Proposal:H.016052.6
Parish:St. Martin
Routes:LA 96
Description:LA 96: 0.12 MI EAST OF LA 347 - LA 352
Type Construction:DRAINAGE STRUCTURES, MILLING ASPHALT PAVEMENT, PAVEMENT PATCHING, ASPHALT CONCRETE OVERLAY, AND RELATED WORK.
Estimated Construction Cost:$13,967,716.44
| Rank | License | Bidder | Construction Bid |
| 1 | 34356 | Prairie Contractors LLC | $12,025,234.09 |
| 2 | 51821 | Elliott Construction, LLC | $12,868,343.61 |
| 3 | 33663 | Glenn Lege Construction LLC | $14,794,905.38 |
Line Number | Item Number | Item Description | Quantity | Unit of Measure | - 1 - Prairie Contractors LLC | - 2 - Elliott Construction, LLC | - 3 - Glenn Lege Construction LLC | | Unit Price | Total Amount | Unit Price | Total Amount | Unit Price | Total Amount | | 0001 | 202-01-00100 | Removal of Structures and Obstructions | 1 | LUMP | 9,000.00 | 9,000.00 | 6,500.00 | 6,500.00 | 26,234.00 | 26,234.00 | | 0002 | 202-02-02020 | Removal of Asphalt Pavement | 108.2 | SQYD | 150.00 | 16,230.00 | 40.00 | 4,328.00 | 108.16 | 11,702.91 | | 0003 | 202-02-04560 | Removal of Bridge Joint STR. #2380311471 | 80 | LNFT | 12.50 | 1,000.00 | 11.00 | 880.00 | 13.12 | 1,049.60 | | 0004 | 202-02-14500 | Removal of Guard Rail | 190 | LNFT | 15.00 | 2,850.00 | 28.00 | 5,320.00 | 17.41 | 3,307.90 | | 0005 | 202-02-32100 | Removal of Pipe (Cross Drain) (12" - 42") | 404 | LNFT | 30.00 | 12,120.00 | 84.00 | 33,936.00 | 194.30 | 78,497.20 | | 0006 | 202-02-32100 | Removal of Pipe (Cross Drain) (60") | 77 | LNFT | 30.00 | 2,310.00 | 132.00 | 10,164.00 | 141.34 | 10,883.18 | | 0007 | 203-07-00100 | Borrow (Vehicular Measurement) | 1,253 | CUYD | 100.00 | 125,300.00 | 50.00 | 62,650.00 | 91.60 | 114,774.80 | | 0008 | 204-05-00100 | Temporary Sediment Check Dams (Hay) | 100 | EACH | 120.00 | 12,000.00 | 165.00 | 16,500.00 | 174.05 | 17,405.00 | | 0009 | 204-06-00100 | Temporary Silt Fencing | 778 | LNFT | 4.00 | 3,112.00 | 4.50 | 3,501.00 | 4.64 | 3,609.92 | | 0010 | 401-02-00100 | Aggregate Surface Course (Adjusted Vehicular Measurement) | 3,736 | CUYD | 62.00 | 231,632.00 | 70.00 | 261,520.00 | 96.48 | 360,449.28 | | 0011 | 402-01-00101 | Traffic Maintenance Surfacing (Aggregate) (Vehicular Measurement) | 300 | CUYD | 50.00 | 15,000.00 | 100.00 | 30,000.00 | 71.27 | 21,381.00 | | 0012 | 502-01-00100 | Asphalt Concrete | 37,310.5 | TON | 125.00 | 4,663,812.50 | 135.00 | 5,036,917.50 | 157.26 | 5,867,449.23 | | 0013 | 502-01-00200 | Asphalt Concrete, Drives, Turnouts and Miscellaneous | 3,851.1 | TON | 196.00 | 754,815.60 | 185.00 | 712,453.50 | 208.39 | 802,530.73 | | 0014 | 509-01-00100 | Milling Asphalt Pavement | 165,222 | SQYD | 3.00 | 495,666.00 | 2.75 | 454,360.50 | 2.86 | 472,534.92 | | 0015 | 509-02-00100 | Contractor Retained Reclaimed Asphalt Pavement | -6,906 | CUYD | 0.01 | -69.06 | 0.01 | -69.06 | 0.01 | -69.06 | | 0016 | 510-01-00300 | Pavement Patching (18" Minimum Thickness) | 13,843 | SQYD | 122.50 | 1,695,767.50 | 185.00 | 2,560,955.00 | 176.70 | 2,446,058.10 | | 