Proposal:H.016149.6
Parish:Tangipahoa
Routes:I-55
Description:I-55: LA 1050 OPASS - ST LINE
Type Construction:CLEARING AND GRUBBING, GRADING, MILLING ASPHALT CONCRETE, PAVEMENT PATCHING, ASPHALT CONCRETE OVERLAY, AND RELATED WORK.
Estimated Construction Cost:$16,408,504.83
Maximum Number of Days Allowed for Construction:9999
Calculated Daily User Cost:$9,000.00
| Rank | License | Bidder | Construction Bid | Bidder's Proposed Contract Time | Total Bid |
| 1 | 06276 | Barriere Construction Co., LLC | $15,171,046.68 | 158.00 | $16,593,046.68 |
| 2 | 73475 | Madden Gulf Coast, LLC | $16,607,954.76 | 260.00 | $18,947,954.76 |
Line Number | Item Number | Item Description | Quantity | Unit of Measure | - 1 - Barriere Construction Co., LLC | - 2 - Madden Gulf Coast, LLC | | Unit Price | Total Amount | Unit Price | Total Amount | | 0001 | 201-01-00100 | Clearing and Grubbing | 40 | LUMP | 120,000.00 | 120,000.00 | 35,000.00 | 35,000.00 | | 0002 | 202-01-00100 | Removal of Structures and Obstructions | 1 | LUMP | 5,750.00 | 5,750.00 | 10,000.00 | 10,000.00 | | 0003 | 202-02-00020 | Removal of Concrete Aprons | 165 | SQYD | 65.00 | 10,725.00 | 40.00 | 6,600.00 | | 0004 | 202-02-14500 | Removal of Guard Rail | 11,699 | LNFT | 6.50 | 76,043.50 | 6.50 | 76,043.50 | | 0005 | 202-02-38300 | Removal of Sign and U-Channel Post | 43 | EACH | 100.00 | 4,300.00 | 25.00 | 1,075.00 | | 0006 | 203-01-00100 | General Excavation | 124 | CUYD | 70.00 | 8,680.00 | 40.00 | 4,960.00 | | 0007 | 203-03-00100 | Embankment | 124 | CUYD | 40.00 | 4,960.00 | 50.00 | 6,200.00 | | 0008 | 203-07-00100 | Borrow (Vehicular Measurement) | 572 | CUYD | 75.00 | 42,900.00 | 150.00 | 85,800.00 | | 0009 | 204-02-00100 | Temporary Hay Bales | 88 | EACH | 35.75 | 3,146.00 | 28.00 | 2,464.00 | | 0010 | 204-06-00100 | Temporary Silt Fencing | 500 | LNFT | 2.50 | 1,250.00 | 3.00 | 1,500.00 | | 0011 | 502-01-00100 | Asphalt Concrete | 55,962.3 | TON | 112.00 | 6,267,777.60 | 107.00 | 5,987,966.10 | | 0012 | 502-01-00200 | Asphalt Concrete, Drives, Turnouts and Miscellaneous | 1,283 | TON | 201.00 | 257,883.00 | 148.00 | 189,884.00 | | 0013 | 502-04-00100 | Asphalt Concrete (SMA) Wearing Course | 25,977.6 | TON | 163.00 | 4,234,348.80 | 164.50 | 4,273,315.20 | | 0014 | 509-01-00100 | Milling Asphalt Pavement | 379,350 | SQYD | 3.00 | 1,138,050.00 | 4.15 | 1,574,302.50 | | 0015 | 509-02-00100 | Contractor Retained Reclaimed Asphalt Pavement | -31,532 | CUYD | 0.01 | -315.32 | 0.01 | -315.32 | | 0016 | 510-01-00102 | Pavement Patching (8" Minimum Thickness) | 255 | SQYD | 80.00 | 20,400.00 | 169.89 | 43,321.95 | | 0017 | 602-02-00200 | Cleaning and Resealing Existing Longitudinal Pavement Joints | 63,023 | LNFT | 2.50 | 157,557.50 | 2.75 | 173,313.25 | | 0018 | 602-02-00300 | Cleaning and Resealing Existing Transverse Pavements