Proposal:H.014813.6
Parish:Lincoln
Routes:LA 150
Description:LA 150: US 80 - LA 149
Type Construction:CLEARING AND GRUBBING, DRAINAGE STRUCTURES, BORROW, MILLING ASPHALT CONCRETE, LIME TREATMENT, IN-PLACE CEMENT TREATED BASE COURSE, ASPHALT CONCRETE OVERLAY, LOOP DETECTORS, AND RELATED WORK.
Estimated Construction Cost:$4,099,857.50
Rank | License | Bidder | Construction Bid |
1 | 08584 | Madden Contracting Co., LLC | $3,541,587.53 |
2 | 12487 | Diamond B Construction Co., L.L.C. | $3,753,149.72 |
Line Number | Item Number | Item Description | Quantity | Unit of Measure | - 1 - Madden Contracting Co., LLC | - 2 - Diamond B Construction Co., L.L.C. | Unit Price | Total Amount | Unit Price | Total Amount | 0001 | 201-01-00100 | Clearing and Grubbing | 0.115 | LUMP | 10,000.00 | 10,000.00 | 20,000.00 | 20,000.00 | 0002 | 201-01-00200 | Clearing and Grubbing (Selective) | 2.083 | LUMP | 7,500.00 | 7,500.00 | 42,000.00 | 42,000.00 | 0003 | 202-01-00100 | Removal of Structures and Obstructions (BRICK MAILBOX) | 1 | LUMP | 2,000.00 | 2,000.00 | 10,000.00 | 10,000.00 | 0004 | 202-02-06100 | Removal of Concrete Walks and Drives | 418 | SQYD | 18.50 | 7,733.00 | 35.00 | 14,630.00 | 0005 | 202-02-14500 | Removal of Guard Rail | 602 | LNFT | 13.00 | 7,826.00 | 13.00 | 7,826.00 | 0006 | 202-02-32100 | Removal of Pipe (Cross Drain) (24" RCP) | 56 | LNFT | 25.00 | 1,400.00 | 22.00 | 1,232.00 | 0007 | 202-02-32100 | Removal of Pipe (Cross Drain) (30" CMP) | 47 | LNFT | 25.00 | 1,175.00 | 22.00 | 1,034.00 | 0008 | 202-02-32100 | Removal of Pipe (Cross Drain) (30" RCP) | 297 | LNFT | 25.00 | 7,425.00 | 25.00 | 7,425.00 | 0009 | 202-02-40100 | Removal of Traffic Signal Equipment | 1 | LUMP | 500.00 | 500.00 | 2,500.00 | 2,500.00 | 0010 | 203-07-00100 | Borrow (Vehicular Measurement) | 3,840 | CUYD | 29.75 | 114,240.00 | 45.00 | 172,800.00 | 0011 | 203-10-00100 | Cleaning Existing Ditches | 100 | LNFT | 25.00 | 2,500.00 | 25.00 | 2,500.00 | 0012 | 204-06-00100 | Temporary Silt Fencing | 798 | LNFT | 5.00 | 3,990.00 | 8.00 | 6,384.00 | 0013 | 303-02-00100 | Removal of Existing Patches | 403 | SQYD | 31.00 | 12,493.00 | 12.00 | 4,836.00 | 0014 | 303-03-00400 | In-Place Cement Treated Base Course (12" Thick) | 51,877.3 | SQYD | 12.25 | 635,496.93 | 12.00 | 622,527.60 | 0015 | 304-01-00100 | Lime | 96.1 | TON | 345.00 | 33,154.50 | 373.00 | 35,845.30 | 0016 | 304-03-00400 | Lime Treatment (Type C) (12" Thick) | 7,626 | SQYD | 6.00 | 45,756.00 | 4.00 | 30,504.00 | 0017 | 401-02-00100 | Aggregate Surface Course (Adjusted Vehicular Measurement) | 