Proposal:H.012587.6
Parish:West Baton Rouge
Routes:I-10
Description:I-10: W END OF BR 290 - W END OF LA 415
Type Construction:CLEARING AND GRUBBING, GRADING, DRAINAGE STRUCTURES, MILLING ASPHALT PAVEMENT, PAVEMENT PATCHING, ASPHALT CONCRETE OVERLAY, CABLE BARRIER SYSTEM, CONCRETE STRIP, AND RELATED WORK.
Estimated Construction Cost:$20,006,505.30
Maximum Number of Days Allowed for Construction:9999
Calculated Daily User Cost:$20,000.00
| Rank | License | Bidder | Construction Bid | Bidder's Proposed Contract Time | Total Bid |
| 1 | 06276 | Barriere Construction Co., LLC | $20,922,940.19 | 213.00 | $25,182,940.19 |
| 2 | 73475 | Madden Gulf Coast, LLC | $22,061,090.56 | 328.00 | $28,621,090.56 |
| 3 | 00046 | Barber Bros. Contracting Co., L.L.C | $26,731,317.14 | 390.00 | $34,531,317.14 |
Line Number | Item Number | Item Description | Quantity | Unit of Measure | - 1 - Barriere Construction Co., LLC | - 2 - Madden Gulf Coast, LLC | - 3 - Barber Bros. Contracting Co., L.L.C | | Unit Price | Total Amount | Unit Price | Total Amount | Unit Price | Total Amount | | 0001 | 201-01-00100 | Clearing and Grubbing | 1 | LUMP | 154,000.00 | 154,000.00 | 49,341.50 | 49,341.50 | 250,000.00 | 250,000.00 | | 0002 | 202-02-00020 | Removal of Concrete (Cable Barrier Mow Strip, Guard Rail Pads) | 308 | SQYD | 28.00 | 8,624.00 | 60.00 | 18,480.00 | 45.00 | 13,860.00 | | 0003 | 202-02-00030 | Removal of Cable Barrier | 19,473 | LNFT | 3.15 | 61,339.95 | 3.50 | 68,155.50 | 5.00 | 97,365.00 | | 0004 | 202-02-06040 | Removal of Concrete Box Headwall (Sta. 860+28) | 1 | EACH | 5,254.94 | 5,254.94 | 15,000.00 | 15,000.00 | 12,000.00 | 12,000.00 | | 0005 | 202-02-06102 | Removal of Incidental Concrete Paving | 10,818 | SQYD | 7.82 | 84,596.76 | 14.50 | 156,861.00 | 15.00 | 162,270.00 | | 0006 | 202-02-14500 | Removal of Guard Rail | 965 | LNFT | 8.00 | 7,720.00 | 8.00 | 7,720.00 | 10.00 | 9,650.00 | | 0007 | 202-02-32180 | Removal of Pipe Headwalls | 10 | EACH | 2,012.54 | 20,125.40 | 2,000.00 | 20,000.00 | 3,000.00 | 30,000.00 | | 0008 | 202-02-38240 | Removal of Signs and Supports | 17 | EACH | 500.00 | 8,500.00 | 500.00 | 8,500.00 | 600.00 | 10,200.00 | | 0009 | 202-03-38000 | Relocation of Sign (Mile Markers, Speed Limit, Misc. Signs) | 25 | EACH | 215.00 | 5,375.00 | 215.00 | 5,375.00 | 250.00 | 6,250.00 | | 0010 | 202-03-38020 | Relocation of Sign Pole (Mile Markers, Speed Limit, Misc. Signs) | 30 | EACH | 1,850.00 | 55,500.00 | 1,850.00 | 55,500.00 | 2,000.00 | 60,000.00 | | 0011 | 203-05-00100 | Excavation and Embankment | 1 | LUMP | 2,537,000.00 | 2,537,000.00 | 3,000,000.00 | 3,000,000.00 | 2,200,000.00 | 2,200,000.00 | | 0012 | 204-02-00100 | Temporary Hay Bales | 100 | EACH | 35.00 | 3,500.00 | 24.94 | 2,494.00 | 32.00 | 3,200.00 | | 0013 | 204-04-00100 | Temporary Sediment Basins | 17 | EACH | 2,096.54 | 35,641.18 | 1,000.00 | 17,000.00 | 200.00 | 3,400.00 | | 0014 | 204-05-00100 | Temporary Sediment Check Dams (Hay) | 68 | EACH | 150.00 | 10,200.00 | 149.90 | 10,193.20 | 170.00 | 11,560.00 | | 0015 | 204-06-00100 | Temporary Silt Fencing | 53,848 | LNFT | 2.00 | 107,696.00 | 1.99 | 107,157.52 | 2.50 | 