Proposal:H.015767.6
Parish:West Baton Rouge
Routes:LA 1
Description:LA 1: INTRACOASTAL BR - US 190 WB
Type Construction:CLEARING AND GRUBBING, MILLING ASPHALT CONCRETE, PAVEMENT PATCHING, CLASS II BASE COURSE, ASPHALT CONCRETE OVERLAY, CONCRETE PIER PROTECTION SYSTEM, HIGH-DENSITY POLYURETHANE FOAM, AND RELATED WORK.
Estimated Construction Cost:$12,616,591.02
| Rank | License | Bidder | Construction Bid |
| 1 | 00046 | Barber Bros. Contracting Co., L.L.C | $12,371,470.63 |
| 2 | 30774 | Progressive Construction Co., LLC | $13,794,027.12 |
| 3 | 06276 | Barriere Construction Co., LLC | $15,186,345.81 |
| 4 | 39462 | JB JAMES CONSTRUCTION LLC | $18,118,198.13 |
Line Number | Item Number | Item Description | Quantity | Unit of Measure | - 1 - Barber Bros. Contracting Co., L.L.C | - 2 - Progressive Construction Co., LLC | - 3 - Barriere Construction Co., LLC | - 4 - JB JAMES CONSTRUCTION LLC | | Unit Price | Total Amount | Unit Price | Total Amount | Unit Price | Total Amount | Unit Price | Total Amount | | 0001 | 201-01-00200 | Clearing and Grubbing (Selective) | 0.1 | LUMP | 1,000.00 | 1,000.00 | 35,000.00 | 35,000.00 | 55,000.00 | 55,000.00 | 700,000.00 | 700,000.00 | | 0002 | 202-02-03030 | Removal of Pavement Structure (12") | 7,647.6 | SQYD | 12.00 | 91,771.20 | 15.00 | 114,714.00 | 10.75 | 82,211.70 | 31.00 | 237,075.60 | | 0003 | 202-02-03030 | Removal of Pavement Structure (4") | 32,622 | SQYD | 7.00 | 228,354.00 | 7.65 | 249,558.30 | 6.00 | 195,732.00 | 20.00 | 652,440.00 | | 0004 | 202-02-14500 | Removal of Guard Rail | 9,062 | LNFT | 8.00 | 72,496.00 | 13.00 | 117,806.00 | 8.00 | 72,496.00 | 12.00 | 108,744.00 | | 0005 | 202-02-40120 | Removal of Traffic Detectors and Associated Equipment | 1 | LUMP | 1,400.00 | 1,400.00 | 5,700.00 | 5,700.00 | 12,570.00 | 12,570.00 | 2,500.00 | 2,500.00 | | 0006 | 203-07-00100 | Borrow (Vehicular Measurement) | 407 | CUYD | 145.00 | 59,015.00 | 70.00 | 28,490.00 | 250.00 | 101,750.00 | 249.00 | 101,343.00 | | 0007 | 204-06-00100 | Temporary Silt Fencing | 4,251 | LNFT | 2.50 | 10,627.50 | 3.00 | 12,753.00 | 1.75 | 7,439.25 | 8.00 | 34,008.00 | | 0008 | 302-02-08020 | Class II Base Course (8" Thick) (Crushed Stone) | 7,640.2 | SQYD | 48.00 | 366,729.60 | 40.00 | 305,608.00 | 45.00 | 343,809.00 | 60.00 | 458,412.00 | | 0009 | 402-01-00101 | Traffic Maintenance Surfacing (Aggregate) (Vehicular Measurement) | 300 | CUYD | 25.00 | 7,500.00 | 125.00 | 37,500.00 | 1.00 | 300.00 | 200.00 | 60,000.00 | | 0010 | 502-01-00100 | Asphalt Concrete | 16,590.8 | TON | 140.00 | 2,322,712.00 | 142.00 | 2,355,893.60 | 132.00 | 2,189,985.60 | 118.00 | 1,957,714.40 | | 0011 | 502-01-00200 | Asphalt Concrete, Drives, Turnouts and Miscellaneous | 1,031.6 | TON | 220.00 | 226,952.00 | 268.00 | 276,468.80 | 275.00 | 283,690.00 | 210.00 | 216,636.00 | | 0012 | 509-01-00100 | Milling Asphalt Pavement | 68,275.9 | SQYD | 3.00 | 204,827.70 | 3.50 | 238,965.65 | 13.00 | 887,586.70 | 3.00 | 204,827.70 | | 0013 | 509-02-00100 | Contractor Retained Reclaimed Asphalt Pavement | -4,202 | CUYD | 0.00 | 0.00 | 0.10 | -420.20 | 0.01 | -42.02 | 0.01 | -42.02 | | 0014 | 602-02-00200 | Cleaning and Resealing Existing Longitudinal Pavement Joints | 55,255 | LNFT | 3.00 | 165,765.00 | 3.25 | 179,578.75 | 3.50 | 193,392.50 | 2.90 | 160,239.50 | | 0015 | 602-02-00300 | Cleaning and Resealing Existing Transverse Pavements Joints | 66,306 | LNFT | 3.00 | 198,918.00 | 3.35 | 222,125.10 | 3.50 | 232,071.00 | 2.90 | 192,287.40 | | 0016 | 602-03-00100 | Cleaning and Sealing Random Cracks | 16,577 | LNFT | 6.00 | 99,462.00 | 8.50 | 140,904.50 | 5.00 | 82,885.00 | 5.00 | 82,885.00 | | 0017 | 602-05-01200 | Full Depth Patching of Jointed Concrete Pavement (16.0 square yards and under) (10" Thick) | 1,552 | SQYD | 280.00 | 434,560.00 | 340.00 | 527,680.00 | 500.00 | 776,000.00 | 620.00 | 962,240.00 | | 0018 | 602-05-02200 | Full Depth Patching of Jointed Concrete Pavement (16.1 square yards to 48.0 square yards) (10" Thick) | 2,632.1 | SQYD | 250.00 | 658,025.00 | 270.00 | 710,667.00 | 300.00 | 789,630.00 | 520.00 | 1,368,692.00 | | 0019 | 602-05-03200 | Full Depth Patching of Jointed Concrete Pavement (48.1 square yards and over) (10" Thick) | 2,400 | SQYD | 220.00 | 528,000.00 | 250.00 | 600,000.00 | 275.00 | 660,000.00 | 460.00 | 1,104,000.00 | | 0020 | 602-08-00100 | Diamond Grinding Concrete Pavement | 1,104 | SQYD | 24.00 | 26,496.00 | 25.00 | 27,600.00 | 28.00 | 30,912.00 | 42.00 | 46,368.00 | | 0021 | 602-09-00100 | Diamond Grooving Concrete Pavement | 1,104 | SQYD | 20.00 | 22,080.00 | 20.00 | 22,080.00 | 7.50 | 8,280.00 | 35.00 | 38,640.00 | | 0022 | 602-10-00100 | Longitudinal Shoulder Joints | 50,380 | LNFT | 3.00 | 151,140.00 | 3.00 | 151,140.00 | 5.00 | 251,900.00 | 2.00 | 100,760.00 | | 0023 | 602-15-00100 | Dowel Bar Retrofit | 15,072 | EACH | 104.50 | 1,575,024.00 | 117.00 | 1,763,424.00 | 200.00 | 3,014,400.00 | 140.00 | 2,110,080.00 | | 0024 | 704-01-01020 | Guard Rail (Single Thrie Beam) (6'-3" post spacing) | 368.8 | LNFT | 48.00 | 17,702.40 | 86.25 | 31,809.00 | 50.00 | 18,440.00 | 43.00 | 15,858.40 | | 0025 | 704-03-00200 | Blocked Out Guard Rail - 31", (6'-3" Post Spacing) | 7,131.3 | LNFT | 30.00 | 213,939.00 | 34.50 | 246,029.85 | 30.00 | 213,939.00 | 27.00 | 192,545.10 | | 0026 | 704-03-00205 | Blocked Out Guard Rail - 31", (18.75" Post Spacing) | 675 | LNFT | 64.00 | 43,200.00 | 86.25 | 58,218.75 | 65.00 | 43,875.00 | 58.00 | 39,150.00 | | 0027 | 704-05-00300 | Guard Rail Anchor Sections - 31", (Trailing End) | 306.9 | LNFT | 193.00 | 59,231.70 | 172.50 | 52,940.25 | 200.00 | 61,380.00 | 175.00 | 53,707.50 | | 0028 | 704-06-00200 | Guard Rail Bridge Attachments (Single Thrie Beam) | 62.5 | LNFT | 60.00 | 3,750.00 | 115.00 | 7,187.50 | 62.00 | 3,875.00 | 54.00 | 3,375.00 | | 0029 | 704-07-00200 | Guard Rail Transitions (Double