Proposal:H.015328.6
Parish:Sabine
Routes:LA 120
Description: LA 120: US 171 - ANGELA LANE
Type Construction:MILLING ASPHALT PAVEMENT, PAVEMENT PATCHING, PAVEMENT WIDENING, ASPHALT CONCRETE OVERLAY, AND RELATED WORK.
Estimated Construction Cost:$1,272,358.03
Rank | License | Bidder | Construction Bid |
1 | 08584 | Madden Contracting Co., LLC | $1,771,236.75 |
Line Number | Item Number | Item Description | Quantity | Unit of Measure | - 1 - Madden Contracting Co., LLC | Unit Price | Total Amount | 0001 | 202-02-32100 | Removal of Pipe (Cross Drain) 30" RCP | 42 | LNFT | 25.00 | 1,050.00 | 0002 | 203-07-00100 | Borrow (Vehicular Measurement) | 132 | CUYD | 137.50 | 18,150.00 | 0003 | 203-10-00100 | Cleaning Existing Ditches | 125 | LNFT | 16.00 | 2,000.00 | 0004 | 204-05-00100 | Temporary Sediment Check Dams (Hay) | 7 | EACH | 250.00 | 1,750.00 | 0005 | 204-06-00100 | Temporary Silt Fencing | 100 | LNFT | 10.00 | 1,000.00 | 0006 | 401-02-00100 | Aggregate Surface Course (Adjusted Vehicular Measurement) | 431 | CUYD | 140.00 | 60,340.00 | 0007 | 502-01-00100 | Asphalt Concrete | 3,589 | TON | 174.00 | 624,486.00 | 0008 | 502-01-00200 | Asphalt Concrete, Drives, Turnouts and Miscellaneous | 464.4 | TON | 100.00 | 46,440.00 | 0009 | 509-01-00100 | Milling Asphalt Pavement | 21,901 | SQYD | 7.00 | 153,307.00 | 0010 | 509-02-00100 | Contractor Retained Reclaimed Asphalt Pavement | -870 | CUYD | 0.10 | -87.00 | 0011 | 510-01-00200 | Pavement Patching (12" Minimum Thickness) | 946 | SQYD | 145.50 | 137,643.00 | 0012 | 510-02-00100 | Pavement Widening (24" THICKNESS) | 711.1 | SQYD | 365.00 | 259,551.50 | 0013 | 701-02-02040 | Cross Drain Pipe Arch (30" Equiv. RCPA or 36" Equiv. CMPA) | 40 | LNFT | 425.00 | 17,000.00 | 0014 | 701-17-00100 | Trench Excavation Safety Protection (Depth >5 feet) | 34 | LNFT | 5.00 | 170.00 | 0015 | 713-01-00100 | Temporary Signs and Barricades | 1 | LUMP | 173,000.00 | 173,000.00 | 0016 | 713-03-01000 | Temporary Pavement Markings (Broken Line) (4" Width) (4' Length) | 4.366 | MILE | 300.00 | 1,309.80 | 0017 | 713-03-02000 | Temporary Pavement Markings (Broken Line) (4" Width) (10' Length) | 3.499 | MILE | 600.00 | 2,099.40 | 0018 | 713-04-01000 | Temporary Pavement Markings (Solid Line) (4" Width) | 13.817 | MILE | 850.00 | 11,744.45 | 0019 | 716-01-00100 | Mulch (Vegetative) | 3.36 | TON | 1,500.00 | 5,040.00 | 0020 | 717-01-00100 | Seeding | 134.4 | LB | 20.00 | 2,688.00 | 0021 | 718-01-00100 | Fertilizer | 1,680 | LB | 1.50 | 2,520.00 | 0022 | 726-01-00100 | Bedding Material | 10.7 | CUYD | 138.00 | 1,476.60 | 0023 | 727-01-00100 | Mobilization | 1 | LUMP | 173,000.00 | 173,000.00 | 0024 | 729-16-00200 | Object Marker Assembly (Type 2) | 2 | EACH | 150.00 | 300.00 | 0025 | 731-02-00100 | Reflectorized Raised Pavement Markers | 480 | EACH | 6.00 | 2,880.00 | 0026 | 732-01-02080 | Plastic Pavement Striping (24" Width) (Thermoplastic 125 mil) | 15 | LNFT | 15.00 | 225.00 | 0027 | 732-02-02000 | Plastic Pavement Striping (Solid Line) (4" Width) (Thermoplastic 90 mil) | 5.526 | MILE | 5,500.00 | 30,393.00 | 0028 | 732-03-02000 | Plastic Pavement Striping (Broken Line) (4" Width) (Thermoplastic 90 mil) | 1.4 | MILE | 2,800.00 | 3,920.00 | 0029 | 735-01-00100 | Mailboxes | 23 | EACH | 20.00 | 460.00 | 0030 | 735-02-00100 | Mailbox Supports (Single) | 21 | EACH | 320.00 | 6,720.00 | 0031 | 735-03-00100 | Mailbox Supports (Double) | 1 | EACH | 420.00 | 420.00 | 0032 | 740-01-00100 | Construction Layout | 1 | LUMP | 30,000.00 | 30,000.00 | 0033 | NS-500-00340 | Saw Cutting Asphalt Concrete Pavement | 24,000 | INLF | 0.01 | 240.00 | | | | | | | | | | CONTRACTOR TOTAL | | | | 1,771,236.75 |
|