Proposal:H.016054.6
Parish:Evangeline
Routes:LA 13
Description:LA 13: LA 10 - US 167
Type Construction:MILLING ASPHALT CONCRETE, PAVEMENT PATCHING, ASPHALT CONCRETE OVERLAY, AND RELATED WORK.
Estimated Construction Cost:$12,804,516.12
| Rank | License | Bidder | Construction Bid |
| 1 | 12312 | Gilchrist Construction Company, LLC | $10,712,520.85 |
| 2 | 34356 | Prairie Contractors LLC | $10,858,509.59 |
| 3 | 12487 | Diamond B Construction Co., L.L.C. | $12,007,828.90 |
Line Number | Item Number | Item Description | Quantity | Unit of Measure | - 1 - Gilchrist Construction Company, LLC | - 2 - Prairie Contractors LLC | - 3 - Diamond B Construction Co., L.L.C. | | Unit Price | Total Amount | Unit Price | Total Amount | Unit Price | Total Amount | | 0001 | 202-02-02020 | Removal of Asphalt Pavement | 584.9 | SQYD | 30.00 | 17,547.00 | 50.00 | 29,245.00 | 25.00 | 14,622.50 | | 0002 | 202-02-04560 | Removal of Bridge Joint (Poured Joint Seal) | 996 | LNFT | 26.00 | 25,896.00 | 12.00 | 11,952.00 | 20.00 | 19,920.00 | | 0003 | 202-02-06100 | Removal of Concrete Walks and Drives | 501 | SQYD | 80.00 | 40,080.00 | 40.00 | 20,040.00 | 27.00 | 13,527.00 | | 0004 | 202-02-14500 | Removal of Guard Rail | 1,316 | LNFT | 12.00 | 15,792.00 | 15.00 | 19,740.00 | 12.00 | 15,792.00 | | 0005 | 203-07-00100 | Borrow (Vehicular Measurement) | 1,292 | CUYD | 67.00 | 86,564.00 | 60.00 | 77,520.00 | 20.00 | 25,840.00 | | 0006 | 204-05-00100 | Temporary Sediment Check Dams (Hay) | 40 | EACH | 180.00 | 7,200.00 | 135.00 | 5,400.00 | 140.00 | 5,600.00 | | 0007 | 204-06-00100 | Temporary Silt Fencing | 2,000 | LNFT | 2.25 | 4,500.00 | 1.30 | 2,600.00 | 1.50 | 3,000.00 | | 0008 | 402-01-00101 | Traffic Maintenance Surfacing (Aggregate) (Vehicular Measurement) | 100 | CUYD | 100.00 | 10,000.00 | 75.00 | 7,500.00 | 60.00 | 6,000.00 | | 0009 | 502-01-00100 | Asphalt Concrete | 64,496.2 | TON | 116.25 | 7,497,683.25 | 118.00 | 7,610,551.60 | 135.00 | 8,706,987.00 | | 0010 | 502-01-00200 | Asphalt Concrete, Drives, Turnouts and Miscellaneous | 2,393.6 | TON | 116.25 | 278,256.00 | 101.50 | 242,950.40 | 205.00 | 490,688.00 | | 0011 | 509-01-00100 | Milling Asphalt Pavement | 335,310 | SQYD | 2.40 | 804,744.00 | 1.95 | 653,854.50 | 1.75 | 586,792.50 | | 0012 | 509-02-00100 | Contractor Retained Reclaimed Asphalt Pavement | -7,693 | CUYD | 1.00 | -7,693.00 | 0.01 | -76.93 | 1.00 | -7,693.00 | | 0013 | 510-01-00300 | Pavement Patching (18" Minimum Thickness) | 1,943 | SQYD | 180.00 | 349,740.00 | 207.00 | 402,201.00 | 210.00 | 408,030.00 | | 0014 | 701-14-00100 | Cleaning Existing Pipes | 5,330 | LNFT | 38.95 | 207,603.50 | 65.00 | 346,450.00 | 55.00 | 293,150.00 | | 0015 | 704-03-00200 | Blocked Out Guard Rail - 31", (6'-3" Post Spacing) | 375 | LNFT | 27.00 | 10,125.00 | 40.00 | 15,000.00 | 35.00 | 13,125.00 | | 0016 | 704-07-00200 | Guard Rail Transitions (Double Thrie Beam) | 300 | LNFT | 122.00 | 36,600.00 | 165.00 | 49,500.00 | 135.00 | 40,500.00 | | 0017 | 704-10-00205 | Guard Rail End Treatment, MASH, (TL-3 Tangent) | 12 | EACH | 3,600.00 | 43,200.00 | 4,800.00 | 57,600.00 | 4,100.00 | 49,200.00 | | 0018 | 706-02-00200 | Concrete Drive (6" Thick) | 404.9 | SQYD | 200.00 | 80,980.00 | 220.00 | 89,078.00 | 170.00 | 68,833.00 | | 0019 | 713-01-00100 | Temporary Signs and Barricades | 1 | LUMP | 120,000.00 | 120,000.00 | 150,000.00 | 150,000.00 | 152,000.00 | 152,000.00 | | 0020 | 713-03-01000 | Temporary Pavement Markings (Broken Line) (4" Width) (4' Length) | 38.168 | MILE | 250.00 | 9,542.00 | 650.00 | 24,809.20 | 154.00 | 5,877.87 | | 0021 | 713-03-02000 | Temporary Pavement Markings (Broken Line) (4" Width) (10' Length) | 33.903 | MILE | 500.00 | 16,951.50 | 1.00 | 33.90 | 710.00 | 24,071.13 | | 0022 | 713-04-01000 | Temporary Pavement Markings (Solid Line) (4" Width) | 90.918 | MILE | 700.00 | 63,642.60 | 1.00 | 90.92 | 1,000.00 | 90,918.00 | | 0023 | 724-01-00100 | Rumble Strips (Centerline) | 11.411 | MILE | 1,000.00 | 11,411.00 | 1,200.00 | 13,693.20 | 1,000.00 | 11,411.00 | | 0024 | 724-02-00100 | Rumble Strips (Shoulder/Edge) | 22.822 | MILE | 1,000.00 | 22,822.00 | 1,200.00 | 27,386.40 | 1,000.00 | 22,822.00 | | 0025 | 727-01-00100 | Mobilization | 1 | LUMP | 600,000.00 | 600,000.00 | 600,000.00 | 600,000.00 | 590,000.00 | 590,000.00 | | 0026 | 729-16-00200 | Object Marker Assembly (Type 2) | 80 | EACH | 75.00 | 6,000.00 | 60.00 | 4,800.00 | 115.00 | 9,200.00 | | 0027 | 729-16-00300 | Object Marker Assembly (Type 3) | 12 | EACH | 85.00 | 1,020.00 | 150.00 | 1,800.00 | 135.00 | 1,620.00 | | 0028 | 731-02-00100 | Reflectorized Raised Pavement Markers | 1,864 | EACH | 4.00 | 7,456.00 | 6.00 | 11,184.00 | 5.00 | 9,320.00 | | 0029 | 732-01-02080 | Plastic Pavement Striping (24" Width) (Thermoplastic 125 mil) | 12 | LNFT | 10.00 | 120.00 | 17.50 | 210.00 | 15.00 | 180.00 | | 0030 | 732-02-02000 | Plastic Pavement Striping (Solid Line) (4" Width) (Thermoplastic 90 mil) | 30.306 | MILE | 4,000.00 | 121,224.00 | 6,250.00 | 189,412.50 | 5,500.00 | 166,683.00 | | 0031 | 732-03-02000 | Plastic Pavement Striping (Broken Line) (4" Width) (Thermoplastic 90 mil) | 11.301 | MILE | 1,500.00 | 16,951.50 | 3,500.00 | 39,553.50 | 2,900.00 | 32,772.90 | | 0032 | 732-04-00001 | Plastic Pavement Legends and Symbols (Message) STOP | 1 | EACH | 400.00 | 400.00 | 600.00 | 600.00 | 500.00 | 500.00 | | 0033 | 732-04-01000 | Plastic Pavement Legends and Symbols (AHEAD) | 1 | EACH | 500.00 | 500.00 | 600.00 | 600.00 | 500.00 | 500.00 | | 0034 | 732-05-00100 | Removal of Existing Markings | 0.095 | MILE | 2,900.00 | 275.50 | 10,000.00 | 950.00 | 8,500.00 | 807.50 | | 0035 | 735-01-00100 | Mailboxes | 123 | EACH | 20.00 | 2,460.00 | 10.00 | 1,230.00 | 1.00 | 123.00 | | 0036 | 735-02-00100 | Mailbox Supports (Single) | 115 | EACH | 210.00 | 24,150.00 | 250.00 | 28,750.00 | 240.00 | 27,600.00 | | 0037 | 735-03-00100 | Mailbox Supports (Double) | 4 | EACH | 220.00 | 880.00 | 320.00 | 1,280.00 | 295.00 | 1,180.00 | | 0038 | 739-01-00100 | Hydro-Seeding | 6.15 | ACRE | 2,700.00 | 16,605.00 | 3,000.00 | 18,450.00 | 2,700.00 | 16,605.00 | | 0039 | 740-01-00100 | Construction Layout | 1 | LUMP | 30,000.00 | 30,000.00 | 1,000.00 | 1,000.00 | 25,000.00 | 25,000.00 | | 0040 | 815-03-00300 | Joint Seal (Poured) | 996 | LNFT | 37.00 | 36,852.00 | 47.50 | 47,310.00 | 20.00 | 19,920.00 | | 0041 | NS-500-00240 | Sawing and Sealing Transverse Joints in Asphalt Concrete Overlay | 264 | LNFT | 50.00 | 13,200.00 | 5.50 | 1,452.00 | 12.00 | 3,168.00 | | 0042 | NS-500-00260 | Sawcuts in Asphalt Concrete Lifts | 264 | LNFT | 27.00 | 7,128.00 | 5.50 | 1,452.00 | 10.00 | 2,640.00 | | 0043 | NS-600-00220 | Saw Cutting Portland Cement Concrete Pavement | 7,194 | INLF | 5.00 | 35,970.00 | 2.00 | 14,388.00 | 1.75 | 12,589.50 | | 0044 | NS-602-00001 | Milling Concrete Pavement | 586.8 | SQYD | 65.00 | 38,142.00 | 63.00 | 36,968.40 | 45.00 | 26,406.00 | | | | | | | | | | | | | | | | CONTRACTOR TOTAL | | | | 10,712,520.85 | | 10,858,509.59 | | 12,007,828.90 |
|