.00 | 6,050.00 | 0046 | 735-03-00100 | Mailbox Supports (Double) | 2 | EACH | 151.50 | 303.00 | 600.00 | 1,200.00 | 0047 | 740-01-00100 | Construction Layout | 1 | LUMP | 15,000.00 | 15,000.00 | 25,000.00 | 25,000.00 | 0048 | NS-401-00100 | Hot-Mix Asphalt Aggregate Surface Course | 1,381 | TON | 120.00 | 165,720.00 | 127.00 | 175,387.00 | 0049 | NS-MSC-00080 | Detectable Warning Surface Retrofit for Curb Ramps | 1 | EACH | 909.00 | 909.00 | 3,500.00 | 3,500.00 | | | | | | | | | | | | CONTRACTOR TOTAL | | | | 1,996,753.58 | | 2,240,901.73 |
|