Joints | 10,374 | LNFT | 2.50 | 25,935.00 | 3.25 | 33,715.50 | | 0019 | 602-03-00100 | Cleaning and Sealing Random Cracks | 300 | LNFT | 10.00 | 3,000.00 | 4.50 | 1,350.00 | | 0020 | 602-05-01160 | Full Depth Patching of Jointed Concrete Pavement (16.0 square yards and under) (9" Thick) | 427.9 | SQYD | 375.00 | 160,462.50 | 650.00 | 278,135.00 | | 0021 | 602-05-02160 | Full Depth Patching of Jointed Concrete Pavement (16.1 square yards to 48.0 square yards) (9" Thick) | 305.4 | SQYD | 375.00 | 114,525.00 | 600.00 | 183,240.00 | | 0022 | 602-10-00100 | Longitudinal Shoulder Joints | 7,090 | LNFT | 6.00 | 42,540.00 | 2.50 | 17,725.00 | | 0023 | 602-11-00100 | Removal of Existing Shoulder Underdrain Systems | 1,680 | LNFT | 4.00 | 6,720.00 | 8.50 | 14,280.00 | | 0024 | 701-15-00100 | Concrete Collar | 22 | EACH | 100.00 | 2,200.00 | 850.00 | 18,700.00 | | 0025 | 703-01-00100 | Shoulder Underdrain Systems | 1,680 | LNFT | 19.00 | 31,920.00 | 48.00 | 80,640.00 | | 0026 | 703-02-00100 | Shoulder Outlet Underdrains | 10 | EACH | 900.00 | 9,000.00 | 200.00 | 2,000.00 | | 0027 | 703-03-00100 | Perforated Pipe Underdrains | 500 | LNFT | 18.00 | 9,000.00 | 48.00 | 24,000.00 | | 0028 | 704-01-01020 | Guard Rail (Single Thrie Beam) (6'-3" post spacing) | 2,606 | LNFT | 42.50 | 110,755.00 | 42.50 | 110,755.00 | | 0029 | 704-03-00200 | Blocked Out Guard Rail - 31", (6'-3" Post Spacing) | 6,107.5 | LNFT | 26.50 | 161,848.75 | 26.50 | 161,848.75 | | 0030 | 704-05-00300 | Guard Rail Anchor Sections - 31", (Trailing End) | 119.9 | LNFT | 176.50 | 21,162.35 | 176.50 | 21,162.35 | | 0031 | 704-06-00200 | Guard Rail Bridge Attachments (Single Thrie Beam) | 734 | LNFT | 46.00 | 33,764.00 | 46.00 | 33,764.00 | | 0032 | 704-07-00200 | Guard Rail Transitions (Double Thrie Beam) | 575 | LNFT | 119.50 | 68,712.50 | 119.50 | 68,712.50 | | 0033 | 704-10-00205 | Guard Rail End Treatment, MASH, (TL-3 Tangent) | 8 | EACH | 3,425.00 | 27,400.00 | 3,425.00 | 27,400.00 | | 0034 | 704-10-00310 | Guard Rail End Treatment, NCHRP 350 - 31" (TL-3 Flared) | 24 | EACH | 3,100.00 | 74,400.00 | 3,100.00 | 74,400.00 | | 0035 | 706-03-00100 | Incidental Concrete Paving (4" Thick) | 578.5 | SQYD | 92.50 | 53,511.25 | 92.50 | 53,511.25 | | 0036 | 706-03-00300 | Incidental Concrete Paving (6" Thick) | 156.2 | SQYD | 100.00 | 15,620.00 | 300.00 | 46,860.00 | | 0037 | 707-04-00100 | Asphalt Curb | 310.5 | LNFT | 105.00 | 32,602.50 | 200.00 | 62,100.00 | | 0038 | 713-01-00100 | Temporary Signs and Barricades | 1 | LUMP | 500,000.00 | 500,000.00 | 600,000.00 | 600,000.00 | | 0039 | 713-02-00300 | Temporary Pavement Markings (8" Width) | 2,424 | LNFT | 0.25 | 606.00 | 0.25 | 606.00 | | 0040 | 713-02-00500 | Temporary Pavement Markings (24" Width) | 3,848 | LNFT | 0.50 | 1,924.00 | 0.50 | 1,924.00 | | 0041 | 713-03-01000 | Temporary Pavement Markings (Broken Line) (4" Width) (4' Length) | 31.54 | MILE | 320.00 | 10,092.80 | 400.00 | 12,616.00 | | 0042 | 713-03-02000 | Temporary Pavement Markings (Broken Line) (4" Width) (10' Length) | 31.54 | MILE | 600.00 | 18,924.00 | 600.00 | 18,924.00 | | 0043 | 713-04-01000 | Temporary Pavement Markings (Solid Line) (4" Width) | 72.096 | MILE | 800.00 | 57,676.80 | 800.00 | 57,676.80 | | 0044 | 721-01-00100 | Mowing | 4 | CYCL | 8,000.00 | 32,000.00 | 32,000.00 | 128,000.00 | | 0045 | 724-02-00100 | Rumble Strips (Shoulder/Edge) | 31.592 | MILE | 265.00 | 8,371.88 | 1,250.00 | 39,490.00 | | 0046 | 727-01-00100 | Mobilization | 1 | LUMP | 780,000.00 | 780,000.00 | 1,600,000.00 | 1,600,000.00 | | 0047 | 729-16-00300 | Object Marker Assembly (Type 3) | 43 | EACH | 95.00 | 4,085.00 | 85.00 | 3,655.00 | | 0048 | 731-02-00100 | Reflectorized Raised Pavement Markers | 4,382 | EACH | 4.00 | 17,528.00 | 4.00 | 17,528.00 | | 0049 | 732-01-01040 | Plastic Pavement Striping (8" Width) (Thermoplastic 90 mil) | 1,212 | LNFT | 3.00 | 3,636.00 | 3.00 | 3,636.00 | | 0050 | 732-01-01080 | Plastic Pavement Striping (24" Width) (Thermoplastic 90 mil) | 1,924 | LNFT | 11.00 | 21,164.00 | 11.00 | 21,164.00 | | 0051 | 732-01-05200 | Plastic Pavement Striping (Dotted Line)(8" W)(2' L)(Thermo 125 mil) | 850 | LNFT | 3.00 | 2,550.00 | 3.00 | 2,550.00 | | 0052 | 732-02-02000 | Plastic Pavement Striping (Solid Line) (4" Width) (Thermoplastic 90 mil) | 36.048 | MILE | 4,000.00 | 144,192.00 | 4,000.00 | 144,192.00 | | 0053 | 732-03-02000 | Plastic Pavement Striping (Broken Line) (4" Width) (Thermoplastic 90 mil) | 15.77 | MILE | 900.00 | 14,193.00 | 900.00 | 14,193.00 | | 0054 | 732-03-02102 | Plastic Pav't Striping (Broken) (4" W) (Preformed Tape Retroreflectivity I or Thermo 90 mil)(Black and White Contrast) | 0.9 | MILE | 4,500.00 | 4,050.00 | 4,500.00 | 4,050.00 | | 0055 | 732-05-00100 | Removal of Existing Markings | 0.9 | MILE | 6,000.00 | 5,400.00 | 6,000.00 | 5,400.00 | | 0056 | 739-01-00100 | Hydro-Seeding | 0.11 | ACRE | 23,523.00 | 2,587.53 | 0.30 | 0.03 | | 0057 | 740-01-00100 | Construction Layout | 1 | LUMP | 13,500.00 | 13,500.00 | 32,000.00 | 32,000.00 | | 0058 | NS-500-00220 | Sawing and Sealing Longitudinal Joints in Asphalt Concrete Overlay | 11,318 | LNFT | 6.50 | 73,567.00 | 1.65 | 18,674.70 | | 0059 | NS-500-00240 | Sawing and Sealing Transverse Joints in Asphalt Concrete Overlay | 4,888 | LNFT | 6.50 | 31,772.00 | 1.65 | 8,065.20 | | 0060 | NS-500-00260 | Sawcuts in Asphalt Concrete Lifts | 69,174 | LNFT | 0.01 | 691.74 | 0.75 | 51,880.50 | | 0061 | NS-713-00009 | Portable Changeable Message Sign (with communications) | 4 | EACH | 16,000.00 | 64,000.00 | 9,000.00 | 36,000.00 | | | | | | | | | | | | | | CONTRACTOR TOTAL | | | | 15,171,046.68 | | 16,607,954.76 |
|