1,523 | CUYD | 44.75 | 68,154.25 | 95.00 | 144,685.00 | 0018 | 402-01-00101 | Traffic Maintenance Surfacing (Aggregate) (Vehicular Measurement) | 139.9 | CUYD | 150.00 | 20,985.00 | 70.00 | 9,793.00 | 0019 | 502-01-00100 | Asphalt Concrete | 9,468.5 | TON | 142.00 | 1,344,527.00 | 145.00 | 1,372,932.50 | 0020 | 502-01-00200 | Asphalt Concrete, Drives, Turnouts and Miscellaneous | 661.2 | TON | 95.00 | 62,814.00 | 275.00 | 181,830.00 | 0021 | 509-01-00100 | Milling Asphalt Pavement | 49,282 | SQYD | 6.75 | 332,653.50 | 5.00 | 246,410.00 | 0022 | 509-02-00100 | Contractor Retained Reclaimed Asphalt Pavement | -3,535 | CUYD | 0.10 | -353.50 | 1.00 | -3,535.00 | 0023 | 701-01-01001 | Cross Drain Pipe (24" RCP) | 16 | LNFT | 280.00 | 4,480.00 | 315.00 | 5,040.00 | 0024 | 701-01-01100 | Cross Drain Pipe (54" RCP) | 112 | LNFT | 335.00 | 37,520.00 | 455.00 | 50,960.00 | 0025 | 701-02-01020 | Cross Drain Pipe Arch (30" Equiv. RCPA) | 40 | LNFT | 225.00 | 9,000.00 | 375.00 | 15,000.00 | 0026 | 701-02-01040 | Cross Drain Pipe Arch (36" Equiv. RCPA) | 48 | LNFT | 252.00 | 12,096.00 | 390.00 | 18,720.00 | 0027 | 701-15-00100 | Concrete Collar | 10 | EACH | 1,350.00 | 13,500.00 | 2,300.00 | 23,000.00 | 0028 | 701-17-00100 | Trench Excavation Safety Protection (Depth >5 feet) | 194 | LNFT | 5.00 | 970.00 | 20.00 | 3,880.00 | 0029 | 704-03-00200 | Blocked Out Guard Rail - 31", (6'-3" Post Spacing) | 531.3 | LNFT | 35.00 | 18,595.50 | 35.00 | 18,595.50 | 0030 | 704-10-00205 | Guard Rail End Treatment, MASH, (TL-3 Tangent) | 2 | EACH | 4,200.00 | 8,400.00 | 4,200.00 | 8,400.00 | 0031 | 706-02-00200 | Concrete Drive (6" Thick) | 417.5 | SQYD | 115.00 | 48,012.50 | 170.00 | 70,975.00 | 0032 | 711-01-05000 | Riprap (130 lb, 24" Thick) | 50 | SQYD | 145.00 | 7,250.00 | 250.00 | 12,500.00 | 0033 | 711-04-00100 | Geotextile Fabric | 50 | SQYD | 5.00 | 250.00 | 6.00 | 300.00 | 0034 | 713-01-00100 | Temporary Signs and Barricades | 1 | LUMP | 206,000.00 | 206,000.00 | 55,000.00 | 55,000.00 | 0035 | 713-02-00500 | Temporary Pavement Markings (24" Width) | 144 | LNFT | 0.50 | 72.00 | 0.50 | 72.00 | 0036 | 713-03-01000 | Temporary Pavement Markings (Broken Line) (4" Width) (4' Length) | 11.256 | MILE | 300.00 | 3,376.80 | 154.00 | 1,733.42 | 0037 | 713-03-02000 | Temporary Pavement Markings (Broken Line) (4" Width) (10' Length) | 2.721 | MILE | 600.00 | 1,632.60 | 600.00 | 1,632.60 | 0038 | 713-04-01000 | Temporary Pavement Markings (Solid Line) (4" Width) | 41.52 | MILE | 900.00 | 37,368.00 | 900.00 | 37,368.00 | 0039 | 713-05-00400 | Temporary