Thrie Beam) | 300 | LNFT | 130.00 | 39,000.00 | 172.50 | 51,750.00 | 135.00 | 40,500.00 | 119.00 | 35,700.00 | | 0030 | 704-07-00300 | Guard Rail Transitions (Full Post to Quarter Post) | 175 | LNFT | 66.00 | 11,550.00 | 172.50 | 30,187.50 | 65.00 | 11,375.00 | 60.00 | 10,500.00 | | 0031 | 704-10-00120 | Guard Rail End Treatment, MASH, (TL-3 Flared) | 5 | EACH | 3,400.00 | 17,000.00 | 3,680.00 | 18,400.00 | 3,500.00 | 17,500.00 | 3,075.00 | 15,375.00 | | 0032 | 704-10-00205 | Guard Rail End Treatment, MASH, (TL-3 Tangent) | 31 | EACH | 3,800.00 | 117,800.00 | 4,025.00 | 124,775.00 | 3,900.00 | 120,900.00 | 3,425.00 | 106,175.00 | | 0033 | 704-10-00305 | Guard Rail End Treatment, MASH, (TL-3 Bi-Directional) | 1 | EACH | 15,000.00 | 15,000.00 | 15,525.00 | 15,525.00 | 15,500.00 | 15,500.00 | 13,400.00 | 13,400.00 | | 0034 | 707-01-00100 | Concrete Curb | 250 | LNFT | 100.00 | 25,000.00 | 45.00 | 11,250.00 | 50.00 | 12,500.00 | 90.00 | 22,500.00 | | 0035 | 707-04-00100 | Asphalt Curb | 87 | LNFT | 100.00 | 8,700.00 | 80.00 | 6,960.00 | 140.00 | 12,180.00 | 175.00 | 15,225.00 | | 0036 | 713-01-00100 | Temporary Signs and Barricades | 1 | LUMP | 745,000.00 | 745,000.00 | 730,000.00 | 730,000.00 | 900,000.00 | 900,000.00 | 2,000,000.00 | 2,000,000.00 | | 0037 | 713-03-01000 | Temporary Pavement Markings (Broken Line) (4" Width) (4' Length) | 4.995 | MILE | 325.00 | 1,623.38 | 350.00 | 1,748.25 | 375.00 | 1,873.13 | 300.00 | 1,498.50 | | 0038 | 713-03-02000 | Temporary Pavement Markings (Broken Line) (4" Width) (10' Length) | 2.549 | MILE | 500.00 | 1,274.50 | 550.00 | 1,401.95 | 550.00 | 1,401.95 | 500.00 | 1,274.50 | | 0039 | 713-04-01000 | Temporary Pavement Markings (Solid Line) (4" Width) | 6.261 | MILE | 700.00 | 4,382.70 | 2,400.00 | 15,026.40 | 800.00 | 5,008.80 | 700.00 | 4,382.70 | | 0040 | 724-02-00100 | Rumble Strips (Shoulder/Edge) | 9.21 | MILE | 330.00 | 3,039.30 | 600.00 | 5,526.00 | 300.00 | 2,763.00 | 275.00 | 2,532.75 | | 0041 | 727-01-00100 | Mobilization | 1 | LUMP | 1,200,000.00 | 1,200,000.00 | 1,350,000.00 | 1,350,000.00 | 1,186,000.00 | 1,186,000.00 | 1,750,000.00 | 1,750,000.00 | | 0042 | 729-16-00300 | Object Marker Assembly (Type 3) | 65 | EACH | 90.00 | 5,850.00 | 110.00 | 7,150.00 | 95.00 | 6,175.00 | 85.00 | 5,525.00 | | 0043 | 731-02-00100 | Reflectorized Raised Pavement Markers | 3,269 | EACH | 4.50 | 14,710.50 | 4.60 | 15,037.40 | 4.50 | 14,710.50 | 4.00 | 13,076.00 | | 0044 | 732-01-01040 | Plastic Pavement Striping (8" Width) (Thermoplastic 90 mil) | 11,721 | LNFT | 2.75 | 32,232.75 | 2.88 | 33,756.48 | 3.00 | 35,163.00 | 2.50 | 29,302.50 | | 0045 | 732-01-02080 | Plastic Pavement Striping (24" Width) (Thermoplastic 125 mil) | 492 | LNFT | 11.00 | 5,412.00 | 11.50 | 5,658.00 | 12.00 | 5,904.00 | 10.00 | 4,920.00 | | 0046 | 732-02-02000 | Plastic Pavement Striping (Solid Line) (4" Width) (Thermoplastic 90 mil) | 22.271 | MILE | 3,800.00 | 84,629.80 | 4,025.00 | 89,640.78 | 4,000.00 | 89,084.00 | 3,500.00 | 77,948.50 | | 0047 | 732-03-02000 | Plastic Pavement Striping (Broken Line) (4" Width) (Thermoplastic 90 mil) | 9.078 | MILE | 1,600.00 | 14,524.80 | 1,725.00 | 15,659.55 | 1,750.00 | 15,886.50 | 1,500.00 | 13,617.00 | | 0048 | 732-03-02030 | Plastic Pavement Striping (Dotted Line)(8" W)(2' L)(Thermo 90 mil) | 1.465 | MILE | 3,300.00 | 4,834.50 | 3,450.00 | 5,054.25 | 3,450.00 | 5,054.25 | 4,000.00 | 5,860.00 | | 0049 | 732-03-02040 | Plastic Pavement Striping (Dotted Line)(8" W)(3' L)(Thermo 90 mil) | 0.232 | MILE | 3,500.00 | 812.00 | 3,680.00 | 853.76 | 3,750.00 | 870.00 | 4,000.00 | 928.00 | | 0050 | 732-04-01080 | Plastic Pavement Legends and Symbols (Arrow - Left Turn) | 6 | EACH | 275.00 | 1,650.00 | 287.50 | 1,725.00 | 275.00 | 1,650.00 | 250.00 | 1,500.00 | | 0051 | 732-04-01100 | Plastic Pavement Legends and Symbols (Arrow - Right Turn) | 6 | EACH | 275.00 | 1,650.00 | 287.50 | 1,725.00 | 275.00 | 1,650.00 | 250.00 | 1,500.00 | | 0052 | 732-04-15020 | Plastic Pavement Legends and Symbols (ONLY) | 8 | EACH | 275.00 | 2,200.00 | 287.50 | 2,300.00 | 275.00 | 2,200.00 | 250.00 | 2,000.00 | | 0053 | 732-05-00100 | Removal of Existing Markings | 8.151 | MILE | 3,300.00 | 26,898.30 | 3,450.00 | 28,120.95 | 3,450.00 | 28,120.95 | 5,000.00 | 40,755.00 | | 0054 | 740-01-00100 | Construction Layout | 1 | LUMP | 50,000.00 | 50,000.00 | 100,000.00 | 100,000.00 | 16,000.00 | 16,000.00 | 600,000.00 | 600,000.00 | | 0055 | 810-06-00100 | Concrete Pier Protection System (Vehicle) 7 FEET WIDE BARRIER FOOTING | 554 | LNFT | 1,100.00 | 609,400.00 | 1,150.00 | 637,100.00 | 900.00 | 498,600.00 | 1,600.00 | 886,400.00 | | 0056 | NS-300-01000 | High-Density Polyurethane Foam 469,168 LB | 67,024 | SQYD | 20.50 | 1,373,992.00 | 27.00 | 1,809,648.00 | 18.00 | 1,206,432.00 | 16.00 | 1,072,384.00 | | 0057 | NS-500-00220 | Sawing and Sealing Longitudinal Joints in Asphalt Concrete Overlay | 13,056 | LNFT | 2.00 | 26,112.00 | 2.00 | 26,112.00 | 5.25 | 68,544.00 | 1.70 | 22,195.20 | | 0058 | NS-500-00240 | Sawing and Sealing Transverse Joints in Asphalt Concrete Overlay | 19,257 | LNFT | 2.00 | 38,514.00 | 2.00 | 38,514.00 | 6.00 | 115,542.00 | 1.70 | 32,736.90 | | 0059 | NS-700-00840 | Impact Attenuator (Reusable, Test Level 3) | 1 | EACH | 60,000.00 | 60,000.00 | 39,000.00 | 39,000.00 | 65,000.00 | 65,000.00 | 58,000.00 | 58,000.00 | | 0060 | NS-713-00009 | Portable Changeable Message Sign (with communications) | 2 | EACH | 12,000.00 | 24,000.00 | 20,000.00 | 40,000.00 | 25,000.00 | 50,000.00 | 25,000.00 | 50,000.00 | | 0061 | NS-736-00022 | Wireless Magnetometer Vehicle Detection System (Magnetometers) | 5 | EACH | 2,800.00 | 14,000.00 | 3,000.00 | 15,000.00 | 3,750.00 | 18,750.00 | 3,300.00 | 16,500.00 | | | | | | | | | | | | | | | | | | CONTRACTOR TOTAL | | | | 12,371,470.63 | | 13,794,027.12 | | 15,186,345.81 | | 18,118,198.13 |
|