Bid Tabulations for the Letting of 6/11/2025 LA DOTD Headquarters

Proposal:H.014802.6
Parish:Lafourche, Terrebonne
Routes:LA 24, LA 316
Description:LA316&LA24:MILL,OVRLY,GRADE RAISING,HFST
Type Construction:GRADING, DRAINAGE STRUCTURES, MILLING ASPHALT CONCRETE AND PORTLAND CEMENT CONCRETE PAVEMENTS, PAVEMENT PATCHING, CLASS II BASE COURSE, ASPHALT CONCRETE OVERLAY, FLEXIBLE PAVEMENT HIGH FRICTION SURFACE TREATMENT, AND RELATED WORK.
Estimated Construction Cost:$12,144,670.00
Rank License BidderConstruction Bid
106276Barriere Construction Co., LLC$8,549,962.99
262139Huey P. Stockstill, LLC$8,944,016.85
373475Madden Gulf Coast, LLC$10,603,867.57


Line
Number
Item NumberItem DescriptionQuantityUnit of
Measure
- 1 -
Barriere Construction Co., LLC
- 2 -
Huey P. Stockstill, LLC
- 3 -
Madden Gulf Coast, LLC
Unit PriceTotal
Amount
Unit PriceTotal
Amount
Unit PriceTotal
Amount
0001201-01-00200Clearing and Grubbing (Selective) 0.2   LUMP40,000.0040,000.0023,000.0023,000.0030,000.0030,000.00
0002202-02-00010Removal of Existing Drainage Safety End Treatment1     EACH5,000.005,000.001,100.001,100.001,250.001,250.00
0003202-02-03030Removal of Pavement Structure 8,213     SQYD18.00147,834.0014.00114,982.0030.25248,443.25
0004202-02-06100Removal of Concrete Walks and Drives 256.5   SQYD40.0010,260.0060.0015,390.0050.0012,825.00
0005202-02-06140Removal of Curbs (Concrete) 992     LNFT22.0021,824.0011.0010,912.0030.0029,760.00
0006202-02-14500Removal of Guard Rail 665     LNFT8.005,320.009.005,985.008.005,320.00
0007202-02-32100Removal of Pipe (Cross Drain) 18" CMP3     LNFT28.0084.00205.00615.0030.0090.00
0008202-02-32100Removal of Pipe (Cross Drain) 18" Plastic1     LNFT28.0028.00205.00205.0030.0030.00
0009202-02-32100Removal of Pipe (Cross Drain) 18" RCP66     LNFT28.001,848.00205.0013,530.0030.001,980.00
0010202-02-32100Removal of Pipe (Cross Drain) 24" RCP64     LNFT28.001,792.00205.0013,120.0030.001,920.00
0011202-02-32120Removal of Pipe (Side Drain) 12" RCP118     LNFT28.003,304.0045.005,310.0030.003,540.00
0012202-02-32120Removal of Pipe (Side Drain) 15" CMP30     LNFT28.00840.0045.001,350.0030.00900.00
0013202-02-32120Removal of Pipe (Side Drain) 15" Plastic20     LNFT28.00560.0045.00900.0030.00600.00
0014202-02-32120Removal of Pipe (Side Drain) 18" CMP31     LNFT28.00868.0045.001,395.0030.00930.00
0015202-02-32120Removal of Pipe (Side Drain) 18" Plastic74     LNFT28.002,072.0045.003,330.0030.002,220.00
0016202-02-38300Removal of Sign and U-Channel Post 55     EACH20.001,100.0022.001,210.0020.001,100.00
0017203-01-00100General Excavation 3,886.5   CUYD35.00136,027.5042.00163,233.0060.00233,190.00
0018203-07-00100Borrow (Vehicular Measurement) 566     CUYD21.0011,886.0055.0031,130.00190.00107,540.00
0019204-06-00100Temporary Silt Fencing 300     LNFT5.001,500.008.502,550.007.742,322.00
0020302-02-08080Class II Base Course (8" Thick) (Asphalt Concrete Base) 16,756.8   SQYD49.00821,083.2055.00921,624.0067.001,122,705.60
0021402-01-00101Traffic Maintenance Surfacing (Aggregate) (Vehicular Measurement) 400     CUYD165.0066,000.0050.0020,000.0080.0032,000.00
0022502-01-00100Asphalt Concrete 23,836.2   TON129.003,074,869.80135.003,217,887.00133.003,170,214.60
0023502-01-00200Asphalt Concrete, Drives, Turnouts and Miscellaneous 2,065.3   TON222.00458,496.60250.00516,325.00275.00567,957.50
0024509-01-00100Milling Asphalt Pavement 140,534     SQYD2.00281,068.002.15302,148.105.00702,670.00
0025509-02-00100Contractor Retained Reclaimed Asphalt Pavement -4,870     CUYD0.01-48.700.01-48.700.01-48.70
