Proposal:H.014891.6
Parish:Rapides
Routes:LA 1207
Description:LA 1207: LA 115 TO LA 28
Type Construction:BORROW, DRAINAGE STRUCTURES, MILLING ASPHALT CONCRETE, PAVEMENT PATCHING, PAVEMENT WIDENING, ASPHALT SURFACE TREATMENT, ASPHALT CONCRETE OVERLAY, AND RELATED WORK.
Estimated Construction Cost:$4,622,671.74
Rank | License | Bidder | Construction Bid |
1 | 12487 | Diamond B Construction Co., L.L.C. | $4,542,400.19 |
2 | 12312 | Gilchrist Construction Company, LLC | $4,708,730.96 |
Line Number | Item Number | Item Description | Quantity | Unit of Measure | - 1 - Diamond B Construction Co., L.L.C. | - 2 - Gilchrist Construction Company, LLC | Unit Price | Total Amount | Unit Price | Total Amount | 0001 | 202-01-00100 | Removal of Structures and Obstructions | 1 | LUMP | 6,000.00 | 6,000.00 | 16,500.00 | 16,500.00 | 0002 | 202-02-02020 | Removal of Asphalt Pavement | 409 | SQYD | 49.00 | 20,041.00 | 14.00 | 5,726.00 | 0003 | 202-02-06102 | Removal of Incidental Concrete Paving | 27 | SQYD | 35.00 | 945.00 | 100.00 | 2,700.00 | 0004 | 202-02-14500 | Removal of Guard Rail | 914 | LNFT | 14.00 | 12,796.00 | 9.00 | 8,226.00 | 0005 | 203-07-00100 | Borrow (Vehicular Measurement) | 625 | CUYD | 20.00 | 12,500.00 | 75.00 | 46,875.00 | 0006 | 204-05-00100 | Temporary Sediment Check Dams (Hay) | 4 | EACH | 200.00 | 800.00 | 151.00 | 604.00 | 0007 | 204-06-00100 | Temporary Silt Fencing | 50 | LNFT | 10.00 | 500.00 | 2.10 | 105.00 | 0008 | 401-02-00100 | Aggregate Surface Course (Adjusted Vehicular Measurement) | 1,273 | CUYD | 50.00 | 63,650.00 | 75.00 | 95,475.00 | 0009 | 402-01-00101 | Traffic Maintenance Surfacing (Aggregate) (Vehicular Measurement) | 30 | CUYD | 126.00 | 3,780.00 | 100.00 | 3,000.00 | 0010 | 502-01-00100 | Asphalt Concrete | 14,722.4 | TON | 130.00 | 1,913,912.00 | 125.00 | 1,840,300.00 | 0011 | 502-01-00200 | Asphalt Concrete, Drives, Turnouts and Miscellaneous | 861.9 | TON | 265.00 | 228,403.50 | 125.00 | 107,737.50 | 0012 | 507-01-00100 | Asphalt Material (CRS-2P Emulsion) | 46,270 | GAL | 4.50 | 208,215.00 | 4.50 | 208,215.00 | 0013 | 507-02-00200 | Aggregate (S2) | 68,044 | SQYD | 2.00 | 136,088.00 | 2.25 | 153,099.00 | 0014 | 507-02-00300 | Aggregate (S3) | 68,044 | SQYD | 1.35 | 91,859.40 | 1.40 | 95,261.60 | 0015 | 509-01-00100 | Milling Asphalt Pavement | 65,815 | SQYD | 2.55 | 167,828.25 | 3.00 | 197,445.00 | 0016 | 509-02-00100 | Contractor Retained Reclaimed Asphalt Pavement | -3,400 | CUYD | 1.00 | -3,400.00 | 1.19 | -4,046.00 | 0017 | 510-01-00300 | Pavement Patching (18" Minimum Thickness) | 4,108 | SQYD | 185.00 | 759,980.00 | 200.00 | 821,600.00 | 0018 | 510-02-00100 | Pavement Widening (24" Thickness) | 222.2 | SQYD | 186.00 | 41,329.20 | 200.00 | 44,440.00 | 0019 | 701-02-01040 | Cross Drain Pipe Arch (36" Equiv. RCPA) | 80 | LNFT | 400.00 | 32,000.00 | 600.00 | 48,000.00 | 0020 | 701-17-00100 | Trench Excavation Safety Protection (Depth >5 feet) | 37 | LNFT | 20.00 | 740.00 | 20.00 | 740.00 | 0021 | 704-01-01000 | Guard Rail (Single Thrie Beam) (3'-1 1/2" post spacing) | 225 | LNFT | 185.00 | 41,625.00 | 180.00 | 40,500.00 | 0022 | 704-01-01020 | Guard Rail (Single Thrie Beam) (6'-3" post spacing) | 180 | LNFT | 150.00 | 27,000.00 | 100.00 | 18,000.00 | 0023 | 704-03-00200 | Blocked Out Guard Rail - 31", (6'-3" Post Spacing) | 281.25 | LNFT | 35.00 | 9,843.75 | 35.00 | 9,843.75 | 0024 | 704-10-00205 | Guard Rail End Treatment, MASH, (TL-3 Tangent) | 8 | EACH | 4,100.00 | 32,800.00 | 3,800.00 | 30,400.00 | 0025 | 706-03-00300 | Incidental Concrete Paving (6" Thick) | 26.7 | SQYD | 275.00 | 7,342.50 | 350.00 | 9,345.00 | 0026 | 713-01-00100 | Temporary Signs and Barricades | 1 | LUMP | 75,000.00 | 75,000.00 | 140,000.00 | 140,000.00 | 0027 | 713-03-01000 | Temporary Pavement Markings (Broken Line) (4" Width) (4' Length) | 13.898 | MILE | 154.00 | 2,140.29 | 300.00 | 4,169.40 | 0028 | 713-03-02000 | Temporary Pavement Markings (Broken Line) (4" Width) (10' Length) | 14.056 | MILE | 500.00 | 7,028.00 | 1.00 | 14.06 | 0029 | 713-04-01000 | Temporary Pavement Markings (Solid Line) (4" Width) | 39.26 | MILE | 800.00 | 31,408.00 | 1.00 | 39.26 | 0030 | 713-06-00200 | Temporary Reflectorized Raised Pavement Markers (Tabs) | 2,438 | EACH | 2.50 | 6,095.00 | 2.50 | 6,095.00 | 0031 | 713-11-00100 | Portable Changeable Message Signs | 4 | EACH | 5,100.00 | 20,400.00 | 25,000.00 | 100,000.00 | 0032 | 724-01-00100 | Rumble Strips (Centerline) | 3.967 | MILE | 1,100.00 | 4,363.70 | 1,100.00 | 4,363.70 | 0033 | 724-02-00100 | Rumble Strips (Shoulder/Edge) | 9.233 | MILE | 1,100.00 | 10,156.30 | 1,100.00 | 10,156.30 | 0034 | 726-01-00100 | Bedding Material | 20.9 | CUYD | 215.00 | 4,493.50 | 2.10 | 43.89 | 0035 | 727-01-00100 | Mobilization | 1 | LUMP | 407,000.00 | 407,000.00 | 470,000.00 | 470,000.00 | 0036 | 729-16-00200 | Object Marker Assembly (Type 2) | 2 | EACH | 115.00 | 230.00 | 120.00 | 240.00 | 0037 | 729-16-00300 | Object Marker Assembly (Type 3) | 8 | EACH | 135.00 | 1,080.00 | 90.00 | 720.00 | 0038 | 731-02-00100 | Reflectorized Raised Pavement Markers | 825 | EACH | 5.00 | 4,125.00 | 6.00 | 4,950.00 | 0039 | 732-01-02040 | Plastic Pavement Striping (8" Width) (Thermoplastic 125 mil) | 132 | LNFT | 3.00 | 396.00 | 3.00 | 396.00 | 0040 | 732-01-02080 | Plastic Pavement Striping (24" Width) (Thermoplastic 125 mil) | 460 | LNFT | 12.50 | 5,750.00 | 13.00 | 5,980.00 | 0041 | 732-02-02000 | Plastic Pavement Striping (Solid Line) (4" Width) (Thermoplastic 90 mil) | 12.244 | MILE | 5,100.00 | 62,444.40 | 5,100.00 | 62,444.40 | 0042 | 732-03-02000 | Plastic Pavement Striping (Broken Line) (4" Width) (Thermoplastic 90 mil) | 3.514 | MILE | 2,900.00 | 10,190.60 | 2,900.00 | 10,190.60 | 0043 | 732-04-01080 | Plastic Pavement Legends and Symbols (Arrow - Left Turn) | 14 | EACH | 315.00 | 4,410.00 | 300.00 | 4,200.00 | 0044 | 732-04-15020 | Plastic Pavement Legends and Symbols (ONLY) | 2 | EACH | 315.00 | 630.00 | 300.00 | 600.00 | 0045 | 735-01-00100 | Mailboxes | 86 | EACH | 10.00 | 860.00 | 25.00 | 2,150.00 | 0046 | 735-02-00100 | Mailbox Supports (Single) | 82 | EACH | 270.00 | 22,140.00 | 255.00 | 20,910.00 | 0047 | 735-03-00100 | Mailbox Supports (Double) | 2 | EACH | 330.00 | 660.00 | 305.00 | 610.00 | 0048 | 736-01-00100 | Trenching and Backfilling | 37 | LNFT | 20.00 | 740.00 | 23.00 | 851.00 | 0049 | 736-09-00100 | Loop Detector | 140 | LNFT | 50.00 | 7,000.00 | 100.00 | 14,000.00 | 0050 | 736-11-00100 | Conduit (1" HDPE, Schedule 80) | 37 | LNFT | 20.00 | 740.00 | 22.00 | 814.00 | 0051 | 739-01-00100 | Hydro-Seeding | 3.375 | ACRE | 2,900.00 | 9,787.50 | 2,800.00 | 9,450.00 | 0052 | 740-01-00100 | Construction Layout | 1 | LUMP | 15,000.00 | 15,000.00 | 30,000.00 | 30,000.00 | 0053 | NS-500-00340 | Saw Cutting Asphalt Concrete Pavement | 21,006 | INLF | 0.55 | 11,553.30 | 0.25 | 5,251.50 | | | | | | | | | | | | CONTRACTOR TOTAL | | | | 4,542,400.19 | | 4,708,730.96 |
|