Pavement Legends & Symbols (RR Crossing) | 6 | EACH | 50.00 | 300.00 | 50.00 | 300.00 | 0040 | 716-01-00100 | Mulch (Vegetative) | 9.9 | TON | 950.00 | 9,405.00 | 900.00 | 8,910.00 | 0041 | 717-01-00100 | Seeding | 301 | LB | 20.00 | 6,020.00 | 15.00 | 4,515.00 | 0042 | 718-01-00100 | Fertilizer | 5,030 | LB | 0.85 | 4,275.50 | 0.70 | 3,521.00 | 0043 | 722-02-00100 | Project Site Laboratory (Equipped) | 1 | EACH | 10,000.00 | 10,000.00 | 10,000.00 | 10,000.00 | 0044 | 726-01-00100 | Bedding Material | 127.9 | CUYD | 150.00 | 19,185.00 | 185.00 | 23,661.50 | 0045 | 727-01-00100 | Mobilization | 1 | LUMP | 206,000.00 | 206,000.00 | 324,000.00 | 324,000.00 | 0046 | 729-16-00200 | Object Marker Assembly (Type 2) | 22 | EACH | 70.00 | 1,540.00 | 115.00 | 2,530.00 | 0047 | 729-16-00300 | Object Marker Assembly (Type 3) | 6 | EACH | 135.00 | 810.00 | 135.00 | 810.00 | 0048 | 731-02-00100 | Reflectorized Raised Pavement Markers | 871 | EACH | 5.00 | 4,355.00 | 5.00 | 4,355.00 | 0049 | 732-01-02080 | Plastic Pavement Striping (24" Width) (Thermoplastic 125 mil) | 48 | LNFT | 15.00 | 720.00 | 15.00 | 720.00 | 0050 | 732-02-02000 | Plastic Pavement Striping (Solid Line) (4" Width) (Thermoplastic 90 mil) | 13.84 | MILE | 4,850.00 | 67,124.00 | 4,850.00 | 67,124.00 | 0051 | 732-03-02000 | Plastic Pavement Striping (Broken Line) (4" Width) (Thermoplastic 90 mil) | 0.907 | MILE | 2,850.00 | 2,584.95 | 2,900.00 | 2,630.30 | 0052 | 732-04-18000 | Plastic Pavement Legends and Symbols (RR Crossing) | 2 | EACH | 1,100.00 | 2,200.00 | 1,200.00 | 2,400.00 | 0053 | 735-01-00100 | Mailboxes | 22 | EACH | 20.00 | 440.00 | 1.00 | 22.00 | 0054 | 735-02-00100 | Mailbox Supports (Single) | 12 | EACH | 295.00 | 3,540.00 | 375.00 | 4,500.00 | 0055 | 735-03-00100 | Mailbox Supports (Double) | 5 | EACH | 395.00 | 1,975.00 | 375.00 | 1,875.00 | 0056 | 736-01-00100 | Trenching and Backfilling | 50 | LNFT | 13.75 | 687.50 | 10.00 | 500.00 | 0057 | 736-09-00100 | Loop Detector | 475 | LNFT | 34.50 | 16,387.50 | 30.00 | 14,250.00 | 0058 | 736-10-00300 | Underground Junction Box (Type F) | 1 | EACH | 2,000.00 | 2,000.00 | 2,100.00 | 2,100.00 | 0059 | 736-11-00100 | Conduit (1" HDPE, Schedule 80) | 20 | LNFT | 14.00 | 280.00 | 22.00 | 440.00 | 0060 | 736-12-00000 | Conductor (2c, Loop Lead in, imsa 50-2, #14 awg, Twisted Pair) | 220 | LNFT | 5.75 | 1,265.00 | 7.50 | 1,650.00 | 0061 | 740-01-00100 | Construction Layout | 1 | LUMP | 50,000.00 | 50,000.00 | 15,000.00 | 15,000.00 | | | | | | | | | | | | CONTRACTOR TOTAL | | | | 3,541,587.53 | | 3,753,149.72 |
|