0026510-01-00200Pavement Patching (12" Minimum Thickness) 6,575     SQYD134.00881,050.0095.00624,625.00127.75839,956.25
0027701-01-00900Cross Drain Pipe (18" RCP) 252     LNFT250.0063,000.00405.00102,060.00150.0037,800.00
0028701-01-01001Cross Drain Pipe (24" RCP) 228     LNFT305.0069,540.00500.00114,000.00185.0042,180.00
0029701-03-01002Storm Drain Pipe (15" RCP/RPVCP) 4     LNFT150.00600.00180.00720.00118.00472.00
0030701-04-01020Storm Drain Pipe Arch (18" Equiv. RCPA) 823     LNFT182.00149,786.00180.00148,140.00120.0098,760.00
0031701-07-00300Yard Drain Pipe (8") 16     LNFT45.00720.0095.001,520.0095.001,520.00
0032701-15-00100Concrete Collar 21     EACH1,650.0034,650.002,000.0042,000.002,950.0061,950.00
0033702-01-00100Junction Boxes 2' x 2'2     EACH5,700.0011,400.004,000.008,000.008,800.0017,600.00
0034702-03-00100Catch Basins (CB-01) 15     EACH5,500.0082,500.006,500.0097,500.005,500.0082,500.00
0035702-03-00400Catch Basins (CB-05) 2     EACH2,250.004,500.003,500.007,000.002,250.004,500.00
0036702-04-00100Adjusting Manholes 1     EACH1,650.001,650.00850.00850.004,800.004,800.00
0037702-04-00150Adjusting Manholes w/Manhole Adjustment Rings 1     EACH275.00275.00500.00500.00500.00500.00
0038702-04-00200Adjusting Catch Basins 5     EACH5,700.0028,500.007,000.0035,000.003,500.0017,500.00
0039704-01-01020Guard Rail (Single Thrie Beam) (6'-3" post spacing) 57     LNFT110.006,270.00125.007,125.00110.006,270.00
0040704-01-02005Guard Rail (DoubleThrie Beam) (18.75" Post Spacing) 42.2   LNFT400.0016,880.00450.0018,990.00400.0016,880.00
0041704-03-00200Blocked Out Guard Rail - 31", (6'-3" Post Spacing) 218.9   LNFT31.006,785.9035.007,661.5030.756,731.18
0042704-06-00200Guard Rail Bridge Attachments (Single Thrie Beam) 10     LNFT150.001,500.00165.001,650.00150.001,500.00
0043704-07-00200Guard Rail Transitions (Double Thrie Beam) 75     LNFT100.007,500.00110.008,250.0098.757,406.25
0044704-07-00250 MASH Guard Rail Transitions (Nested Thrie Beam) 65.7   LNFT127.008,343.90145.009,526.50127.008,343.90
0045704-10-00310Guard Rail End Treatment, NCHRP 350 - 31" (TL-3 Flared) 6     EACH3,200.0019,200.003,500.0021,000.003,200.0019,200.00
0046706-01-00100Concrete Walk (4" Thick) 124.9   SQYD95.0011,865.50130.0016,237.00105.0013,114.50
0047706-02-00200Concrete Drive (6" Thick) 142.3   SQYD104.5014,870.35135.0019,210.50115.0016,364.50
0048706-03-00300Incidental Concrete Paving (6" Thick) 47.3   SQYD97.004,588.10155.007,331.50175.008,277.50
0049706-04-00110Curb Ramps Type 417.9   SQYD260.004,654.00285.005,101.50265.004,743.50
0050706-04-00110Curb Ramps Type 613.7   SQYD260.003,562.00285.003,904.50265.003,630.50
0051706-04-00110Curb Ramps Type 726.6   SQYD260.006,916.00285.007,581.00265.007,049.00
0052707-01-00100Concrete Curb 125     LNFT46.005,750.0042.005,250.0035.004,375.00
0053707-01-00100Concrete Curb Barrier278     LNFT48.0013,344.0042.0011,676.0045.0012,510.00
0054707-01-00100Concrete Curb Mountable589     LNFT62.0036,518.0042.0024,738.0045.0026,505.00
0055711-01-03000Riprap (30 lb, 14" Thick) 253.5   SQYD138.5035,109.75200.0050,700.00165.0041,827.50
0056711-04-00100Geotextile Fabric 253.5   SQYD3.05773.181.70430.952.00507.00
0057713-01-00100Temporary Signs and Barricades 1     LUMP740,000.00740,000.00361,500.00361,500.001,050,000.001,050,000.00
0058713-02-00300Temporary Pavement Markings (8" Width) 1,488     LNFT0.25372.000.25372.000.35520.80
0059713-02-00500Temporary Pavement Markings (24" Width) 2,178     LNFT0.501,089.000.501,089.000.501,089.00