0017 | 602-12-00100 | Undersealing Pavement | 17 | TON | 4,250.00 | 72,250.00 | 3,850.00 | 65,450.00 | 4,061.23 | 69,040.91 | | 0018 | 602-14-00100 | Holes | 16 | EACH | 600.00 | 9,600.00 | 550.00 | 8,800.00 | 580.18 | 9,282.88 | | 0019 | 701-01-01063 | Cross Drain Pipe (42" RCP/RPVCP) | 48 | LNFT | 750.00 | 36,000.00 | 685.00 | 32,880.00 | 403.09 | 19,348.32 | | 0020 | 701-02-01000 | Cross Drain Pipe Arch (24" Equiv. RCPA) | 230 | LNFT | 475.00 | 109,250.00 | 435.00 | 100,050.00 | 354.81 | 81,606.30 | | 0021 | 701-02-01020 | Cross Drain Pipe Arch (30" Equiv. RCPA) | 160 | LNFT | 550.00 | 88,000.00 | 380.00 | 60,800.00 | 321.89 | 51,502.40 | | 0022 | 701-02-01040 | Cross Drain Pipe Arch (36" Equiv. RCPA) | 48 | LNFT | 550.00 | 26,400.00 | 450.00 | 21,600.00 | 389.05 | 18,674.40 | | 0023 | 701-14-00100 | Cleaning Existing Pipes | 436 | LNFT | 85.00 | 37,060.00 | 50.00 | 21,800.00 | 13.12 | 5,720.32 | | 0024 | 701-17-00100 | Trench Excavation Safety Protection (Depth >5 feet) | 312 | LNFT | 6.00 | 1,872.00 | 25.00 | 7,800.00 | 126.18 | 39,368.16 | | 0025 | 704-07-00200 | Guard Rail Transitions (Double Thrie Beam) | 75 | LNFT | 160.00 | 12,000.00 | 138.00 | 10,350.00 | 163.96 | 12,297.00 | | 0026 | 704-10-00204 | Guard Rail End Treatment, MASH, (TL-2 Tangent) | 1 | EACH | 5,000.00 | 5,000.00 | 3,300.00 | 3,300.00 | 3,935.10 | 3,935.10 | | 0027 | 704-10-00205 | Guard Rail End Treatment, MASH, (TL-3 Tangent) | 2 | EACH | 4,500.00 | 9,000.00 | 3,800.00 | 7,600.00 | 4,525.37 | 9,050.74 | | 0028 | 711-01-04020 | Riprap (55 lb, 24" Thick) | 214 | SQYD | 195.00 | 41,730.00 | 115.00 | 24,610.00 | 121.99 | 26,105.86 | | 0029 | 711-04-00100 | Geotextile Fabric | 214 | SQYD | 6.00 | 1,284.00 | 5.00 | 1,070.00 | 9.18 | 1,964.52 | | 0030 | 713-01-00100 | Temporary Signs and Barricades | 1 | LUMP | 510,000.00 | 510,000.00 | 125,000.00 | 125,000.00 | 612,367.15 | 612,367.15 | | 0031 | 713-03-01000 | Temporary Pavement Markings (Broken Line) (4" Width) (4' Length) | 34.45 | MILE | 650.00 | 22,392.50 | 800.00 | 27,560.00 | 655.85 | 22,594.03 | | 0032 | 713-03-02000 | Temporary Pavement Markings (Broken Line) (4" Width) (10' Length) | 34.45 | MILE | 1.00 | 34.45 | 550.00 | 18,947.50 | 580.18 | 19,987.20 | | 0033 | 713-04-01000 | Temporary Pavement Markings (Solid Line) (4" Width) | 68.9 | MILE | 1.00 | 68.90 | 770.00 | 53,053.00 | 812.25 | 55,964.03 | | 0034 | 713-11-00100 | Portable Changeable Message Signs | 2 | EACH | 18,000.00 | 36,000.00 | 4,400.00 | 8,800.00 | 18,565.60 | 37,131.20 | | 0035 | 724-01-00100 | Rumble Strips (Centerline) | 10.289 | MILE | 1,200.00 | 12,346.80 | 1,100.00 | 11,317.90 | 1,160.35 | 11,938.84 | | 0036 | 724-02-00100 | Rumble Strips (Shoulder/Edge) | 20.579 | MILE | 1,200.00 | 24,694.80 | 1,100.00 | 22,636.90 | 1,160.35 | 23,878.84 | | 0037 | 726-01-00100 | Bedding Material | 68.9 | CUYD | 165.00 | 11,368.50 | 200.00 | 13,780.00 | 200.17 | 13,791.71 | | 0038 | 727-01-00100 | Mobilization | 1 | LUMP | 1,050,000.00 | 1,050,000.00 | 750,000.00 | 750,000.00 | 750,948.25 | 750,948.25 | | 0039 | 729-16-00200 | Object Marker Assembly (Type 2) | 44 | EACH | 70.00 | 3,080.00 | 85.00 | 3,740.00 | 87.03 | 3,829.32 | | 0040 | 729-16-00300 | Object Marker Assembly (Type 3) | 8 | EACH | 150.00 | 1,200.00 | 95.00 | 760.00 | 98.63 | 789.04 | | 0041 | 731-02-00100 | Reflectorized Raised Pavement Markers | 2,021 | EACH | 5.00 | 10,105.00 | 5.00 | 10,105.00 | 4.64 | 9,377.44 | | 0042 | 732-02-02000 | Plastic Pavement Striping (Solid Line) (4" Width) (Thermoplastic 90 mil) | 34.196 | MILE | 3,800.00 | 129,944.80 | 4,070.00 | 139,177.72 | 4,293.30 | 146,813.69 | | 0043 | 732-03-02000 | Plastic Pavement Striping (Broken Line) (4" Width) (Thermoplastic 90 mil) | 7.689 | MILE | 1,200.00 | 9,226.80 | 1,100.00 | 8,457.90 | 1,160.35 | 8,921.93 | | 0044 | 732-03-02010 | Plastic Pavement Striping (Dotted Line)(4" W)(2' L)(Thermo 90 mil) | 0.024 | MILE | 20,000.00 | 480.00 | 16,500.00 | 396.00 | 17,405.25 | 417.73 | | 0045 | 732-05-00100 | Removal of Existing Markings | 0.057 | MILE | 15,000.00 | 855.00 | 11,000.00 | 627.00 | 11,603.50 | 661.40 | | 0046 | 735-01-00100 | Mailboxes | 289 | EACH | 10.00 | 2,890.00 | 28.00 | 8,092.00 | 29.01 | 8,383.89 | | 0047 | 735-02-00100 | Mailbox Supports (Single) | 289 | EACH | 250.00 | 72,250.00 | 220.00 | 63,580.00 | 232.07 | 67,068.23 | | 0048 | 739-01-00100 | Hydro-Seeding | 5.85 | ACRE | 3,250.00 | 19,012.50 | 3,000.00 | 17,550.00 | 3,132.95 | 18,327.76 | | 0049 | 740-01-00100 | Construction Layout | 1 | LUMP | 15,000.00 | 15,000.00 | 25,000.00 | 25,000.00 | 453,323.52 | 453,323.52 | | 0050 | 805-15-02100 | Reinforced Concrete Box Culverts (Precast) (8' x 8') | 56 | LNFT | 3,500.00 | 196,000.00 | 4,200.00 | 235,200.00 | 2,063.30 | 115,544.80 | | 0051 | 805-17-00100 | Reinforced Concrete Box Culvert Headwall STEEL = 2786 LBS; CONCRETE = 40.41 CUYD | 2 | EACH | 100,000.00 | 200,000.00 | 75,000.00 | 150,000.00 | 63,086.21 | 126,172.42 | | 0052 | 812-01-00200 | Treated Timber (Coastal Treatment) | 3 | MFBM | 9,000.00 | 27,000.00 | 3,900.00 | 11,700.00 | 6,996.61 | 20,989.83 | | 0053 | 815-03-00200 | Joint Seal (Preformed Silicone) | 80 | LNFT | 80.00 | 6,400.00 | 11.00 | 880.00 | 75.42 | 6,033.60 | | 0054 | NS-500-00240 | Sawing and Sealing Transverse Joints in Asphalt Concrete Overlay | 104 | LNFT | 4.25 | 442.00 | 5.00 | 520.00 | 4.07 | 423.28 | | 0055 | NS-500-00260 | Sawcuts in Asphalt Concrete Lifts | 104 | LNFT | 1.75 | 182.00 | 2.00 | 208.00 | 1.75 | 182.00 | | 0056 | NS-502-04200 | Reinforced Paving Mat for Asphalt Concrete Overlay | 161,525 | SQYD | 6.00 | 969,150.00 | 6.75 | 1,090,293.75 | 7.08 | 1,143,597.00 | | 0057 | NS-502-04210 | Asphalt Tack Coat | 38,766 | GAL | 4.50 | 174,447.00 | 12.75 | 494,266.50 | 13.35 | 517,526.10 | | 0058 | NS-602-00001 | Milling Concrete Pavement | 266.7 | SQYD | 115.00 | 30,670.50 | 40.00 | 10,668.00 | 45.84 | 12,225.53 | | | | | | | | | | | | | | | | CONTRACTOR TOTAL | | | | 12,025,234.09 | | 12,868,343.61 | | 14,794,905.38 |
|