Bid Tabulations for the Letting of 8/13/2025 LA DOTD Headquarters

Proposal:H.015866.6
Parish:Lafayette
Routes:LA 720
Description:LA 720: LA 719 - LA 343
Type Construction:CLEARING AND GRUBBING, DRAINAGE STRUCTURES, MILLING ASPHALT CONCRETE, LIME TREATMENT, IN-PLACE CEMENT STABILIZED BASE, ASPHALT CONCRETE OVERLAY, AND RELATED WORK.
Estimated Construction Cost:$2,736,016.98
Rank License BidderConstruction Bid
151821Elliott Construction, LLC$2,503,942.51
234356Prairie Contractors LLC$2,558,152.22
333663Glenn Lege Construction LLC$2,767,951.80
446747Triumph Construction, LLC$4,711,918.12


Line
Number
Item NumberItem DescriptionQuantityUnit of
Measure
- 1 -
Elliott Construction, LLC
- 2 -
Prairie Contractors LLC
- 3 -
Glenn Lege Construction LLC
- 4 -
Triumph Construction, LLC
Unit PriceTotal
Amount
Unit PriceTotal
Amount
Unit PriceTotal
Amount
Unit PriceTotal
Amount
0001202-02-02000Removal of Asphalt Drives 99     SQYD25.002,475.0080.007,920.0055.075,451.9363.006,237.00
0002202-02-06100Removal of Concrete Walks and Drives 79     SQYD55.004,345.0040.003,160.0059.844,727.3642.003,318.00
0003202-02-32100Removal of Pipe (Cross Drain) (24" RCP) (29"x18" CMPA)69     LNFT50.003,450.0035.002,415.0095.036,557.0721.001,449.00
0004203-07-00100Borrow (Vehicular Measurement) 198     CUYD65.0012,870.0020.003,960.00139.2527,571.5078.0015,444.00
0005204-05-00100Temporary Sediment Check Dams (Hay) 30     EACH155.004,650.00200.006,000.00174.235,226.90131.003,930.00
0006303-01-00200In-Place Cement Stabilized Base Course (8-1/2" Thick) 30,999     SQYD12.00371,988.0014.00433,986.008.93276,821.0716.00495,984.00
0007303-02-00100Removal of Existing Patches 100     SQYD20.002,000.00100.0010,000.00137.8713,787.0063.006,300.00
0008304-01-00100Lime 109.21  TON360.0039,315.60500.0054,605.00295.8432,308.69981.00107,135.01
0009304-03-00400Lime Treatment (Type C) (12" Thick) 7,750     SQYD7.0054,250.0011.0085,250.0010.5081,375.0012.0093,000.00
0010309-01-12000In-Place Cement Treated Subgrade (12" Thick) 30,999     SQYD15.00464,985.0012.50387,487.5012.37383,457.6321.00650,979.00
0011401-02-00100Aggregate Surface Course (Adjusted Vehicular Measurement) 1,052     CUYD75.0078,900.0043.0045,236.0094.2799,172.0459.0062,068.00
0012402-01-00101Traffic Maintenance Surfacing (Aggregate) (Vehicular Measurement) 100     CUYD100.0010,000.0050.005,000.0098.489,848.0075.007,500.00
0013502-01-00100Asphalt Concrete 6,373.5   TON135.00860,422.50120.00764,820.00136.80871,894.80254.001,618,869.00
0014502-01-00200Asphalt Concrete, Drives, Turnouts and Miscellaneous 599.7   TON195.00116,941.50230.00137,931.00187.99112,737.60254.00152,323.80
0015509-01-00100Milling Asphalt Pavement 12,275     SQYD3.5042,962.5015.32188,053.004.4554,623.7510.00122,750.00
0016509-02-00100Contractor Retained Reclaimed Asphalt Pavement -767     CUYD0.01-7.670.01-7.670.01-7.670.07-53.69
0017510-01-00250Pavement Patching (14 inch Minimum Thickness) 27     SQYD250.006,750.00350.009,450.00409.1311,046.51218.005,886.00
0018701-01-01001Cross Drain Pipe (24" RCP) 4     LNFT550.002,200.00450.001,800.00380.651,522.60368.001,472.00