134,620.00 | | 0016 | 302-03-00100 | Base Drain Outlet | 180 | EACH | 750.87 | 135,156.60 | 950.00 | 171,000.00 | 1,000.00 | 180,000.00 | | 0017 | 502-01-00100 | Asphalt Concrete | 69,597 | TON | 130.25 | 9,065,009.25 | 115.50 | 8,038,453.50 | 152.00 | 10,578,744.00 | | 0018 | 502-01-00200 | Asphalt Concrete, Drives, Turnouts and Miscellaneous | 388.3 | TON | 175.00 | 67,952.50 | 350.00 | 135,905.00 | 275.00 | 106,782.50 | | 0019 | 502-04-00100 | Asphalt Concrete (SMA) Wearing Course | 22,270.3 | TON | 100.00 | 2,227,030.00 | 112.00 | 2,494,273.60 | 152.00 | 3,385,085.60 | | 0020 | 509-01-00100 | Milling Asphalt Pavement | 58,272 | SQYD | 1.00 | 58,272.00 | 10.30 | 600,201.60 | 7.50 | 437,040.00 | | 0021 | 509-02-00100 | Contractor Retained Reclaimed Asphalt Pavement | -2,745 | CUYD | 0.01 | -27.45 | 0.01 | -27.45 | 0.00 | 0.00 | | 0022 | 510-01-00102 | Pavement Patching (8" Minimum Thickness) | 2,092 | SQYD | 82.00 | 171,544.00 | 81.00 | 169,452.00 | 125.00 | 261,500.00 | | 0023 | 602-11-00100 | Removal of Existing Shoulder Underdrain Systems | 3,080 | LNFT | 17.82 | 54,885.60 | 20.00 | 61,600.00 | 8.00 | 24,640.00 | | 0024 | 701-10-01040 | Reinforced Concrete Pipe (Extension) (18") | 16 | LNFT | 373.06 | 5,968.96 | 350.00 | 5,600.00 | 500.00 | 8,000.00 | | 0025 | 701-10-01080 | Reinforced Concrete Pipe (Extension) (30") | 144 | LNFT | 246.19 | 35,451.36 | 430.00 | 61,920.00 | 400.00 | 57,600.00 | | 0026 | 701-10-01100 | Reinforced Concrete Pipe (Extension) (36") | 32 | LNFT | 464.55 | 14,865.60 | 449.00 | 14,368.00 | 470.00 | 15,040.00 | | 0027 | 701-10-01120 | Reinforced Concrete Pipe (Extension) (42") | 32 | LNFT | 511.47 | 16,367.04 | 525.00 | 16,800.00 | 500.00 | 16,000.00 | | 0028 | 701-10-01140 | Reinforced Concrete Pipe (Extension) (48") | 48 | LNFT | 456.02 | 21,888.96 | 649.00 | 31,152.00 | 650.00 | 31,200.00 | | 0029 | 701-15-00100 | Concrete Collar | 18 | EACH | 1,488.06 | 26,785.08 | 2,650.00 | 47,700.00 | 3,400.00 | 61,200.00 | | 0030 | 702-04-00200 | Adjusting Catch Basins | 13 | EACH | 4,800.00 | 62,400.00 | 5,500.00 | 71,500.00 | 7,500.00 | 97,500.00 | | 0031 | 703-02-00100 | Shoulder Outlet Underdrains | 154 | EACH | 1,549.99 | 238,698.46 | 2,800.00 | 431,200.00 | 1,600.00 | 246,400.00 | | 0032 | 704-03-00200 | Blocked Out Guard Rail - 31", (6'-3" Post Spacing) | 839.6 | LNFT | 27.00 | 22,669.20 | 27.00 | 22,669.20 | 32.00 | 26,867.20 | | 0033 | 704-05-00300 | Guard Rail Anchor Sections - 31", (Trailing End) | 19.6 | LNFT | 190.00 | 3,724.00 | 190.00 | 3,724.00 | 220.00 | 4,312.00 | | 0034 | 704-07-00200 | Guard Rail Transitions (Double Thrie Beam) | 50 | LNFT | 125.00 | 6,250.00 | 125.00 | 6,250.00 | 145.00 | 7,250.00 | | 0035 | 704-10-00120 | Guard Rail End Treatment, MASH, (TL-3 Flared) | 3 | EACH | 3,250.00 | 9,750.00 | 3,250.00 | 9,750.00 | 3,750.00 | 11,250.00 | | 0036 | 704-10-00205 | Guard Rail End Treatment, MASH, (TL-3 Tangent) | 1 | EACH | 3,725.00 | 3,725.00 | 3,725.00 | 3,725.00 | 4,300.00 | 4,300.00 | | 0037 | 706-03-00300 | Incidental Concrete Paving (6" Thick) | 427 | SQYD | 80.00 | 34,160.00 | 125.00 | 53,375.00 | 215.00 | 91,805.00 | | 0038 | 707-04-00100 | Asphalt Curb | 27 | LNFT | 30.00 | 810.00 | 800.00 | 21,600.00 | 100.00 | 2,700.00 | | 0039 | 713-01-00100 | Temporary Signs and Barricades | 1 | LUMP | 1,445,729.00 | 1,445,729.00 | 1,525,000.00 | 1,525,000.00 | 2,000,000.00 | 2,000,000.00 | | 0040 | 713-03-01000 | Temporary Pavement Markings (Broken Line) (4" Width) (4' Length) | 70.448 | MILE | 85.00 | 5,988.08 | 1.00 | 70.45 | 325.00 | 22,895.60 | | 0041 | 713-03-02000 | Temporary Pavement Markings (Broken Line) (4" Width) (10' Length) | 70.448 | MILE | 1,000.00 | 70,448.00 | 1,000.00 | 70,448.00 | 635.00 | 44,734.48 | | 0042 | 713-04-01000 | Temporary Pavement Markings (Solid Line) (4" Width) | 140.896 | MILE | 300.00 | 42,268.80 | 1,250.00 | 176,120.00 | 835.00 | 117,648.16 | | 0043 | 713-11-00100 | Portable Changeable Message Signs | 8 | EACH | 14,000.00 | 112,000.00 | 10,000.00 | 80,000.00 | 26,000.00 | 208,000.00 | | 0044 | 724-02-00100 | Rumble Strips (Shoulder/Edge) | 17.612 | MILE | 960.00 | 16,907.52 | 270.00 | 4,755.24 | 1,000.00 | 17,612.00 | | 0045 | 726-01-00100 | Bedding Material | 64.6 | CUYD | 157.33 | 10,163.52 | 155.00 | 10,013.00 | 200.00 | 12,920.00 | | 0046 | 727-01-00100 | Mobilization | 1 | LUMP | 1,380,000.00 | 1,380,000.00 | 2,000,000.00 | 2,000,000.00 | 3,300,000.00 | 3,300,000.00 | | 0047 | 729-16-00200 | Object Marker Assembly (Type 2) | 11 | EACH | 75.00 | 825.00 | 75.00 | 825.00 | 88.00 | 968.00 | | 0048 | 729-16-00300 | Object Marker Assembly (Type 3) | 4 | EACH | 90.00 | 360.00 | 90.00 | 360.00 | 100.00 | 400.00 | | 0049 | 731-02-00100 | Reflectorized Raised Pavement Markers | 4,650 | EACH | 7.00 | 32,550.00 | 7.00 | 32,550.00 | 6.00 | 27,900.00 | | 0050 | 732-02-02000 | Plastic Pavement Striping (Solid Line) (4" Width) (Thermoplastic 90 mil) | 17.612 | MILE | 5,000.00 | 88,060.00 | 5,000.00 | 88,060.00 | 5,700.00 | 100,388.40 | | 0051 | 732-03-02000 | Plastic Pavement Striping (Broken Line) (4" Width) (Thermoplastic 90 mil) | 8.806 | MILE | 1,750.00 | 15,410.50 | 1,750.00 | 15,410.50 | 1,700.00 | 14,970.20 | | 0052 | 739-01-00100 | Hydro-Seeding | 64.23 | ACRE | 2,650.00 | 170,209.50 | 2,572.08 | 165,204.70 | 2,700.00 | 173,421.00 | | 0053 | 740-01-00100 | Construction Layout | 1 | LUMP | 80,000.00 | 80,000.00 | 210,500.00 | 210,500.00 | 125,000.00 | 125,000.00 | | 0054 | 805-16-00700 | Reinforced Concrete Box Culverts (Extension) (6' x 5') | 4 | LNFT | 7,303.54 | 29,214.16 | 3,350.00 | 13,400.00 | 5,450.00 | 21,800.00 | | 0055 | 805-17-00100 | Reinforced Concrete Box Culvert Headwall (17.15 CUYD Conc., 1206 LB Steel) | 1 | EACH | 50,369.30 | 50,369.30 | 48,500.00 | 48,500.00 | 23,000.00 | 23,000.00 | | 0056 | NS-704-00001 | High Tension Cable Barrier | 19,741 | LNFT | 35.59 | 702,582.19 | 19.50 | 384,949.50 | 23.00 | 454,043.00 | | 0057 | NS-704-00002 | Cable Barrier Gated End Terminal | 12 | EACH | 9,913.04 | 118,956.48 | 6,700.00 | 80,400.00 | 7,500.00 | 90,000.00 | | 0058 | NS-704-00003 | Concrete Strip | 17,547 | SQYD | 66.25 | 1,162,488.75 | 65.00 | 1,140,555.00 | 75.00 | 1,316,025.00 | | | | | | | | | | | | | | | | CONTRACTOR TOTAL | | | | 20,922,940.19 | | 22,061,090.56 | | 26,731,317.14 |
|