Proposal:H.016100.6
Parish:Bossier, Caddo
Routes:LA 511, LA 614, LA 789, US 80
Description:DISTRICT 04 OVERLAYS: NORTHERN PARISHES
Type Construction:MILLING ASPHALT PAVEMENT, PAVEMENT PATCHING, ASPHALT CONCRETE OVERLAY, AND RELATED WORK
Estimated Construction Cost:$1,796,863.00
| Rank | License | Bidder | Construction Bid |
| 1 | 17464 | Benton & Brown, LLC. | $2,297,165.18 |
Line Number | Item Number | Item Description | Quantity | Unit of Measure | - 1 - Benton & Brown, LLC. | | Unit Price | Total Amount | | 0001 | 202-01-00100 | Removal of Structures and Obstructions Removal of existing brick mailbox | 1 | LUMP | 2,000.00 | 2,000.00 | | 0002 | 203-07-00100 | Borrow (Vehicular Measurement) | 370.5 | CUYD | 100.00 | 37,050.00 | | 0003 | 502-01-00100 | Asphalt Concrete | 5,631.5 | TON | 185.00 | 1,041,827.50 | | 0004 | 502-01-00200 | Asphalt Concrete, Drives, Turnouts and Miscellaneous | 211.4 | TON | 500.00 | 105,700.00 | | 0005 | 509-01-00100 | Milling Asphalt Pavement | 38,648 | SQYD | 9.00 | 347,832.00 | | 0006 | 509-02-00100 | Contractor Retained Reclaimed Asphalt Pavement | -1,592 | CUYD | 0.01 | -15.92 | | 0007 | 510-01-00100 | Pavement Patching (6" Minimum Thickness) | 1,057 | SQYD | 120.00 | 126,840.00 | | 0008 | 510-01-00200 | Pavement Patching (12" Minimum Thickness) | 158 | SQYD | 240.00 | 37,920.00 | | 0009 | 602-02-00200 | Cleaning and Resealing Existing Longitudinal Pavement Joints | 1,236 | LNFT | 11.00 | 13,596.00 | | 0010 | 602-02-00300 | Cleaning and Resealing Existing Transverse Pavements Joints | 834.3 | LNFT | 11.00 | 9,177.30 | | 0011 | 706-04-00110 | Curb Ramps Type 1 | 76.8 | SQYD | 275.00 | 21,120.00 | | 0012 | 706-04-00110 | Curb Ramps Type 3 | 16.2 | SQYD | 275.00 | 4,455.00 | | 0013 | 706-04-00110 | Curb Ramps Type 7 | 53.2 | SQYD | 275.00 | 14,630.00 | | 0014 | 706-04-00110 | Curb Ramps Type 8 | 124 | SQYD | 275.00 | 34,100.00 | | 0015 | 711-01-03020 | Riprap (30 lb, 18" Thick) | 120 | SQYD | 150.00 | 18,000.00 | | 0016 | 713-01-00100 | Temporary Signs and Barricades | 1 | LUMP | 115,750.00 | 115,750.00 | | 0018 | 713-02-00300 | Temporary Pavement Markings (8" Width) | 1,806 | LNFT | 1.10 | 1,986.60 | | 0019 | 713-02-00500 | Temporary Pavement Markings (24" Width) | 2,932 | LNFT | 1.10 | 3,225.20 | | 0020 | 713-03-01000 | Temporary Pavement Markings (Broken Line) (4" Width) (4' Length) | 2.864 | MILE | 1,000.00 | 2,864.00 | | 0021 | 713-03-02000 | Temporary Pavement Markings (Broken Line) (4" Width) (10' Length) | 2.118 | MILE | 1,100.00 | 2,329.80 | | 0022 | 713-04-01000 | Temporary Pavement Markings (Solid Line) (4" Width) | 17.51 | MILE | 1,100.00 | 19,261.00 | | 0023 | 724-01-00100 | Rumble Strips (Centerline) | 1.042 | MILE | 4,400.00 | 4,584.80 | | 0024 | 724-02-00100 | Rumble Strips (Shoulder/Edge) | 4.782 | MILE | 4,400.00 | 21,040.80 | | 0025 | 727-01-00100 | Mobilization | 1 | LUMP | 115,750.00 | 115,750.00 | | 0026 | 731-02-00100 | Reflectorized Raised Pavement Markers | 1,232 | EACH | 11.00 | 13,552.00 | | 0027 | 732-01-02040 | Plastic Pavement Striping (8" Width) (Thermoplastic 125 mil) | 903 | LNFT | 6.60 | 5,959.80 | | 0028 | 732-01-02080 | Plastic Pavement Striping (24" Width) (Thermoplastic 125 mil) | 1,444 | LNFT | 25.00 | 36,100.00 | | 0029 | 732-01-05200 | Plastic Pavement Striping (Dotted Line)(8" W)(2' L)(Thermo 125 mil) | 50 | LNFT | 22.00 | 1,100.00 | | 0030 | 732-02-02000 | Plastic Pavement Striping (Solid Line) (4" Width) (Thermoplastic 90 mil) | 10.692 | MILE | 7,150.00 | 76,447.80 | | 0031 | 732-03-02000 | Plastic Pavement Striping (Broken Line) (4" Width) (Thermoplastic 90 mil) | 1.184 | MILE | 4,400.00 | 5,209.60 | | 0032 | 732-04-16000 | Plastic Pavement Legends and Symbols (Pedestrian Crossing) | 7 | EACH | 2,200.00 | 15,400.00 | | 0033 | 732-05-00100 | Removal of Existing Markings | 0.066 | MILE | 110,000.00 | 7,260.00 | | 0034 | 735-01-00100 | Mailboxes | 29 | EACH | 1.10 | 31.90 | | 0035 | 735-02-00100 | Mailbox Supports (Single) | 27 | EACH | 360.00 | 9,720.00 | | 0036 | 735-03-00100 | Mailbox Supports (Double) | 1 | EACH | 360.00 | 360.00 | | 0037 | 740-01-00100 | Construction Layout | 1 | LUMP | 25,000.00 | 25,000.00 | | | | | | | | | | | | CONTRACTOR TOTAL | | | | 2,297,165.18 |
|