0019701-02-01000Cross Drain Pipe Arch (24" Equiv. RCPA) 64     LNFT335.0021,440.00500.0032,000.00206.8813,240.3279.005,056.00
0020701-15-00100Concrete Collar 1     EACH2,550.002,550.003,500.003,500.001,444.301,444.30620.00620.00
0021706-02-00200Concrete Drive (6" Thick) 79     SQYD165.0013,035.00275.0021,725.0082.236,496.1772.005,688.00
0022712-02-00100Sacked Concrete Revetment 2     SQYD1,500.003,000.00800.001,600.003,807.707,615.40280.00560.00
0023712-04-00100Flexible Revetment 3     SQYD650.001,950.00250.00750.001,181.703,545.103,080.009,240.00
0024713-01-00100Temporary Signs and Barricades 1     LUMP60,000.0060,000.0020,000.0020,000.00223,032.75223,032.7515,010.0015,010.00
0025713-02-00500Temporary Pavement Markings (24" Width) 66     LNFT1.75115.500.010.661.75115.5019.001,254.00
0026713-03-01000Temporary Pavement Markings (Broken Line) (4" Width) (4' Length) 6.018 MILE800.004,814.401.006.02787.804,740.98770.004,633.86
0027713-03-02000Temporary Pavement Markings (Broken Line) (4" Width) (10' Length) 6.018 MILE660.003,971.881.006.02696.904,193.94885.005,325.93
0028713-04-01000Temporary Pavement Markings (Solid Line) (4" Width) 13.44  MILE880.0011,827.201.0013.44929.2012,488.451,009.0013,560.96
0029722-02-00100Project Site Laboratory (Equipped) 1     EACH10,000.0010,000.0030,000.0030,000.0010,110.1010,110.1039,200.0039,200.00
0030724-02-00100Rumble Strips (Shoulder/Edge) 4.035 MILE1,100.004,438.501,250.005,043.751,161.504,686.65868.003,502.38
0031726-01-00100Bedding Material 5.9   CUYD200.001,180.00185.001,091.50151.00890.90407.002,401.30
0032727-01-00100Mobilization 1     LUMP200,000.00200,000.00185,000.00185,000.00252,096.00252,096.00455,950.00455,950.00
0033729-16-00200Object Marker Assembly (Type 2) 12     EACH85.001,020.0095.001,140.00144.431,733.1687.001,044.00
0034731-02-00100Reflectorized Raised Pavement Markers 269     EACH5.501,479.508.002,152.005.811,562.8912.003,228.00
0035732-01-01080Plastic Pavement Striping (24" Width) (Thermoplastic 90 mil) 22     LNFT22.00484.0016.00352.0023.23511.0665.001,430.00
0036732-02-02000Plastic Pavement Striping (Solid Line) (4" Width) (Thermoplastic 90 mil) 4.48  MILE4,400.0019,712.006,500.0029,120.004,646.0020,814.086,603.0029,581.44
0037732-03-02000Plastic Pavement Striping (Broken Line) (4" Width) (Thermoplastic 90 mil) 2.006 MILE1,100.002,206.603,500.007,021.001,161.502,329.973,116.006,250.70
0038735-01-00100Mailboxes 63     EACH25.001,575.0010.00630.0030.201,902.6024.001,512.00
0039735-02-00100Mailbox Supports (Single) 63     EACH275.0017,325.00350.0022,050.00296.1818,659.34289.0018,207.00
0040739-01-00100Hydro-Seeding 0.73  ACRE3,850.002,810.508,500.006,205.004,065.252,967.632,891.002,110.43
0041740-01-00100Construction Layout 1     LUMP10,000.0010,000.001,000.001,000.00141,264.62141,264.6227,180.0027,180.00
0042NS-MSC-18080Root Barrier 1,017     LNFT30.0030,510.0040.0040,680.0032.8333,388.11693.00704,781.00
             
  CONTRACTOR TOTAL   2,503,942.51 2,558,152.22 2,767,951.80 4,711,918.12