0060713-03-01000Temporary Pavement Markings (Broken Line) (4" Width) (4' Length) 16.558 MILE658.0010,895.16165.002,732.07350.005,795.30
0061713-03-02000Temporary Pavement Markings (Broken Line) (4" Width) (10' Length) 10.847 MILE500.005,423.50525.005,694.68750.008,135.25
0062713-04-01000Temporary Pavement Markings (Solid Line) (4" Width) 51.778 MILE772.0039,972.62850.0044,011.30950.0049,189.10
0063716-01-00100Mulch (Vegetative) 7.7   TON884.006,806.80900.006,930.00883.616,803.80
0064717-01-00100Seeding 152     LB11.001,672.0011.001,672.0010.531,600.56
0065718-01-00100Fertilizer 5,075     LB1.005,075.001.005,075.000.974,922.75
0066726-01-00100Bedding Material 891.3   CUYD98.0087,347.40120.00106,956.0075.0066,847.50
0067727-01-00100Mobilization 1     LUMP390,000.00390,000.00825,000.00825,000.00920,000.00920,000.00
0068729-16-00300Object Marker Assembly (Type 3) 71     EACH85.006,035.0095.006,745.0085.006,035.00
0069729-19-00300Dead End Road Installations (Type C) 60     EACH850.0051,000.00925.0055,500.00850.0051,000.00
0070731-02-00100Reflectorized Raised Pavement Markers 2,215     EACH6.0013,290.004.509,967.506.5014,397.50
0071732-01-01040Plastic Pavement Striping (8" Width) (Thermoplastic 90 mil) 744     LNFT3.002,232.003.402,529.603.002,232.00
0072732-01-01080Plastic Pavement Striping (24" Width) (Thermoplastic 90 mil) 969     LNFT12.0011,628.0013.5013,081.5012.0011,628.00
0073732-01-02080Plastic Pavement Striping (24" Width) (Thermoplastic 125 mil) 120     LNFT12.001,440.0013.501,620.0013.001,560.00
0074732-01-05200Plastic Pavement Striping (Dotted Line)(8" W)(2' L)(Thermo 125 mil) 866     LNFT3.002,598.003.252,814.503.002,598.00
0075732-02-02000Plastic Pavement Striping (Solid Line) (4" Width) (Thermoplastic 90 mil) 25.007 MILE3,650.0091,275.554,600.00115,032.204,000.00100,028.00
0076732-03-02000Plastic Pavement Striping (Broken Line) (4" Width) (Thermoplastic 90 mil) 5.064 MILE1,350.006,836.401,000.005,064.001,500.007,596.00
0077732-05-00100Removal of Existing Markings 0.081 MILE8,500.00688.508,500.00688.5010,000.00810.00
0078735-01-00100Mailboxes 369     EACH20.007,380.0021.007,749.0020.007,380.00
0079735-02-00100Mailbox Supports (Single) 283     EACH250.0070,750.00255.0072,165.00250.0070,750.00
0080735-03-00100Mailbox Supports (Double) 43     EACH350.0015,050.00365.0015,695.00350.0015,050.00
0081736-01-00100Trenching and Backfilling 10     LNFT13.00130.0020.00200.0012.57125.70
0082736-09-00100Loop Detector 224     LNFT41.009,184.0045.0010,080.0040.479,065.28
0083736-11-00050Conduit (1/2" HDPE, Schedule 80) 10     LNFT10.00100.0010.00100.009.4794.70
0084740-01-00100Construction Layout 1     LUMP40,000.0040,000.0050,000.0050,000.00140,000.00140,000.00
0085NS-500-00340Saw Cutting Asphalt Concrete Pavement 123,598     INLF0.011,235.980.4555,619.100.2530,899.50
0086NS-600-00220Saw Cutting Portland Cement Concrete Pavement 7,803     INLF2.0015,606.000.856,632.552.0015,606.00
0087NS-602-00001Milling Concrete Pavement 1,182     SQYD22.0026,004.0020.0023,640.0010.0011,820.00
0088NS-700-00840Impact Attenuator (Reusable, Test Level 3) 2     EACH36,500.0073,000.0040,000.0080,000.0036,500.0073,000.00
0089NS-719-00002Tree Trimming 1     LUMP16,500.0016,500.0065,000.0065,000.0018,875.0018,875.00
0090NS-DEV-50241Flexible Pavement High Friction Surface Treatment 5,360     SQYD32.30173,128.0035.00187,600.0038.00203,680.00
           
  CONTRACTOR TOTAL   8,549,962.99 8,944,016.85 10,603,867.57